Progress in remediating dangerous cladding
Closed
What the inquiry looked at
“After the Grenfell tower block fire tragedy that killed 71 people the Government established the Building Safety Programme, to “ensure that residents of high-rise residential buildings are safe, and feel safe from the risk of fire”. The Grenfell Inquiry said it was essential that similar cladding was removed from the exterior of high-rise buildings “as quickly as possible”. In May 2018 MHCLG made £400 million available for the remediation of dangerous cladding from high-rise flats in the social housing sector, and in May 2019 announced a further £200 million for the remediation of equivalent buildings in the private housing sector. Nearly three years later, the NAO report into remediating dangerous cladding on high-rise buildings finds that only about one third of the buildings which fit the specification for the work - 18 metres and above with unsafe “aluminium composite material” (ACM) cladding systems - had been fully remediated, leaving 307 of the total 456 where remediation was not yet finished, and work has not yet begun on 167 of those. The original deadline for completing all these buildings was this month, June 2020. Not all buildings with dangerous ACM cladding fall within scope of the government’s existing funding schemes for the social and private housing sectors, but the Department’s own Independent Expert Advisory Panel has advised that the most dangerous forms of ACM cladding are unsafe on buildings of any height, and that risks are increased in buildings with elderly and vulnerable residents. The Department now estimates that all buildings within the scope of its funding will now be remediated by mid-2022, but this new deadline does not take account of the impacts of COVID-19: there are early signs that the epidemic has slowed the pace of remediation, with up to 60% of projects that were under way paused by April 2020. The pace of remediation has been slowest in the private residential sector, with only 13.5% of private sector residential buildings fixed: by the end of April 2020, the Department had paid out £1.42 million (0.7%) from the £200 million private sector fund compared to £133 million (33.3%) from the £400 million social sector fund. It has been difficult to identify those legally responsible for private buildings, and they have “required more support than was expected”. The owners of 84 private sector residential buildings have committed to fund remediation, with a further 23 self-funded through warranty claims. The Government expects to pay for 94 projects out of 208 in the private sector, where the developer or building owner has not agreed to fund remediation themselves. Seven buildings have not agreed a funding route. In the social sector, the Department has committed to fund 139 out of 154 residential buildings. In March 2020 the Department announced a further £1 billion funding for the remediation of other unsafe cladding, not ACM, on high-rise buildings in the social and private residential sectors. The NAO reports that administration of this new scheme may present significant challenges, given the issues with the existing fund of around half the size. On Monday 6 July the Committee will question officials from the Ministry for Housing, Communities and Local Government on the Government’s progress on remediating dangerous cladding. If you have evidence on the questions and issues raised in this report, please submit it here by 5.30pm on Thursday 2 July.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
Three years after the Grenfell Tower disaster in which 72 people lost their lives, only a third (155 out of 455) of high-rise buildings with Grenfell-style flammable cladding had had their cladding replaced with a safe alternative. Progress has been unacceptably slow, a conclusion accepted by the Ministry of Housing, Communities and Local Government (the Department). The Department has missed its target badly for Grenfell-style cladding to be removed from all high-rise blocks by June 2020, other than in a few exceptional cases. The Department’s new target is for works on the remaining high-rise blocks to be completed by the end of 2021. It is imperative that the new deadline be met.
Most residents in blocks with dangerous cladding face exorbitant costs of funding interim safety measures (such as ‘waking watches’) while waiting for the cladding to be removed. Leaseholders have been trapped in this situation, unable to sell their flats which are worth nothing. This accentuates the urgent need for the replacement of dangerous cladding to be accelerated. Many residents have reported worsening mental health as a result of worries about their safety, and the life-changing bills they face for remediation works.
While the Department has made £600 million available to fund the replacement of aluminium composite material (ACM) cladding (as used on Grenfell) on buildings above 18 metres, by April 2020 it had only paid out £134 million, due in part to difficulties in working with private building owners. By April 2020, cladding had been replaced on two-thirds of student accommodation blocks and nearly half of the social housing buildings, compared to only 13.5% of private sector residential buildings.
In March 2020 the Department announced that a further £1 billion would be made available to fund the replacement of other forms of dangerous cladding on high-rise buildings, although it estimates this would meet only around a third of the total costs.
It has no plans to support residents or social landlords to meet the costs of replacing dangerous cladding in buildings below 18 metres, of providing ‘waking watches’, or of fixing other serious defects brought to light by post-Grenfell inspections. Although the Department recognises that care homes would be at additional risk due to the difficulties in evacuating residents in the event of a fire, it has no knowledge of whether any of the 40,000 care homes, sheltered housing and hospitals below 18 metres in height are clad with unsafe material.
The Grenfell disaster has exposed serious shortcomings in the construction industry.
But while the Department is clear that building owners are responsible for the safety of their buildings, it is the Department which is responsible for the building regulation system, which it accepts has been “not fit for purpose” for many years. These failings have left a legacy of problems for the Department to address which extend beyond the immediate need to remove dangerous cladding. A lack of skills, capacity, and access to insurance is hampering efforts to improve or simply assure the structural safety of apartment blocks, and thereby to restore the confidence of buyers and mortgage lenders in sales of flats across the country. Leaseholders are in limbo and facing huge bills because of a system-wide failure to protect purchasers.
What the government said
The government responded on 18 November 2020. The deadline was 16 November 2020.
The government agrees with most of the Committee's recommendations on remediating dangerous cladding, but disagrees with two, on publishing an impact assessment and on identifying care homes below 18 metres with dangerous cladding.
- On enforcement, the government agrees, noting that the Building Safety Regulator, in shadow form, "does not yet have enforcement powers (which are subject to legislation)". Ministers have urged owners yet to start remediation to begin works "by the end of 2020 or expect to face enforcement actions".
- On transparency, the government agrees and states its "intention is to include updates on projected completion dates" for high-rise buildings with ACM cladding in the monthly data release "by February 2021".
- The government disagrees with publishing the impact assessment within three months, saying it is "unable to implement" this "under the timeframe proposed" because applications for non-ACM cladding removal are "still being processed". It will publish updates on Building Safety Fund data as the scheme progresses.
- On care homes below 18 metres, the government disagrees, noting that care homes are covered by the Regulatory Reform (Fire Safety) Order 2005. It will write to the Committee "in the spring of 2021" on data collection for 11-18 metre residential buildings.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 15 June 2020 to 14 June 2021. The dashed mark is the deadline Parliament records for the government's response.
- Oral evidence 6 Jul 2020
- Report 16 Sep 2020
- Government response 18 Nov 2020
- Correspondence 4 letters
What it recommended 13 recommendations · 12 conclusions
2The Department is not fully funding the replacement of forms of dangerous cladding which are...
3The Department has no knowledge of how many care homes below 18 metres in height...
4The Department has not done enough to address spiralling insurance costs and ‘nil’ mortgage valuations.
5There is a shortage of specialist skills to support the remediation of buildings with unsafe...
1On the basis of a report by the Comptroller and Auditor General, we took evidence...
6In a review commissioned jointly by the Department and the Home Office in the wake...
7Aluminium composite material cladding is not the only form of flammable cladding that has prompted...
8The Department told us it estimated the costs of replacing this cladding as between £3...
9The Department intends for the £1 billion Building Safety Fund for non-ACM cladding to be...
10The Department said it was unacceptable that buildings of any height had unsafe cladding, not...
11One category of buildings below 18 metres that might present increased risks are care homes.
12The Department understands there are around 40,000 care homes, sheltered homes, and hospitals (i.e.
13The number of residents living in buildings with unsafe cladding is not clear.
14Living in unsafe buildings has clearly impacted residents’ mental well-being.
15Private leaseholders’ emotional strain has been compounded by rising costs passed on to them by...
16Additional costs may also arrive through wider fire safety issues discovered during remediation works and...
17We asked the Department if it knew of any impact to social sector rents as...
18Leaseholders in blocks with dangerous cladding have had their properties valued nil, making it impossible...
19However, the process has not been working as intended.
20In response to our concern that leaseholders are receiving nil valuations, the Department told us...
21We made it clear to the Department that professional indemnity insurance has been regularly brought...
22While leaseholders have been unable to move or remortgage, some have seen their insurances premiums...
23The National Audit Office found that there has been a shortage of skills or personnel...
24We raised concerns with the Department about the ability to complete remediation work by the...
25The demand for resources to inspect and remediate buildings with safety concerns is already high...
Evidence
Oral evidence sessions 1
- 6 Jul 2020Progress in remediating dangerous cladding2 witnesses, listed belowparliament.uk ↗
Who gave evidence 2 witnesses
- Jeremy PocklingtonPermanent Secretary, Ministry of Housing, Communities and Local Government
- Neil 0'ConnorDirector, Building Safety Programme, Ministry of Housing, Communities and Local Government
Correspondence 4 letters
- 14 Jun 2021Correspondence from Jeremy Pocklington CB, Permanent Secretary Ministry of Housing, Communities & Local Government, re In response to the Public Accounts Committee’s 16th Report of Session 2019-2021 ‘Progress in remediating dangerous cladding’, dated 7 June 2021
- 1 Mar 2021Correspondence from Jeremy Pocklington, Permanent Secretary, Ministry for Housing, Communities and Local Government, re Progress in remediating dangerous cladding, 24 February 2021
- 26 Jan 2021Correspondence from Jeremy Pocklington, Permanent Secretary, Ministry for Housing, Communities and Local Government, re Remediation of dangerous cladding, dated 18 January 2021
- 13 Jan 2021Correspondence from Jeremy Pocklington, Permanent Secretary, Ministry for Housing, Communities and Local Government, re Building Safety Fund – Risks of committing all £1bn by end of March 2021, dated 22 December 2020