Submarine defueling and dismantling inquiry
Closed
What the inquiry looked at
“In 1995, the government took the decision to dispose of its nuclear liabilities, including nuclear submarines. It was agreed that these would be disposed of as soon as was ‘reasonably practicable’. However, since then no nuclear submarines have been dismantled: despite the fact that 20 submarines have been taken out of service since 1980. These decommissioned submarines have incurred £0.5 billion in maintenance and storage costs at the dockyards in Devonport and Rosyth. In June, the National Audit Office reviewed the Ministry of Defence’s progress on submarine disposal and considered the main reason for the delays. The NAO reported that there have been major delays to the MoD’s defueling work which has not progressed since 2004 as facilities were not up to standard. The upgrade of these required facilities has now been delayed by 11 years and will cost £100 million more than expected. The MoD now expects to start defueling in 2023. The MoD’s dismantling project has also encountered major delays and is 15 years behind schedule: costs of this project have now increased from £0.8 billion to £2.4 billion. These delays have led to the MoD incurring even further costs: it spends £30 million a year on maintenance and storage costs, as well as the £24 million it pays a year to Babock International Group plc, the contractor which owns the dockyards at Rosyth and Devonport. On Wednesday 1 May, the Committee will be hearing from senior officials at the MoD, as well as a representative from Babcock to ask what progress the MoD has made against its disposal requirements and what the implications of the delays of this project will be. The Committee will also ask the MoD how it intends to prevent similar problems and delays in future.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The UK retired its 20 legacy submarines in 1980 and the Ministry of Defence’s (the Department) progress in disposing of these submarines has been a serious disappointment. The project has moved at a glacial pace and the 15-year delay has led to extortionate storage and maintenance costs which are now costing the taxpayer £30 million per year. The Department is also looking increasingly likely to find itself without any further storage space by the mid-2020s. The Department is rapidly approaching crisis point and simply cannot afford any further delays, particularly as much of the money currently being spent on the project is not going directly towards either defueling or dismantling. While it has taken the Department 16 years to devise a workable dismantling strategy, it is encouraging to see that progress is now being made and there is finally some momentum behind the project. However, while there is now an agreed policy, we remain sceptical that the ambitious timetable will be met, particularly given how many times this project has been delayed or deprioritised over the years.
It is clear that the commitment to dismantle its first submarine—Swiftsure—by 2023 will not be met and will likely be completed three years after the target date. The scale of the task faced by the Department appears even more challenging given the defence affordability ‘black hole’ which totals at least £7 billion. The Department has some way to go to establish submarine disposal as a routine part of its business.
What the government said
No government response is linked to this report.
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 7 March 2019 to 19 June 2019.
- Oral evidence 1 May 2019
- Report 19 Jun 2019
- Correspondence 2 letters
What it recommended 1 recommendation · 19 conclusions
1The continual failure to progress submarine disposal has created an unacceptable and unnecessary problem for...
2The Department has yet to resolve significant uncertainties affecting the projects that are needed in...
3The Department has repeatedly made decisions on short-term affordability grounds which have increased costs in...
4We remain unconvinced that funds will be available for disposal-related projects, or that the Department...
5The engineering challenge of dismantling and disposing of nuclear submarines provides an opportunity to develop...
6The Department’s ability to achieve value for money depends on managing complex commercial risks and...
7While acknowledging responsibility for past delays, the Department told us it remains committed to the...
8In July 2018, the Department acknowledged that although it had deferred dismantling submarines for affordability...
9To avoid space constraints, the Department needs to restart defueling in 2024, which it admits...
10The Department will not meet its previous commitment to fully dismantle its first submarine in...
11To keep spending within the available funding, the Department has made decisions that have increased...
12Looking ahead, it remains uncertain whether long-term funding will be available to progress submarine disposal.
13The Department faces significant affordability challenges, on which we last reported in February 2019, highlighting...
14Consistent regulatory and safety standards apply across civil and defence nuclear, with the Department working...
15Both the Department and Babcock identified submarine disposal skills shortages as a significant concern.34 The...
16Submarine disposal can be attractive work for engineers given the technical challenges and complexities involved.
17In September 2018, we reported on national skills shortages across nuclear work, recommending that the...
18The Department has a significant and unique relationship with Babcock, which owns the nuclear-licensed sites,...
19To progress submarine defueling, the Department needs to complete challenging commercial negotiations with Babcock by...
20In 2018, the Department had to re-start its procurement for intermediate-level waste transport procurement after...