Select committee inquiry

Crossrail: progress review inquiry

Closed

Public Accounts Committee · Opened 25 February 2019 · Closed 25 February 2019

1 recommendation · 26 conclusions
Inquiry on parliament.uk ↗

What the inquiry looked at

“Crossrail is a major programme to run new, direct rail services between Reading and all passenger terminals of Heathrow Airport at the western ends of the railway, through a new underground section beneath central London to Shenfield in Essex and Abbey Wood in south east London at the eastern ends. The project currently has a total funding envelope of £17.6 billion in its entirety. The Department for Transport (DfT) provides £4.9 billion, Network Rail provides £2.3 billion, and Transport for London and the Greater London Authority (GLA) jointly provide £7.1 billion, with the remainder coming from private sector contributions. The railway was due to open fully by the end of 2018, with works commencing in 2009. The final cost, however, remains uncertain, and there is currently no exact date for when the railway will be fully operational. In August 2018, Crossrail Ltd announced a delay to the project with an estimated opening date in Autumn 2019. In December 2018, the Mayor of London, the Greater London Authority (GLA), and Transport for London (TfL) confirmed an additional financing package with the Government to deliver the final stages of the Crossrail project. Emerging findings by KPMG, which did a review into Crossrail Ltd's finances, show that the likely cost impact of this delay could be between £1.6bn and £2bn. This includes the £300m already contributed by the DfT and TfL in July 2018, which leaves an estimated £1.3bn to £1.7bn to complete the project. Members will use this hearing to review the project’s overall progress, and examine the cost impact of the latest delay , as well as potential future delays.”

The committee's words, from the inquiry page on parliament.uk ↗.

What it found

In the committee's words, from the summary of 92nd Report - Crossrail: progress review ↗

The Crossrail programme aims to deliver a new east-west railway through central London, providing passengers with new train services to improve connections on the existing transport network, reduce journey times and ease congestion. It was supposed to set the standard for delivery of transport programmes, where the skills and knowledge gained from the programme could be exported around the world. Instead, yet again, costs have escalated and delivery dates have turned out to be over-optimistic. New train services were due to start in December 2018 but have been badly delayed. Until a revised opening schedule has been agreed, we are not convinced that new services will start to run in 2020 as now hoped, nor that the additional £2.8 billion of funding provided will be enough.

The Department and Crossrail Limited are unable to fully explain how the programme has been allowed to unravel. Crossrail Limited failed to properly report the position of the programme and risks. Key warning signs were missed or ignored, and Parliament and potential new passengers still do not know the root causes of the delays and significant cost overruns. As the programme progressed, the Department, as a joint sponsor of the programme with Transport for London, failed to ensure that the governance arrangements it had put in place were robust. We are becoming increasingly alarmed at the continual shortcomings our work has highlighted in the Department’s project management and oversight of the railways and we will continue to look closely at progress with this programme. We are also concerned about the clarity of message we have received from the Department throughout the programme. We have, previously, questioned the Department on the additional funding announced in July 2018 to cope with cost increases, only for further cost escalation and more funding to be agreed at a later date. This is symptomatic of how the costs of this project have been allowed to spiral out of control whilst question marks remain around its completion and when new train services will start to run.

What the government said

No government response is linked to this report.

How the inquiry ran

Each dot is a dated item listed on this page, from the inquiry's opening on 25 February 2019 to 30 September 2019.

  1. Oral evidence 6 Mar 2019
  2. Report 3 Apr 2019
  3. Correspondence 4 letters

What it recommended 1 recommendation · 26 conclusions

1The Department for Transport, Transport for London and Crossrail Limited’s fixation on a delivery deadline...
Concluded (the committee's words)
The Department for Transport, Transport for London and Crossrail Limited’s fixation on a delivery deadline of December 2018 led to warning signs that the programme was in trouble being missed or ignored. A key, politically important, milestone for the programme was train services starting through the central section of the line in December 2018. The pressure on, and determination within, those delivering the programme to meet this deadline led to an overriding culture of over-optimism when the programme began to slip in 2016 and failings identified then were not addressed as they should have been. The Department told us that “risks were not adequately identified, assessed, mitigated and reported on by and within Crossrail Ltd”. Had these risks been addressed earlier then it is likely that the programme would not have veered so drastically off course. The Pudding Mill Lane explosion in late 2017 contributed to delays, but many elements of the programme, including the stations and signalling systems, were already a long way behind schedule. Even if the explosion had not happened, the programme would still have failed to deliver on time. The Department and Crossrail Limited failed to fully understand the cumulative effect of the risks that the programme was carrying. In May 2018, the Department’s representative embedded within Crossrail Limited was reporting significant risks that the programme would not be delivered on time, but this information was not sufficiently acted upon by the Department who remained convinced by assurances from Crossrail Limited that the programme was still on track. Given that the stations and signalling systems are still some way from being completed, and that at least a further year of work now appears to be required, we find it difficult to believe that it was not evident before the public announcement in August 2018 that the central section of the railway would not open on time. Recommendation: The Department should write to the Committee within six months of this report to explain the steps it is taking to encourage a culture of openness and transparency internally and across its delivery bodies. This should include how it will ensure that project and programme teams reconsider and revisit completion dates for major programmes at key points through the programme lifecycle and engage early with the Department on challenges meeting agreed dates. The Department should also commit to updating the Committee at regular intervals and ensure that we are kept up-to-date with all key developments.
2It is unacceptable that the Department and Crossrail Limited are unable to identify the root...
Concluded (the committee's words)
It is unacceptable that the Department and Crossrail Limited are unable to identify the root causes of the programme unravelling so quickly and so disastrously. A member of the Committee visited a Crossrail site in June 2018 and was told that the programme was on track. It was not until August 2018, four months before the central section was due to open, that there was any public recognition of the seriousness of the problems with the programme. Since then, it has become clear that the programme will be delayed by at least a year and forecast costs have potentially grown by nearly a fifth. There is an incongruity between how the programme can be described as performing so well and such significant issues emerging so quickly. The Department and Crossrail Limited’s explanation for this focuses on a failure to assess the cumulative risks that were emerging as the programme schedule 6 Crossrail: progress review was becoming more and more compressed due to delays. Crossrail Limited also accepted that at the time its management team did not have a good enough grip or understanding of the work that was still to be completed. However, the Department and Crossrail were unable to provide a convincing explanation of the root causes of the delays. Recommendation: The Department should consider the root causes of cost increases and delays and should write to the Committee by June 2019 setting out how it has taken lessons learned into consideration and what impact this has had on its approach to the project.
3We are disappointed at the Department’s and Crossrail Limited’s unacceptably laissez-faire attitude to costs potentially...
Recommended (the committee's words)
We are disappointed at the Department’s and Crossrail Limited’s unacceptably laissez-faire attitude to costs potentially rising by nearly £3 billion. In response to escalating costs, in July 2018 the government announced an additional £0.59 billion of funding for the programme. After further cost increases and delays, in December 2018 the government announced £2.15 billion of additional funding, bringing the total budget to £17.6 billion (approximately a £2.8 billion, or 19%, increase on the £14.8 billion funding agreed in 2010). We are not satisfied by the Department’s vague response to our questioning on how it protected taxpayers’ money when overseeing delivery of the programme. The Department failed to identify what it had done proactively on this programme. Instead, the Department asserted that it aimed to consistently learn lessons from issues when they arise and apply those to new projects. The Department and Crossrail Limited still do not have a revised estimate of the programme’s cost. Recommendation: In response to this report, the Department should set out how it considered the value for money for the taxpayer when agreeing to increased funding for the programme in 2018.
4We are concerned that the value for money of the programme is at risk from...
Concluded (the committee's words)
We are concerned that the value for money of the programme is at risk from further cost increases and delays. While originally due to open in December 2018, the central section of the railway has been delayed and a revised opening date has not yet been set. Since December 2018, Crossrail Limited has been re-sequencing the remaining works required for the central section of the railway, untangling a schedule that had become more and more compressed over time because of delays. It has not yet completed this work. Crossrail Limited is looking at completing the railway systems needed to run the trains on the line (such as the signalling systems and operational systems to control parts of the railway including platform doors) before completing the stations, which it acknowledges was not the optimal way of completing the programme. The Department and Crossrail Limited will not fully know how much the programme is now expected to cost until they have agreed a revised schedule to completion and have secured revised contracts with Crossrail Limited’s main contractors. We are therefore not convinced that the £2.8 billion of additional funding will be sufficient to see the programme through to completion. Recommendation: The Department must write to the Committee immediately after reaching agreement with Crossrail Limited to outline how it has assured itself that the revised schedule and cost to completion are robust. The Department should also detail how the £2.8 billion of extra funding should be allocated. Crossrail: progress review 7
5The Department and Crossrail Limited’s governance arrangements have been weak and characterised by a catalogue...
Concluded (the committee's words)
The Department and Crossrail Limited’s governance arrangements have been weak and characterised by a catalogue of failures to adequately oversee performance. The Department, as a joint sponsor of the programme with Transport for London, failed to ensure that the governance arrangements it put in place continued to be fit for purpose as the programme progressed. The Department acknowledges that it did not do enough in response to the recommendations in 2014 that governance arrangements should be changed to reflect the programme moving from construction to integrating the elements of the new railway, such as stations and signalling systems. The Department told us that the autonomy it and Transport for London gave to Crossrail Limited hindered their ability as sponsors to understand and challenge progress during the later stages of the programme. This, and Crossrail Limited’s failure to properly report the position of the programme and risks, meant that the Department did not understand the true position of the programme. The Department accepts that its governance arrangements were insufficient to properly capture the risks to the programme as it progressed and that it should have reviewed its governance arrangements several years ago. In the last year, the Department and Transport for London have replaced senior staff responsible for overseeing the programme and added new appointees to the Crossrail Limited Board that have relevant experience. We are not convinced by the Department’s assertion that it stepped up its challenge of the programme in 2018. Crossrail Limited told us that it is now working more closely with sponsors. However, we are concerned that the Department, Transport for London and Crossrail Limited have effectively given up on the previous contractual structure without any sense of clarity on what the new relationship is. Recommendation: By July 2019, the Department must explain how it has changed its contractual relationship with Crossrail so that it can properly exercise oversight and hold Crossrail Limited to account for its performance managing the programme to completion.
6Despite acknowledging that there were major failings in the programme, the Department and Crossrail Limited...
Concluded (the committee's words)
Despite acknowledging that there were major failings in the programme, the Department and Crossrail Limited have been unwilling to accept their responsibilities for the significant delays and cost overruns of the programme. The Department is ultimately responsible for ensuring that the programme delivers value for money for the taxpayer and for the funding it provides to Crossrail Limited. Crossrail Limited’s Board is accountable to the Department and Transport for London for delivering the programme to time, quality and cost. Both the Department and Crossrail Limited identify the compressed delivery schedule and a failure to properly identify risks as the fundamental problem in the programme which led to unacceptable levels of cost increases and delays. They also accept that governance arrangements failed to adequately identify these risks. However, neither are willing to identify who should be held responsible for these failures, and simply assert that there are systems failures. We are entirely unconvinced by this rationale as the Department and Crossrail Limited were responsible for creating and managing the system that enabled these failures to occur. The Department accepts that there was an insufficient level of accountability regarding the amount of money that senior executives were paid within Crossrail Limited. Some of Crossrail Limited’s former executives are paid much more than senior executives in the Department’s arm’s- 8 Crossrail: progress review length bodies to deliver programmes or project of equal weight. These executives were paid to bring expertise into the programme and deliver an operational railway, but failed to do so. Recommendation: The Department should, as a matter of urgency, write to the Committee clearly articulating what it, Transport for London and Crossrail Limited are responsible and accountable for in relation to Crossrail and what the consequences have been for those senior officials in positions of accountability and responsibility for failures on the programme. We expect this letter by the end of April 2019. Crossrail: progress review 9 1 Delays and cost overruns
7Crossrail Limited told us that it would not be possible for the central section of...
Concluded (the committee's words)
Crossrail Limited told us that it would not be possible for the central section of the railway to open in 2019 become of the amount of work still to complete, but that its aim was for it to open in 2020.7 Crossrail Limited told us that it expects to announce in April 2019 when the railway will fully open. However, it told us that it would not be naming a single date, but would instead announce a range of dates that it expects to narrow over time as levels of risk and uncertainty reduce. It told us that a wide date range may be announced initially.8
8Crossrail Limited told us that the programme did not yet have a revised cost estimate...
Concluded (the committee's words)
Crossrail Limited told us that the programme did not yet have a revised cost estimate because there was not an agreed schedule to completion or a plan of work. However, it expected the final cost of the programme to be within the revised total budget that was set by the Department in December 2018. The Department confirmed that it expected Crossrail Limited to deliver the programme within the revised budget, which had some contingency built into it. Crossrail Limited was similarly unable to provide us with a detailed assessment of its level of confidence that the additional funding would be enough.9
9We pressed the Department on how it protected taxpayers’ money when overseeing the delivery of...
Concluded (the committee's words)
We pressed the Department on how it protected taxpayers’ money when overseeing the delivery of Crossrail. The Department asserted that it was a large, complex programme that was difficult to deliver. It was scrutinising what had happened over the last two years to learn lessons from the difficulties that had arisen. We were not satisfied with the Department’s response because it failed to identify what it had done proactively on this programme to protect taxpayers’ money. Instead, it asserted that it aimed to consistently learn lessons from issues when they arise and apply those to new projects. Also, we were not convinced that it had a grip on the root causes of the delays and cost overruns, which must be established before lessons can be learned. Crossrail Limited was similarly unable to provide us with a detailed assessment of its level of confidence that the additional funding would be enough.10 6 Qq 46, 97, 99–101 7 Qq 47, 48 8 Qq 67, 98, 101 9 Qq 25, 107–111 10 Qq 24–31, 105–109 Crossrail: progress review 11 Warning signs of programme failure
10Crossrail Limited told us that there was an “extreme commitment” both within, and outside, the...
Concluded (the committee's words)
Crossrail Limited told us that there was an “extreme commitment” both within, and outside, the programme to meet the December 2018 milestone, set in 2010, for the start of train services running through the central section of the railway, between Paddington and Abbey Wood.11 The Department acknowledged that this date had become politically important to TfL, the Mayor of London and the Department, and that this was not conducive to the effective management of this complex programme. However, it asserted that the creation of Crossrail Limited as a separate delivery body was a way of enabling a responsible view to be taken of what could be delivered, and that it was Crossrail Limited’s responsibility to tell the Department if the delivery date could not be achieved.12
11We heard that the commitment and pressure to meet the December 2018 milestone, plus the...
Concluded (the committee's words)
We heard that the commitment and pressure to meet the December 2018 milestone, plus the challenges the programme had already overcome, led to optimism bias in Crossrail Limited on what could be achieved in the time available and a failure to properly assess the risks to the schedule from delays. The Chairman of Crossrail Limited’s Board, who has experience of large programmes but was not in post at the time that the failures emerged, told us that the courage required to challenge the schedule and stop such a large programme would have been “immense”.13 The Department recognised that there were broader lessons for government and the scope of the work it had commissioned following the problems with this programme included considering how government and the public sector can be more realistic about schedule pressure in complex programmes.14
12Crossrail Limited believed that there was no systematic failure in how the programme was organised...
Concluded (the committee's words)
Crossrail Limited believed that there was no systematic failure in how the programme was organised or designed, but a failure to understand the scale and complexity of the programme. We heard that London Underground would typically build three stations at once and commission or put into service, one or two a year. The Crossrail programme was of a different magnitude and involved building and commissioning 10 new stations.15
13Crossrail Limited explained that the work on the stations started to slip in 2016 and...
Concluded (the committee's words)
Crossrail Limited explained that the work on the stations started to slip in 2016 and that this had a ratcheting effect of building up risk within the programme. It told us that it had now re-sequenced the programme to complete the stations after the railway systems (such as signalling systems and operational systems to control parts of the railway including platform doors), a situation it did not want to be in. It accepted that this re- sequencing should have happened earlier when the stations first became delayed.16
14In November 2017, there was an explosion at an electrical substation at Pudding Mill Lane,...
Concluded (the committee's words)
In November 2017, there was an explosion at an electrical substation at Pudding Mill Lane, which had “far-reaching consequences” and the “explosion set off a chain reaction of glitches—delaying power to the central tunnels and thus all the extensive testing that needed to be done”.17 The Department told us that this set off significant alarm bells and had an enormous impact on the programme because three months of the schedule was lost, with only 13 months to go before the December 2018 opening. It told us that this had prompted it to question Crossrail Limited on whether the December 2018 milestone 11 Qq 3, 6, 67 12 Qq 86–87, 94 13 Qq 6, 38, 68, 69; Tony Meggs was previously the Chief Executive of the Infrastructure and Projects Authority. He became the Chairman of Crossrail Limited’s Board on 14 January 2019. 14 Q 94 15 Qq 41, 43; C&AG’s Report, page 7 16 Qq 50–52 17 Financial Times, Crossrail: how Europe’s largest transport project stalled, 20 December 2018 12 Crossrail: progress review could still be met and that Crossrail had assured it that by revising its plan for testing and commissioning, it could still deliver the railway in December. It told us that it was disappointed that it had not received better information and that over-optimism had led to inaccurate assumptions being made about what was possible. Crossrail Limited told us that while the explosion was a significant event, it was not the main cause of the delays as at the date of the explosion there was already a lack of installed signalling systems and the stations were a long way behind schedule. It asserted that the risk profile of the programme at that stage was such that, even if the explosion had not happened, the programme would still have failed to deliver on time. It recognised that individuals and teams were working in silos and were not able to identify the impact that individual delays had on the overall programme, so this information was not communicated upwards.18
15Since December 2018, TfL has published some Crossrail programme documents on its website, including project...
Concluded (the committee's words)
Since December 2018, TfL has published some Crossrail programme documents on its website, including project status reports by the Project Representative.19 The Project Representative is a team appointed by the programme’s sponsors, embedded in Crossrail Limited, to undertake reviews and provide commentary to the sponsors on progress.20 The Project Representative’s May 2018 project status report, even though redacted, includes statements such as “significant completion and integration challenges remain” with the stations, tunnel portals and shafts, and “technical difficulties and poor progress” in the completion of other rail systems. The operational readiness assessment within the report notes that 16 readiness tasks are rated as ‘red’ and a further 5 are rated as ‘amber’. None are rated at ‘green’. The report summarised that the schedule “remains highly ambitious” and there “remains a high risk that [the December 2018 opening date] will not be achieved”.21 Around the same time, in June 2018, a member of the Committee visited a Crossrail site and was told by programme representatives that the programme was on track and would be delivered on time. Crossrail Limited told us that it did not believe there was any intention to deceive or mislead, but that programme staff probably failed to understand the work still to complete or the amalgamation of risk.22
16The Department was unable to explain how it reconciled the Project Representative’s bleak assessment with...
Concluded (the committee's words)
The Department was unable to explain how it reconciled the Project Representative’s bleak assessment with other information it was getting from Crossrail Limited that the programme would be delivered on time. The Department argued, unconvincingly, that the Project Representative was a small team undertaking deep dives into small aspects of the programme, compared to thousands of members of staff in Crossrail Limited. It told us that while it was aware of delivery risks to the December 2018 delivery date, it expected these to be a matter of weeks not months and the scale of the problems emerged far faster than it expected. It recognised that there had been warning bells in March and April 2018 because of projected cost increases, but given the scale of the programme, it had believed these were not as major as the problems that crystallised over summer 2018.23 The Department told us that in 2018 there was a “real stepping up” of its challenging, and the questions that it was asking, of Crossrail Limited’s executive team in order to get 18 Qq 62–65 19 Transport for London, Crossrail project updates 20 C&AG’s Report, page 16 21 Jacobs, Project status report 111, Period 1 FY 2018–19, 1 April 2018 – 28 April 2018, 24 May 2018 22 Qq 65, 74–77 23 Qq 82–85, 143 Crossrail: progress review 13 clarity and assurance on progress, and that Crossrail had remained confident consistently that the delivery date of December 2018 could be achieved.24 The Department was not able to explain sufficiently what changed as a result of this reported increased scrutiny.25
17The new Chief Executive of Crossrail Limited, who took on this role in November 2018,...
Concluded (the committee's words)
The new Chief Executive of Crossrail Limited, who took on this role in November 2018, asserted that individual reporting of risks was managed well and that there was a good audited risk process.26 However, they accepted that the management team did not have a good enough grip or understanding of the work that was still to be completed and that there was a systematic failure to properly assess the amalgamation of individual risks from delays to the interrelated work on the stations and signalling systems. The Department similarly asserted that staff involved were not incompetent and were acting professionally and in good faith. However, it told us that “risks were not adequately identified, assessed, mitigated and reported on by and within Crossrail Ltd”.27 The evidence we heard focused on explaining the failure to properly identify and get a grip on systematic risks across the programme. However, we did not hear a convincing explanation of the root causes of the delays that led to the schedule becoming compressed.28 We look forward to the results of a NAO review into the root causes of the delays.
18We questioned the Department on its confidence in the risk assessments for other departmental projects...
Concluded (the committee's words)
We questioned the Department on its confidence in the risk assessments for other departmental projects and programmes. We heard that the arrangements for delivering projects and programmes varied. It asserted, however, that it did have detailed risk registers for all the projects it directly managed and that it looked at cumulative risk across its portfolio of projects. Where it did not directly manage projects, the Department expected all risks to be reported to it by those delivering the projects and that it would challenge and assure reported risks. It was, however, keen to learn lessons and would be implementing the recommendations from a review it had commissioned jointly with the Infrastructure and Projects Authority on the wider lessons from the Department’s delivery of major projects.29 24 Qq 63, 78–81, 85 25 Qq 80–87, 90–93 26 Qq 12–14; Mark Wild was previously a non-executive director on Crossrail Limited’s Board. 27 Qq 2, 13, 17, 37, 65 28 Qq 32, 33 29 Qq 53, 54 14 Crossrail: progress review 2 Governance arrangements
19The Department for Transport (the Department) and Transport for London (TfL) are joint sponsors of...
Concluded (the committee's words)
The Department for Transport (the Department) and Transport for London (TfL) are joint sponsors of the Crossrail programme. Sponsors’ oversight of the programme has been through appointed non-executive members of Crossrail Limited’s Board and through discussions with the Crossrail executive at a sponsor board that meets monthly to discuss progress. The sponsor board is supported by a sponsor team made up of sponsor representatives. The sponsors have contracted for a Project Representative team (Jacobs) made up of engineers and project management specialists to provide advice to the sponsor team and board. The Project Representative conducts detailed reviews of aspects of the programme, as well as analysing Crossrail Limited’s regular progress reporting.30
20Crossrail Limited, a company wholly-owned by TfL, is a delivery body created by programme sponsors...
Concluded (the committee's words)
Crossrail Limited, a company wholly-owned by TfL, is a delivery body created by programme sponsors to manage the Crossrail programme at arm’s-length from government. A Project Development Agreement between the Department, TfL and Crossrail Limited defines Crossrail Limited overall responsibility for delivery of the Crossrail programme, including construction, integrating the programme and preparing for operating the new line.31 Governance
21The Department told us that Crossrail Limited had been set up at arm’s-length from government...
Concluded (the committee's words)
The Department told us that Crossrail Limited had been set up at arm’s-length from government to provide independence, protect it from political interference from the sponsors, and to enable it to deliver this complex and large programme to a fixed budget. It asserted that while this was an effective delivery structure for the first seven or eight years, this autonomy made it difficult for the sponsors to challenge and understand programme progress during the later stages of the programme, protecting Crossrail Limited from necessary and important challenge. Crossrail Limited told us that there were benefits from its status, which included enabling it to attract the best and brightest staff in a way that the civil service found difficult and also protecting it from money being stripped from the programme. However, the new Chairman of Crossrail Limited’s Board described this as an example of “extreme autonomy” and recognised that with hindsight, more periodic deeps reviews and external scrutiny would have been beneficial. The Department asserted that other arm’s-length bodies it sponsors, such as High Speed Two Limited and the Highways Agency, operate on a different basis and have different governance arrangements.32
22Crossrail Limited has always been responsible for integrating the different elements of the new railway...
Concluded (the committee's words)
Crossrail Limited has always been responsible for integrating the different elements of the new railway being delivered by contractors, Network Rail and suppliers of the trains.33 The Department and Crossrail Limited recognised that there were insufficient people involved in the programme with the necessary skills and experience of integrating elements of a railway. The Department also acknowledged that Crossrail Limited’s Board did not have sufficient strength or depth of expertise in systems integration that it needed to effectively challenge programme performance. It told us that sponsors had strengthened the Board in 2018 by appointing additional non-executives, including people with skills in systems integration. The Chairman of Crossrail Limited’s Board told us that both the 30 C&AG’s report, pages 15–17 31 C&AG’s report, pages 16–17; Committee of Public Accounts, Accountability to Parliament for taxpayers’ money, Thirty-ninth Report of Session 2015–16, HC 732, 4 May 2016 32 Qq 31, 70, 113, 114, 127 33 Qq 11–12 Crossrail: progress review 15 Board and executive team now had a different set of skills, with a “tremendous” amount of experience in complex railway systems brought into the programme.34 Both the Department and Crossrail Limited recognised that if they had acted earlier to enhance Crossrail Limited’s capability, some of the issues on the programme could have been picked up sooner.35
23The Department accepted that there should have been a fundamental revisit of the governance structure...
Concluded (the committee's words)
The Department accepted that there should have been a fundamental revisit of the governance structure two or three years ago, and that this should have been built into the programme from the outset.36 However, we note that this is an area that was raised by the NAO and others in 2014. In its report on Crossrail, the NAO recommended that the Department put in place governance arrangements appropriate for the programme’s transition from construction to operations, together with a transition plan.37 We questioned the Department on what changes were made following the NAO’s recommendation. The Department told us that it had appointed a new Crossrail operations director who attended the sponsor board and that there were regular discussions and updates on bringing the railway into use. The Department told us that Crossrail Limited produced a transition strategy which was signed-off by Crossrail Limited’s Board and the sponsors in
24The Department told us that it thought the Crossrail Limited Board should have done more...
Concluded (the committee's words)
The Department told us that it thought the Crossrail Limited Board should have done more to challenge the Crossrail executive team and ensure that it fully understood whether the information it was receiving accurately captured the programme’s progress. It acknowledged that the sponsor board did not get “under the skin” of the information that was being reported by Crossrail Limited. Both the Chairman of Crossrail Limited’s Board, and the Chief Executive, who were not in place at the time, accepted that information on progress of the programme being reported upwards was not sufficient and did not adequately assess the work to be done. The Department told us that it did not consider there to have been any attempt by Crossrail Limited to deceive the sponsors, and that information had been reported was in good faith, but the information did not give a full picture of some of the risks as they grew and became more complex.39
25The Project Development Agreement sets out a number of actions sponsors could take, and sanctions...
Concluded (the committee's words)
The Project Development Agreement sets out a number of actions sponsors could take, and sanctions they could apply if, for example, successful delivery of the programme was under threat or if forecast costs exceeded defined thresholds.40 The Department told us that these were rarely used and not very helpful, partly because the bar set for triggering them was high, and also because the sanctions available were “a bit nuclear”. Nevertheless, sponsors could not tell us whether these actions and sanctions, or indeed the terms of the Project Development Agreement, still applied. The Department told us that another mechanism for escalating issues, that did not have such formality around it, could be 34 Qq 8, 15, 21, 141 35 Qq 19, 132, 135 36 Q 142 37 C&AG’s Report, Crossrail, Session 2013–14, HC 965, 24 January 2014 38 Qq 31, 55–60 39 Qq 3, 4, 34, 36, 139 40 C&AG’s Report, page 16 16 Crossrail: progress review developed to improve transparency. Crossrail Limited told us that it was “moving beyond contractual arrangements” and working more closely with sponsors, for example meeting with the sponsors 10 times in the previous five weeks.41 Responsibilities for problems on the programme
26Given that the Department and Transport for London are responsible for establishing the governance arrangements...
Concluded (the committee's words)
Given that the Department and Transport for London are responsible for establishing the governance arrangements for the programme, and Crossrail Limited responsible for delivery, we pressed the Department and Crossrail Limited on who should be held responsible for the delays and cost overruns on the programme. They were unwilling to pin-point responsibility to a single individual or entity. Crossrail Limited asserted that it was unlikely that one person could be held ultimately responsible because it was a complex situation and the Crossrail programme was the single biggest railway project in the UK. The Department argued that the governance arrangements did not allow an individual to be pin-pointed as responsible, and that it was important not to over-simplify a complex set of factors that contributed to problems with the programme. We heard repeatedly that this was a ‘system failure’.42 The Department summarised this as Crossrail Limited failing to identify systemic risk, Crossrail Limited’s Board not challenging Crossrail’s executive team and the reporting of progress, and the Department failing to properly challenge the information that Crossrail Limited was reporting to it.43
27The Department told us that the amounts paid to former senior members of the Crossrail...
Concluded (the committee's words)
The Department told us that the amounts paid to former senior members of the Crossrail Limited Board were higher than those for the Chief Executives of the Department’s arm’s-length bodies and that the Department had senior executives doing equally challenging roles elsewhere for less. For example, the remuneration of the former Chief Executive of Crossrail Limited over the two year period between 1 April 2016 and 31 March 2018 was approximately £1.7 million. The Department told us that it was not directly involved in setting remuneration packages for senior Crossrail Limited executives and acknowledged that there had been insufficient challenge in setting these.44 41 Qq 112, 113, 115–125 42 Qq 3, 5, 7, 11, 22, 23, 31, 33, 35, 38, 39 43 Q 34 44 Qq 128, 129–131; C&AG’s Report, page 19 Crossrail: progress review 17

Evidence

Oral evidence sessions 1

Correspondence 4 letters