Renewing the EastEnders set inquiry
Closed
What the inquiry looked at
“The BBC built the external filming set for EastEnders (including ‘Albert Square’) in 1984, and originally planned to use it for two years. It has lasted for 34 years but is no longer fit for purpose. The BBC’s E20 programme, to replace and enlarge the set and improve various infrastructure at BBC Elstree Centre, is now forecast to cost £27 million more, and take an additional two and a half years to complete, compared to its plans in October 2015. A recent National Audit Office (NAO) report found that the BBC will not be able to deliver value for money on the E20 programme in the way that it envisaged in 2015. The BBC now forecasts that E20 will cost £86.7m – 45% more than the original budget. It is also estimating that it will be completed in May 2023 – 31 months later than planned. On 30 January, the Committee will question the BBC on the reasons for the delays and cost increases, as well as examining the planning processes.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
EastEnders is one of the BBC’s flagship TV programmes. Its external set was built 35 years ago and is no longer fit for purpose. The completion of E20 will be critical if EastEnders is to compete successfully against rival shows and retain audiences in a context where fewer people are watching traditional linear TV. However, E20 is late and over budget due to the BBC’s fundamental project management failures. We are concerned that E20 has gone off-track yet again after the 26-month delay that we heard about in 2016, and disappointed by the BBC’s complacency in managing this project, particularly in its early stages. The project is now set to cost licence fee payers £87 million — £27 million more than budgeted. It is not set to be complete until May 2023, nearly five years later than originally planned.
What the government said
The government responded on 25 April 2019.
BBC Response to Public Accounts Committee’s Eighty-Seventh Report of Session 2017-19 -Recommendation 1
BBC Response to Public Accounts Committee’s Eighty-Seventh Report of Session 2017-19 -Recommendation 1, 5 November 2019.
Summary written by Accountability Index from the government's response.The BBC responds to the Committee's recommendation for annual updates with a progress report stating that the E20 Programme is "on track to be delivered within the agreed overall budget of £86.7m by spring 2023, as planned".
- On the Front Lot, the BBC says construction works are "well underway" and it is "on course to complete in spring 2021 as planned, within the agreed budget". The key risk it identifies is the cost of the scenic works, which are going through a tender process.
- On the Back Lot, the BBC says the project is "at an early stage of design development" but "expected to be completed in spring 2023 within the agreed overall Programme budget".
- On lessons learned, the BBC says the Programme "continues to capture and apply lessons", citing a visit to the Coronation Street team in June and a "lessons learned" exercise in May.
- On risk and contingency, the BBC says the contingency budget "is being tracked closely" and reported to the Steering Group monthly, and that an external construction cost manager has been appointed to advise on the Back Lot budget.
BBC Response to Public Accounts Committee's Eighty-Seventh Report of Session 2017-19 - recommendation 3
BBC Response to Public Accounts Committee's Eighty-Seventh Report of Session 2017-19 - recommendation 3, 5 November 2019.
Summary written by Accountability Index from the government's response.The BBC's response to Recommendation 3 sets out the evidence it provides of best practice in procurement and contract management, and does not state any new commitment.
- The BBC states that its Procurement team is "recognised in the industry as one of the leaders in public sector procurement", citing accreditations in 2017 from the Global Sourcing Association and the Chartered Institute of Purchasing and Supply.
- It says the team runs over 80 tenders a year and has developed a lifecycle approach covering contracting through to delivery and exit, "aligning to the audit process undertaken by the NAO".
- The BBC published a Purchasing Policy in 2018 setting out purchasing rules by level of spend, and says BBC Procurement advises teams to calculate the "true whole life cost" of a purchase and to comply with the Public Contracts Regulations.
BBC response to the Committee's report on Renewing the EastEnders set
BBC response to the Committee's report on Renewing the EastEnders set, 25 April 2019.
Summary written by Accountability Index from the government's response.The BBC notes the Committee's findings, welcomes its recognition of the importance of the E20 Programme, and says it will provide the updates and evidence the Committee requested.
- On progress reporting, the BBC says E20, as a Critical Project, receives additional oversight from the BBC Board, and it will give the Committee a copy of the October 2019 report "as far as it relates to E20, once it has been considered by the Board".
- On skills, the BBC says Critical Project teams regularly assess the skills mix required and "will continue to do so", and it "will update the committee as suggested in July 2019".
- On procurement, the BBC describes its Procurement team as "recognised in the industry as one of the leaders in public sector procurement" and says it "will write to the committee by October 2019" with evidence of how it ensures best practice.
Read the government's response: BBC Response to Public Accounts Committ… ↗Read the government's response: BBC Response to Public Accounts Committ… ↗Read the government's response: BBC response to the Committee's report … ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 15 November 2018 to 5 November 2019.
- Oral evidence 30 Jan 2019
- Report 20 Mar 2019
- Government response 3 responses
- Correspondence 2 letters
What it recommended 0 recommendations · 11 conclusions
1Despite considering it crucial to the future success of EastEnders, the BBC has managed its...
2The BBC failed to get the right construction project management skills in place from the...
3The BBC’s procurement approach for the Front Lot contract was ineffective and increased the cost...
4The BBC told us that the forecast cost of E20 had increased partly because of...
5The BBC accepted that it had underestimated the scale and complexity of the project, including...
6The BBC failed to allocate enough money to manage the risks and contingencies of the...
7For any project to be successful and deliver the intended outcomes, it is vitally important...
8The lack of sufficient construction project management skills also meant that the project team failed...
9One of the most important elements of E20 is the Front Lot, which will replicate...
10Owing to the limited market interest on the first procurement, the BBC adopted a new...
11The BBC’s contract negotiations with Wates took 11 months — six months longer than planned...
Evidence
Oral evidence sessions 1
- 30 Jan 2019No witnesses recordedparliament.uk ↗