Defence Nuclear Infrastructure
Closed
What the inquiry looked at
“The Ministry of Defence currently has a number of large and complex construction projects for facilities at nuclear-regulated sites. In January 2020 the NAO published a report examining the building or replacing of three nuclear-regulated sites – with a current value of £2.5bn. The report finds that the three projects experienced problems in their earlier and riskier stages, with a cumulative £1.35bn cost increase and delays of between 1.7 and 6.3 years. The report also expresses disappointment that the challenges affecting these projects are not unique, and have been experienced by the Ministry of Defence for decades. The Committee will ask officials from the Ministry of Defence what lessons it has learnt as it completes these projects, and how the Government will be revising the projects’ commercial, regulatory and governance arrangements to ensure value for money for the taxpayer.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The Ministry of Defence (the Department) maintains a submarine-based nuclear deterrent, which relies on a network of programmes, equipment and people, including specialised infrastructure. Poor management of three on-going critical infrastructure projects on nuclear-regulated sites has contributed to a combined cost increase of £1.35 billion and delays of between 1.7 and 6.3 years. Each project suffered significant problems in its early stages and the Department said it immensely regretted the amount of taxpayers’ money lost. It accepts that poor contracting had made it difficult to incentivise better performance from contractors, and that it had not engaged effectively with the nuclear regulatory bodies. It also describes its arrangements for the Nuclear Enterprise in the past as ‘fragmented and balkanised’, with insufficient recognition of the interdependencies between projects.
Since 2016, the Department has negotiated some changes to the contract at one of the three programmes—MENSA—to reduce its financial risk exposure. It has also made some improvements to the oversight of the nuclear enterprise, including the infrastructure projects, through creation of the Defence Nuclear Organisation and the Submarine Delivery Agency. As a result, the Department considers it now has a better understanding and control of the programmes. It has also worked to develop better relationships with the regulators to ensure there is a more effective discussion about the balance between risk and value for money, although it is too early to assess whether all these reforms have been effective. The Department acknowledges that it still has shortages of the specialist skills it needs.
What the government said
The government responded on 21 October 2020. The deadline was 13 July 2020.
The Government states that it "agrees with the Committee's recommendation" on each of the six recommendations, and sets target implementation dates between November 2020 and June 2021.
- On approvals and risk, it says the recommendation is implemented, citing Project MAID, which has replaced the Initial Gate and Main Gate system with the 3-stage model laid out in the Treasury's Green Book.
- It will update the Committee on use of the Single Source Contract Regulations, and on corporate memory and skills, "within the December 2020 report to Parliament on the Dreadnought programme".
- On ring-fencing the nuclear budget, it says discussions with HM Treasury are underway to review the funding model, with "details" to be shared "once discussions have concluded".
- On ownership of nuclear regulated sites, it says work on the detailed assessment is underway and that "the report will be issued by 31 December 2020".
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 10 February 2020 to 13 July 2021. The dashed mark is the deadline Parliament records for the government's response.
- Report 13 May 2020
- Government response 21 Oct 2020
- Correspondence 3 letters
What it recommended 0 recommendations · 25 conclusions
1The Department’s nuclear infrastructure projects have suffered from major cost increases and delays.
2We understand the need to make early progress given the interdependencies between the infrastructure programmes...
3The Department’s previous contracts have been poorly designed, which has left the taxpayer to shoulder...
4The contracts for the three infrastructure projects did not allow the Department to share the...
5The current funding regime does not work for the Nuclear Enterprise due to its uniquely...
6The Department finds that the demands of Treasury annularity expectations and managing to a 31...
7The Department has belatedly learned through experience the importance of strong relationships between it, the...
8More recently, the Department says there has been improved dialogue via senior leadership groups which...
9It is unacceptable that the Department in other areas has repeated past mistakes, and has...
10The failure to learn from the past underlines the importance of the Department maintaining a...
11Ultimately, the Department retains the risk associated with these programmes and must manage them itself,...
12On whether it is considering taking on the risk directly and then contracting out the...
13The contracts the Department prepared did not allow it to share the financial risk, which...
14The Department accepted the National Audit Office’s criticism that its contracts had not been well...
15In addition, around £37 billion of contracts—some 252 in total—are now subject to the Single...
16Because of the risks associated with defence and civil nuclear sites and the handling of...
17Regulatory arrangements for nuclear sites involve the Department, the site operators and one or both...
18The Department said that the importance of improved relationships with the regulator was one of...
19The Department considered that the more the different parties worked together, the greater likelihood that...
20We asked the Department whether the current regulatory model was the best way of working.
21Many of the mistakes made on these infrastructure projects were similar to those on which...
22The failure to learn from the past underlines the importance of maintaining a robust corporate...
23Despite this, there are shortages of personnel with crucial specialist skills.
24The Department uses eight nuclear-regulated sites.
25We asked the Department about the ownership of intellectual property where it is not the...
Correspondence 3 letters
- 13 Jul 2021Correspondence from David Williams, Permanent Secretary, Ministry of Defence, re Following the publication of Second Report of Session, 2019-2021 on Defence Nuclear Infrastructure, 30 June 2021
- 13 Jan 2021Correspondence from Sir Stephen Lovegrove, Permanent Secretary, Ministry of Defence, re Following the publication of Second Report of Session, 2019-2021 on Defence Nuclear Infrastructure, dated 17 December 2020
- 13 Jan 2021Correspondence from Sir Stephen Lovegrove, permanent secretary, Ministry of Defence, re PAC hearing – defence nuclear infrastructure, dated 04 January 2021
Meetings and visits 1
- 11 Mar 2020Defence nuclear infrastructureFormal meeting