High Speed 2: Spring 2020 update
Closed
What the inquiry looked at
“The National Audit Office published its progress update on High Speed 2 in January (its fourth report on the project). The report finds that optimistic estimates have been used to set budgets and delivery dates for the project. In not fully and openly recognising the programme’s risks from the outset, the report finds that the Department and HS2 Ltd have not adequately managed the risks to value for money. The report also welcomes the recent increased realism on the estimated cost and schedule for the programme. The Committee will ask officials from HS2 Ltd and the Department of Transport about the Government’s current vision for the project, the challenges in getting Phase One into construction, and what it is being done to manage the cost and schedule estimates for Phase Two of the project.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The High Speed Two programme has gone badly off-course and is now estimated to cost up to £88 billion, significantly more than the original budget of £55.7 billion (both figures are 2015 prices). We are unconvinced that there will not be further cost increases, such as those we have seen in Crossrail and many other programmes, especially given that the route and forecast cost of the northern sections of the proposed railway is still very uncertain and will remain so for years to come. Passengers will not see the benefits from Phase One between London and the West Midlands until 2029 at the earliest, compared to the original plan of 2026, with passengers in the North having to wait much longer while the Government decides the future of the northern sections of the railway.
As well as cost increases and delays, public confidence in the programme has been undermined. At best, the Department for Transport’s (the Department’s) previous evidence to the Committee has been less than clear. The Department withheld information from us which would have given a clearer and more accurate picture of the budget and schedule pressures the project was facing. The Department and High Speed Two Ltd (HS2 Ltd) seemed to believe that a lack of transparency with Parliament and the public on the problems facing the programme would in some way protect it. With so many peoples’ homes and livelihoods affected by the construction of the railway, there is no justification for the Department and HS2 Ltd having been so opaque about the delays and budget overruns. Now that the Government has given the programme the green light, things must change and there must be much greater transparency in future.
What we have seen about Government’s management of this programme is all too familiar and we remain concerned that lessons from the delivery of other major projects are still not being learned. To protect taxpayers’ money there should be far greater focus on fostering and embedding a culture that values learning from experience to do things even better and avoid repeating the same mistakes. We will regularly examine how this programme is progressing and what the Department and HS2 Ltd are doing to address our recommendations for improvement.
What the government said
The government responded on 21 October 2020. The deadline was 17 July 2020.
The Government states that it agrees with the Committee's recommendations in the report, giving target implementation dates between August and November 2020 for several of them.
- On reporting to Parliament, the Department confirms that six-monthly reports on delivery, including cost, schedule and risks, will be published, starting in Autumn 2020 for April to September 2020, with the second in Spring 2021.
- On Accounting Officer assessments, the Department states that it "will publish summaries on GOV.UK" for projects in the Government's Major Projects Portfolio, including High Speed 2, "in line with this guidance" on balancing transparency with confidentiality.
- On Euston, the Department has commissioned a study with the objective of selecting a design and delivery strategy "this Autumn", and says it will update the Committee on its plan within six months of the report's publication.
- On lessons learned, the Department says it "will write to the committee in the coming months", with a target implementation date of November 2020.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 10 February 2020 to its close on 4 November 2020. The dashed mark is the deadline Parliament records for the government's response.
- Oral evidence 4 Mar 2020
- Report 17 May 2020
- Government response 21 Oct 2020
- Correspondence 1 May 2020
What it recommended 0 recommendations · 28 conclusions
1The Department and HS2 Ltd’s lack of transparency has undermined public confidence in the programme.
2The Department failed to provide Parliament with clear warning that the programme was going off-course...
3Having raised concerns in the past, we are not yet convinced that the Department and...
4Several years into the programme, we are concerned by the huge uncertainty remaining with the...
5The Department and HS2 Ltd did not understand the consequences of changes made during scrutiny...
6We are concerned, given the scale of the programme and its future impact on the...
7The Department did not convince us that it was making sufficient and meaningful changes to...
8HM Treasury guidance states that, in addition to producing an Accounting Officer assessment for projects...
9We asked the Department whether, considering the cost overruns, it had sought a Ministerial direction...
10The Department explained that it would have been premature to seek a direction on the...
11The Department did not share summaries of any of the four Accounting Officer assessments on...
12In 2013, the previous Committee concluded that the Department faced a challenge in making sure...
13We heard from HS2 Ltd that it had recently concluded a two-year programme that considered...
14The Crossrail programme suffered with skills and capability issues during the completion stage.
15We heard from HS2 Ltd that it is using a revised commercial model with its...
16Euston is an important and complex part of the High Speed Two programme and involves...
17Euston station was originally intended to open with the rest of Phase One in 2026,...
18HS2 Ltd stated it had spent around £30 million designing Euston station based on the...
19HS2 Ltd also informed us that there are links between High Speed Two and the...
20The High Speed Two programme is complex and involves many interrelated elements, including land and...
21Phase Two of the HS2 programme provides connections to the existing railway to enable journeys...
22We were interested to hear from the Department whether its criteria for environmental project assurance...
23HS2 Ltd and the Department needed to deposit a hybrid Bill in Parliament to give...
24In light of this, we asked HS2 Ltd how it could assure us that Phase...
25In response to being questioned on how it is learning lessons from major programmes, the...
26The Department told us that there are important lessons to learn from High Speed Two...
27In addition to implementing the Department/IPA report lessons, the Department explained that it has tasked...
28We also asked about what lessons the Department had learned on its approach to skills...
Evidence
Oral evidence sessions 1
- 4 Mar 2020High Speed 2: Spring 2020 update4 witnesses, listed belowparliament.uk ↗
Who gave evidence 4 witnesses
- Bernadette KellyPermanent Secretary, Department for Transport
- Clive MaxwellSecond Permanent Secretary, Department for Energy Security and Net Zero
- Mark ThurstonChief Executive, HS2 Ltd
- Michael BradleyChief Finance Officer, High Speed Two
Correspondence 1 letter
- 1 May 2020Corresp - Letter from Bernadette Kelly regarding progress of HS2 - 200415To committee