Crossrail: progress review inquiry
Closed
What the inquiry looked at
“Crossrail is a major programme to run new, direct rail services between Reading and all passenger terminals of Heathrow Airport at the western ends of the railway, through a new underground section beneath central London to Shenfield in Essex and Abbey Wood in south east London at the eastern ends. The project currently has a total funding envelope of £17.6 billion in its entirety. The Department for Transport (DfT) provides £4.9 billion, Network Rail provides £2.3 billion, and Transport for London and the Greater London Authority (GLA) jointly provide £7.1 billion, with the remainder coming from private sector contributions. The railway was due to open fully by the end of 2018, with works commencing in 2009. The final cost, however, remains uncertain, and there is currently no exact date for when the railway will be fully operational. In August 2018, Crossrail Ltd announced a delay to the project with an estimated opening date in Autumn 2019. In December 2018, the Mayor of London, the Greater London Authority (GLA), and Transport for London (TfL) confirmed an additional financing package with the Government to deliver the final stages of the Crossrail project. Emerging findings by KPMG, which did a review into Crossrail Ltd's finances, show that the likely cost impact of this delay could be between £1.6bn and £2bn. This includes the £300m already contributed by the DfT and TfL in July 2018, which leaves an estimated £1.3bn to £1.7bn to complete the project. Members will use this hearing to review the project’s overall progress, and examine the cost impact of the latest delay , as well as potential future delays.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The Crossrail programme aims to deliver a new east-west railway through central London, providing passengers with new train services to improve connections on the existing transport network, reduce journey times and ease congestion. It was supposed to set the standard for delivery of transport programmes, where the skills and knowledge gained from the programme could be exported around the world. Instead, yet again, costs have escalated and delivery dates have turned out to be over-optimistic. New train services were due to start in December 2018 but have been badly delayed. Until a revised opening schedule has been agreed, we are not convinced that new services will start to run in 2020 as now hoped, nor that the additional £2.8 billion of funding provided will be enough.
The Department and Crossrail Limited are unable to fully explain how the programme has been allowed to unravel. Crossrail Limited failed to properly report the position of the programme and risks. Key warning signs were missed or ignored, and Parliament and potential new passengers still do not know the root causes of the delays and significant cost overruns. As the programme progressed, the Department, as a joint sponsor of the programme with Transport for London, failed to ensure that the governance arrangements it had put in place were robust. We are becoming increasingly alarmed at the continual shortcomings our work has highlighted in the Department’s project management and oversight of the railways and we will continue to look closely at progress with this programme. We are also concerned about the clarity of message we have received from the Department throughout the programme. We have, previously, questioned the Department on the additional funding announced in July 2018 to cope with cost increases, only for further cost escalation and more funding to be agreed at a later date. This is symptomatic of how the costs of this project have been allowed to spiral out of control whilst question marks remain around its completion and when new train services will start to run.
What the government said
No government response is linked to this report.
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 25 February 2019 to 30 September 2019.
- Oral evidence 6 Mar 2019
- Report 3 Apr 2019
- Correspondence 4 letters
What it recommended 1 recommendation · 26 conclusions
1The Department for Transport, Transport for London and Crossrail Limited’s fixation on a delivery deadline...
2It is unacceptable that the Department and Crossrail Limited are unable to identify the root...
3We are disappointed at the Department’s and Crossrail Limited’s unacceptably laissez-faire attitude to costs potentially...
4We are concerned that the value for money of the programme is at risk from...
5The Department and Crossrail Limited’s governance arrangements have been weak and characterised by a catalogue...
6Despite acknowledging that there were major failings in the programme, the Department and Crossrail Limited...
7Crossrail Limited told us that it would not be possible for the central section of...
8Crossrail Limited told us that the programme did not yet have a revised cost estimate...
9We pressed the Department on how it protected taxpayers’ money when overseeing the delivery of...
10Crossrail Limited told us that there was an “extreme commitment” both within, and outside, the...
11We heard that the commitment and pressure to meet the December 2018 milestone, plus the...
12Crossrail Limited believed that there was no systematic failure in how the programme was organised...
13Crossrail Limited explained that the work on the stations started to slip in 2016 and...
14In November 2017, there was an explosion at an electrical substation at Pudding Mill Lane,...
15Since December 2018, TfL has published some Crossrail programme documents on its website, including project...
16The Department was unable to explain how it reconciled the Project Representative’s bleak assessment with...
17The new Chief Executive of Crossrail Limited, who took on this role in November 2018,...
18We questioned the Department on its confidence in the risk assessments for other departmental projects...
19The Department for Transport (the Department) and Transport for London (TfL) are joint sponsors of...
20Crossrail Limited, a company wholly-owned by TfL, is a delivery body created by programme sponsors...
21The Department told us that Crossrail Limited had been set up at arm’s-length from government...
22Crossrail Limited has always been responsible for integrating the different elements of the new railway...
23The Department accepted that there should have been a fundamental revisit of the governance structure...
24The Department told us that it thought the Crossrail Limited Board should have done more...
25The Project Development Agreement sets out a number of actions sponsors could take, and sanctions...
26Given that the Department and Transport for London are responsible for establishing the governance arrangements...
27The Department told us that the amounts paid to former senior members of the Crossrail...
Evidence
Oral evidence sessions 1
- 6 Mar 2019No witnesses recordedparliament.uk ↗
Correspondence 4 letters
- 30 Sep 2019Letter from Bernadette Kelly to the Chair on the Committees report – Crossrail: progress reviews, 26 September 2019To committee
- 8 May 2019Letter from Bernadette Kelly MP to Chair in response to report Crossrail: progress review, recommendation 6 - dated 29 April 2019To committee
- 5 Mar 2019Letter from Chair of the Committee, Meg Hillier MP to Bernadette Kelly, Permanent Secretary, Department for Transport relating to the Eurotunnel Settlement – dated 05/03/2019To committee
- 4 Mar 2019Letter from Chair to Permanent Secretary in relation to Crossrail: progress review inquiry - dated 04.03.19To committee