Brexit consultancy costs inquiry
Closed
What the inquiry looked at
“Since early 2018, Government departments have used consultants in their preparations for exiting the EU. The Cabinet Office and departments were concerned that they would not be able to make sufficient progress in their EU Exit work because of difficulties in securing the required expertise, particularly in areas such as strategic planning and programme management. In a recent report , the National Audit Office (NAO) have found that by April 2019, departments had spent or agreed to spend £97 million on consultancy. The total maximum value of contracts, which run to February 2020, is £240 million – although the Cabinet Office does not expect that all of this will be used. The NAO investigation also found that departments have not met the standards of transparency expected by government when publishing details of contracts. In fact, publishing basic details for EU Exit consultancy contracts has taken on average 119 days, whereas the Crown Commercial Service normally recommends this information is published within 90 days. The contracts that have been published are significantly redacted. On 12 June at the start of its session on Sale of public land, the Public Accounts Committee will question John Manzoni, head of the Cabinet Office, on how departments are using consultants for EU Exit work and examine the transparency of arrangements. The Committee may also challenge the Cabinet Office on what it is doing to improve its understanding of overall spending on consultancy.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
Departments have made extensive use of consultancy firms in support of their preparations for Brexit, spending at least £97 million by April 2019. Departments have been overly secretive about what the consultants are doing, as they have been before in providing information on other aspects of the Brexit preparations. When departments have published information on consultancy work, usually later than they should have, they have failed to meet the government’s own transparency standards. Departments took too long to publish information on the contracts being let, and some contracts were over-zealously redacted before publication.
While we welcome the Cabinet Office’s establishment of a central call-off framework to help departments access consultants for Brexit work, the Cabinet Office seems overly relaxed that 96% of the work by value has so far gone to just six large companies, despite its own aspirations for more government work to go to small and medium-sized enterprises. Too much of the work procured to date appears to have been focused on “thinking and shaping” rather than getting practical things done. This only compounds our concerns over the speed of preparations for Brexit across Whitehall.
There is a widening gap between the Cabinet Office’s analysis of data on overall spending on consultancy services, not just to support Brexit, and expenditure reported by departments. It appears that different departments are choosing to categorise their spending on consultancy services in different ways. The Cabinet Office’s failure to agree a common definition of “consultancy with departments and get to grips with this long-standing issue threatens its ability to exercise effective control over spending on consultancy and related services.
What the government said
No government response is linked to this report.
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 7 June 2019 to 30 September 2019.
- Oral evidence 12 Jun 2019
- Report 12 Sep 2019
- Correspondence 9 letters
What it recommended 1 recommendation · 15 conclusions
1Departments have again proved overly secretive with their preparations for Brexit, taking far too long...
2The skills accessed through the Cabinet Office’s consultancy call-off arrangement suggest departments had been more...
3We are concerned that the bulk of Brexit consultancy contracts by value have been awarded...
4There is a longstanding and widening discrepancy between Cabinet Office and departmental data on consultancy...
5The Cabinet Office and other departments have failed to follow the guidance on publishing contracts...
6Where departments have published details of contracts, they have still often failed to meet expected...
7After the evidence session, the Cabinet Office submitted further evidence, pointing to revisions to the...
8Until the Committee raised it with the Cabinet Office, there were also key components of...
9We have reported previously on the shortage of information in the public domain about what...
10In February 2018, we reported that it would be critical that the civil service had...
11In April 2018, the Cabinet Office set up a framework to provide departments with rapid...
12We questioned why consultants had been more used often to support thinking and shaping, which...
13In 2016, we found that the Cabinet Office’s procurement agreements for consultancy tended to benefit...
14Large consultancy firms have since taken an overwhelming share of the consultancy work in support...
15We questioned the Cabinet Office on a widening disparity between its analysis of overall spending...
16We asked the Cabinet Office whether departments were under-reporting their expenditure on consultancy services.
Evidence
Oral evidence sessions 1
- 12 Jun 2019No witnesses recordedparliament.uk ↗
Correspondence 9 letters
- 30 Sep 2019Letter from Sir Stephen Lovegrove to the Chair on MOD's contracts with CAPITA, 23 September 2019To committee
- 23 Jul 2019Letter from John Manzoni to Chair in response to Chair's letter of 2 July - dated 10 July 2019To committee
- 23 Jul 2019Letter from Cabinet Office to Chair regarding Brexit consultancy contracts - dated 15 July 2019To committee
- 23 Jul 2019Letter from Chair to John Manzoni, following up from session on Brexit consultancy costs on 12 June - dated 18 June 2019To committee
- 23 Jul 2019Letter from Chair to John Manzoni, following up on Brexit consultancy costs - dated 2 July 2019To committee
- 23 Jul 2019Letter from Chair to John Manzoni, regarding Brexit consultancy contracts - dated 15 July 2019To committee
- 15 Jul 2019Letter from Home Office to Chair, regarding Brexit consultancy contracts - dated 10 July 2019To committee
- 8 Jul 2019EU Exit consultancy contracts Annex A – Cabinet Office
- 2 Jul 2019Letter from Cabinet Office to Chair, regarding EU Exit consultancy contracts - dated 24 June 2019To committee