The Nuclear Decommissioning Authority’s management of the Magnox contract
Closed
What the inquiry looked at
“In 2017 the NAO reported on the Nuclear Decommissioning Authority’s (NDA) failed 14-year, £6.2bn contract to decommission 12 Magnox nuclear energy sites, following a 2016 High Court ruling that the contract had been wrongly awarded. In March 2017, the NDA decided, based on legal advice, to terminate the 14 year contract it had awarded to the Cavendish Fluor Partnership (CFP) nine years early due to a “significant mismatch” between the work specified in the tendered contract and the work that needed to be done. The failed procurement had cost the taxpayer more than £122 million by the time it was announced that it was to be terminated, with the NDA being sued by one of the other bidders for the failed procurement, and forced to agree legal settlements totalling £97.3 million. In August 2017, the NDA agreed a renegotiated contract with CFP. This covered the five-year period from the start of the Magnox contract in September 2014 to the end of the notice period on 31 August 2019. Now a new NAO report follows up on how the NDA has managed this new contract to decommission the Magnox nuclear sites. It shows the NDA successfully negotiated a revised contract with CFP, avoided further litigation and succeeded in maintaining a working relationship with its supplier that led to the completion of £2.72 billion of decommissioning work before the contract ended in August 2019, reducing the degree of hazard on the Magnox sites. However, the NDA were in a weak bargaining position and in renegotiating the contract, agreed to pay a premium of £20 million to negotiate its early exit from the contract and incentivise a smooth handover of sites without further legal challenge. The NDA now estimates that the cost of putting Magnox sites into a safe state has increased, and billions of pounds of uncertainty remains around the final cost, with current estimates ranging from £6.9 billion to £8.7 billion. The Committee will follow up its 2018 report on the letting of the Magnox contract, which was highly critical of the NDA’s understanding of the state of its nuclear sites and the commercial capability of the NDA’s executive team, with questions to senior officials from the Department for BEIS and the NDA. If you have evidence on these issues, please submit it here by Monday 28 September 2020.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The cost of the long-term liability to decommission the UK’s civil nuclear sites now stands at £132 billion, though by its nature this estimate is inherently uncertain. Even the cost to take the Magnox sites to the care and maintenance stage of the decommissioning process is highly uncertain, with the Nuclear Decommissioning Authority (NDA)
currently estimating that it will cost anything from £6.9 billion to £8.7 billion. The timetable for completing this work is similarly uncertain, with a current estimate of anything from 12 to 15 years. Past experience tells us that these estimates could increase further. Efforts to produce a reliable estimate are made more difficult by the historical legacy of decommissioning being an afterthought when the nuclear industry was established, and poor records of what hazardous materials are on the sites. In this context, the NDA faces a considerable challenge to produce a reliable cost estimate.
However, lack of knowledge about the sites was a significant factor in the failure of the Magnox procurement and original contract, which seriously damaged the NDA’s reputation and has now cost the taxpayer in excess of £140 million, and it continues to be a major barrier to making progress. A further barrier is developing sufficient skills and capacity to decommission sites efficiently. That said, the UK nuclear industry possesses valuable technical skills and new technologies that could be better exploited to the benefit of the UK economy. The NDA also holds substantial assets in terms of land and employment opportunities that could be used to serve local communities.
The Department for Business, Energy & Industrial Strategy recognises that its oversight of the NDA has been weak in the past and we welcome the steps it is taking to provide stronger oversight and improved governance. Implementing the recommendations of the Holliday inquiry into the Magnox contract and the Department’s ‘Tailored Review’
of the role of the NDA will be critical and the publication of these reports cannot come soon enough. We welcome the Department and the NDA’s commitments to improve performance over the next 10 years. We also look forward to reviewing the latest quarterly performance reports which the Department has offered to send us, and note there is an enhanced commercial assurance review to consider all future commercial decisions. We will hold the Department and the NDA to account for their progress in improving the transparency of the nuclear industry and making a success of the new delivery and governance approach.
What the government said
The government responded on 25 March 2021.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 18 September 2020 to 26 October 2021.
- Oral evidence 5 Oct 2020
- Report 27 Nov 2020
- Government response 25 Mar 2021
- Correspondence 3 letters
What it recommended 8 recommendations · 10 conclusions
2The uncertainty affecting the Magnox sites reflects a wider uncertainty about the costs and timetable...
3A shortage of the right skills within the Nuclear Decommissioning Authority and across the nuclear...
4For the new delivery model to work, it will be vital that the Department exercises...
5The Nuclear Decommissioning Authority is not doing enough to exploit its various assets, either for...
6Public accountability is hindered by a lack of transparency about the scale and nature of...
1On the basis of a report by the Comptroller and Auditor General, we took evidence...
7An informed understanding of the sites is important to develop reliable estimates of the potential...
8There is also an opportunity to save taxpayers’ money by accelerating the programme to create...
9While the cost of decommissioning represents a substantial liability for the UK taxpayer, the NDA...
10The NDA told us about some notable achievements in relation to the decommissioning of the...
11The NDA owns and occupies substantial amounts of land that could be returned to communities...
12In our 2018 report on the Magnox contract we identified that lack of commercial capability—including...
13The Department and the NDA pointed to the increasing importance of developing skills across the...
14The Department acknowledged the improvements which the NDA has made in developing its own skills...
15In September 2019, the NDA’s Magnox contract with CFP ended following a two- year run...
16We asked the Department if it believed it now had sufficient oversight and governance arrangements...
17We asked the Department about the progress of the Holliday inquiry into the failure of...
18The public is not fully aware of the challenges of nuclear decommissioning and given past...
Evidence
Oral evidence sessions 1
- 5 Oct 2020NDA’s management of the Magnox contract3 witnesses, listed belowparliament.uk ↗
Who gave evidence 3 witnesses
- David PeattieGroup Chief Executive Officer, Nuclear Decommissioning Authority
- Kate EllisCommercial Director, Nuclear Decommissioning Authority
- Sarah MunbyPermanent Secretary, Department for Business, Energy and Industrial Strategy
Correspondence 3 letters
- 26 Oct 2021Correspondence from David Peattie, Group Chief Executive Officer, NDA, re PAC outstanding recommendations responses, dated 11 October 2021
- 10 Sep 2021Correspondence from Sarah Munby, Permanent Secretary, Department for Business, Energy & Industrial Strategy, re Government response to the Magnox Inquiry and the BEIS Departmental Review into the NDA, dated 20 July 2021
- 19 May 2021Correspondence from Sarah Healey, Permanent Secretary, Department for Digital, Culture, Media and Sport, re Update on the implementation of Public Accounts Committee recommendations, 4 May 2021