Transport Infrastructure in the South West inquiry
Closed
What the inquiry looked at
“In December 2014, the Department for Transport introduced a new regime of 5-yearly road investment strategies to improve the management of England’s strategic road network. As part of the first Road Investment Strategy, the Department announced plans to upgrade the A303/A358 road corridor to the South West by 2029 to improve road connectivity. This includes the £1.7 billion (£1.9 billion including VAT) project to upgrade the road between Amesbury and Berwick Down and a tunnel (the Stonehenge tunnel) under the World Heritage Site. The NAO’s recent report found that the financial return on investment for the Stonehenge tunnel is low for road projects: offering a return of £1.15 for every £1 spent. In February 2019, we raised concerns about how HM Treasury and the Department planned to fund the Stonehenge tunnel project, following the decision not to sign future PFI/PF2 deals. We will be asking the Department and Highways England about the Stonehenge tunnel project, and other projects along the A303/A358 corridor, seeking answers on how they will be funded. The Committee will also be using this evidence session to raise a number of other issues with the Department. The Committee will be questioning officials on transport infrastructure in the South West and in particular will be asking for an update on the Great Western railway modernisation programme and intends to cover the A417 roundabout in the Cotswolds. The session will also provide an opportunity for Members to question the Department about its decision to award contracts to provide additional freight capacity on ferry services. The Committee has questioned the Department on this before in February but this will provide an opportunity to consider the matter in light of the out-of-court settlement with Eurotunnel and the NAO’s memorandum on the matter which was published earlier this month.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
After several failed attempts, the government believes that it now has a Stonehenge tunnel scheme that is affordable, deliverable and has the support of heritage and environmental bodies. However, decisions on how to fund the project are on the critical path for the planned opening date of 2026 and are now at the mercy of the much-awaited Spending Review. Delaying those decisions further will jeopardise the opening date.
The Stonehenge tunnel project, expected to cost around £1.7 billion (excluding VAT), is a key part of the government’s plans for the A303 road corridor. The Department and Highways England expect it to deliver significant heritage benefits as well as easing road congestion. Yet the Department and Highways England do not yet have a clear idea of what improvements they are expecting to see at the World Heritage Site and the surrounding area. The Department and Highways England aspire to upgrading the whole A303 road corridor to dual carriageway standard to improve connectivity and support economic growth in the South West. However, it is not yet certain that all eight road improvement projects needed to do this will go ahead. So far, the Department has only committed to starting three out of the eight projects required along the route.
With improvements to only some parts of the road corridor, traffic congestion is likely to be eased at some points but pushed to other sections of the road. Similarly, the contribution of any one project to enabling growth in jobs and housing is undermined if neighbouring projects to provide a free-flowing and reliable road connection are not given the go-ahead.
It will be extremely challenging to deliver the South West road improvements to cost and time, and the Department does not have a good track record in delivering major projects. The region needs a properly integrated transport strategy, going beyond road to incorporate rail, sea and air, but the bodies tasked with delivering this strategy are still very immature.
What the government said
No government response is linked to this report.
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 5 June 2019 to 9 March 2020.
- Oral evidence 5 Jun 2019
- Report 3 Jul 2019
- Correspondence 2 letters
What it recommended 3 recommendations · 32 conclusions
1If uncertainty about funding is not resolved before 2020, the timetable and viability of Stonehenge...
2It will be extremely challenging to deliver the South West road improvements to cost and...
3The Department and Highways England do not yet have a clear picture of what improvements...
4The Department and Highways England’s piecemeal approach to upgrading the A303/A358 makes it more difficult...
5The sub-national transport bodies in the South West are not yet mature enough to develop...
6While the government is committed to building a new sea wall at Dawlish and other...
7Highways England told us that it was funded this financial year with all the money...
8The Spending Review has already been delayed, and we drew attention to the Chief Secretary...
9As stated earlier, the expected range of costs for the Stonehenge tunnel project is £1.5...
10The Department told us it had learned from experience on other projects that it was...
11On skills and capacity, Highways England said that, in the four years since Highways England...
12On cost, Highways England said that the upper end of the range, £2.4 billion was...
13The Department added a slight note of caution, commenting that while “the scheme is well...
14In October 2018, Highways England applied to the Planning Inspectorate for development consent for the...
15The A358 project is one of the others committed to within the first Road Investment...
16The first A358 option put out to public consultation had an estimated cost of £251...
17We drew attention to concerns highlighted by Ian Liddell-Grainger MP about the vague figures quoted...
18The high cost of building a tunnel, compared with widening or moving the road, means...
19Highways England told us that in its view the transport and heritage benefits were indivisible,...
20We asked about the Department supporting Highways England to work with other government departments, local...
21We asked whether the Department and Highways England had come up with any innovative schemes...
22The Department and Highways England have chosen not to produce an overarching programme-level business case...
23The Department confirmed that it had no formal commitment to the remaining five projects and...
24The Department explained that a programme-level assessment done earlier had added something like £273 million...
25We challenged the Department and Highways England further on the risk of ending up with...
26In February 2019 the Department published Investing in the South West.47 We noted that the...
27The Department described how there were now two new sub-national transport bodies—Peninsula Transport and Western...
28The Department further explained that the two sub-national transport bodies were collections of elected members...
29Autumn and winter 2013 and 2014 saw the wettest period in the south of England...
30We asked about longer-term resilience, in particular the project to build a new sea wall...
31The Department told us it understood that Network Rail was announcing a consultation about treatment...
32We asked about the status of other parts of the project in addition to the...
33The Department wrote to us after the evidence session providing further information, which included that:...
34The report deals with the 8 projects along the A303/A358 corridor to improve the road...
35Gross Domestic Product per capita is lower in the South West than the UK average.
Evidence
Oral evidence sessions 1
- 5 Jun 2019No witnesses recordedparliament.uk ↗
Correspondence 2 letters
- 9 Mar 2020Correspondence from Jim O’Sullivan, Chief Executive, Highways England regarding Transport Infrastructure in the South West, 17 June 2019
- 18 Jun 2019Letter from Bernadette Kelly to Chair following up to hearing on 5 June regarding Transport Infrastructure in the South West - dated 11 June 2019To committee