Select committee inquiry

Renewing the EastEnders set inquiry

Closed

Public Accounts Committee · Opened 15 November 2018 · Closed 15 November 2018

11 conclusions
Inquiry on parliament.uk ↗

What the inquiry looked at

“The BBC built the external filming set for EastEnders (including ‘Albert Square’) in 1984, and originally planned to use it for two years. It has lasted for 34 years but is no longer fit for purpose. The BBC’s E20 programme, to replace and enlarge the set and improve various infrastructure at BBC Elstree Centre, is now forecast to cost £27 million more, and take an additional two and a half years to complete, compared to its plans in October 2015. A recent National Audit Office (NAO) report found that the BBC will not be able to deliver value for money on the E20 programme in the way that it envisaged in 2015. The BBC now forecasts that E20 will cost £86.7m – 45% more than the original budget. It is also estimating that it will be completed in May 2023 – 31 months later than planned. On 30 January, the Committee will question the BBC on the reasons for the delays and cost increases, as well as examining the planning processes.”

The committee's words, from the inquiry page on parliament.uk ↗.

What it found

In the committee's words, from the summary of 87th Report - Renewing the EastEnders set ↗

EastEnders is one of the BBC’s flagship TV programmes. Its external set was built 35 years ago and is no longer fit for purpose. The completion of E20 will be critical if EastEnders is to compete successfully against rival shows and retain audiences in a context where fewer people are watching traditional linear TV. However, E20 is late and over budget due to the BBC’s fundamental project management failures. We are concerned that E20 has gone off-track yet again after the 26-month delay that we heard about in 2016, and disappointed by the BBC’s complacency in managing this project, particularly in its early stages. The project is now set to cost licence fee payers £87 million — £27 million more than budgeted. It is not set to be complete until May 2023, nearly five years later than originally planned.

What the government said

The government responded on 25 April 2019.

BBC Response to Public Accounts Committee’s Eighty-Seventh Report of Session 2017-19 -Recommendation 1

BBC Response to Public Accounts Committee’s Eighty-Seventh Report of Session 2017-19 -Recommendation 1, 5 November 2019.

Summary written by Accountability Index from the government's response.

The BBC responds to the Committee's recommendation for annual updates with a progress report stating that the E20 Programme is "on track to be delivered within the agreed overall budget of £86.7m by spring 2023, as planned".

  • On the Front Lot, the BBC says construction works are "well underway" and it is "on course to complete in spring 2021 as planned, within the agreed budget". The key risk it identifies is the cost of the scenic works, which are going through a tender process.
  • On the Back Lot, the BBC says the project is "at an early stage of design development" but "expected to be completed in spring 2023 within the agreed overall Programme budget".
  • On lessons learned, the BBC says the Programme "continues to capture and apply lessons", citing a visit to the Coronation Street team in June and a "lessons learned" exercise in May.
  • On risk and contingency, the BBC says the contingency budget "is being tracked closely" and reported to the Steering Group monthly, and that an external construction cost manager has been appointed to advise on the Back Lot budget.

BBC Response to Public Accounts Committee's Eighty-Seventh Report of Session 2017-19 - recommendation 3

BBC Response to Public Accounts Committee's Eighty-Seventh Report of Session 2017-19 - recommendation 3, 5 November 2019.

Summary written by Accountability Index from the government's response.

The BBC's response to Recommendation 3 sets out the evidence it provides of best practice in procurement and contract management, and does not state any new commitment.

  • The BBC states that its Procurement team is "recognised in the industry as one of the leaders in public sector procurement", citing accreditations in 2017 from the Global Sourcing Association and the Chartered Institute of Purchasing and Supply.
  • It says the team runs over 80 tenders a year and has developed a lifecycle approach covering contracting through to delivery and exit, "aligning to the audit process undertaken by the NAO".
  • The BBC published a Purchasing Policy in 2018 setting out purchasing rules by level of spend, and says BBC Procurement advises teams to calculate the "true whole life cost" of a purchase and to comply with the Public Contracts Regulations.

BBC response to the Committee's report on Renewing the EastEnders set

BBC response to the Committee's report on Renewing the EastEnders set, 25 April 2019.

Summary written by Accountability Index from the government's response.

The BBC notes the Committee's findings, welcomes its recognition of the importance of the E20 Programme, and says it will provide the updates and evidence the Committee requested.

  • On progress reporting, the BBC says E20, as a Critical Project, receives additional oversight from the BBC Board, and it will give the Committee a copy of the October 2019 report "as far as it relates to E20, once it has been considered by the Board".
  • On skills, the BBC says Critical Project teams regularly assess the skills mix required and "will continue to do so", and it "will update the committee as suggested in July 2019".
  • On procurement, the BBC describes its Procurement team as "recognised in the industry as one of the leaders in public sector procurement" and says it "will write to the committee by October 2019" with evidence of how it ensures best practice.

How the inquiry ran

Each dot is a dated item listed on this page, from the inquiry's opening on 15 November 2018 to 5 November 2019.

  1. Oral evidence 30 Jan 2019
  2. Report 20 Mar 2019
  3. Government response 3 responses
  4. Correspondence 2 letters

What it recommended 0 recommendations · 11 conclusions

The committee's own words. Open an item to read it in full.

1Despite considering it crucial to the future success of EastEnders, the BBC has managed its...
Concluded (the committee's words)
Despite considering it crucial to the future success of EastEnders, the BBC has managed its E20 project badly. EastEnders is a flagship programme for the BBC but is being outperformed by its soap rivals, such as Coronation Street, and its overall audience has reduced as fewer people watch traditional linear TV. Therefore, it is important for EastEnders that the BBC completes E20 so that the programme is best placed to not only succeed but to also secure its long-term future. However, since we last heard about a 26-month delay to the project in 2016, it has gone off-track again. The project is now set to cost £87 million — £27 million more than initially budgeted - and complete in May 2023, nearly five years later than originally planned in 2013. The costs have increased partly because of inflation in the construction industry, the effect of which has been exacerbated by delays — with the construction of the Front Lot only starting in October 2018 rather than August 2017 as planned in 2015. The BBC has also underestimated the scale and complexity of the project, including how it would age the new sets so that they either exactly replicate what viewers are used to, or look realistic where there are new locations. In addition, the BBC initially failed to allocate enough money to manage risks and contingencies. It has encountered problems including asbestos and obstructions in the ground, which have, to date, cost the BBC around £1.8 million and delayed works by around four months. Under its latest plans, the BBC has substantially increased its risk and contingency budget. Recommendation: Commencing in October 2019 — one year into the construction of the Front Lot — the BBC should annually update the Committee on the progress, expected costs and completion date of E20. These updates should demonstrate how the BBC has learned lessons from previous project failings, and whether its revised risk and contingency budget has been adequate.
2The BBC failed to get the right construction project management skills in place from the...
Concluded (the committee's words)
The BBC failed to get the right construction project management skills in place from the outset of the project. It is disappointing that the BBC failed to consider what skills it needed in critical roles in the E20 project team. The BBC accepts that as a result, it did not have enough construction project management expertise to plan and deliver E20 effectively. One of the impacts of this was that the project team did not introduce design development and change processes early enough. After the 2015 project business case had been approved, it took over a year for a design change process to be agreed between the E20 programme and EastEnders production teams. This led to a build-up of change requests after the design was supposed to be stable. This issue was exacerbated by the project and production teams failing to work together effectively in the early stages of E20. Recommendation: By July 2019, the BBC should develop, and update us on, processes to make sure the right skills are in place from the outset for all of its critical projects.
3The BBC’s procurement approach for the Front Lot contract was ineffective and increased the cost...
Concluded (the committee's words)
The BBC’s procurement approach for the Front Lot contract was ineffective and increased the cost of the project by £2.3 million. In 2016, the BBC carried out a single-stage open procurement for the Front Lot but this was unsuccessful owing to limited market interest. This led the BBC to move to a two-stage procurement through its Building Contractor Service Framework, which cost it £2.3 million and 6 Renewing the EastEnders set delayed the project by six months. The second procurement, in which only two bidders met the BBC’s requirements, led to Wates being awarded the contract at a cost of £24.2 million, £9.5 million more than budgeted. The BBC’s cost consultants were unable to validate £3.1 million of the costs that were included in the final contract and concluded that limited market interest was likely to have inflated prices. In addition, the BBC’s contract negotiations with Wates took six months longer than planned, partly because of discussions about what bricks to use for the set. The commercial problems the BBC has encountered on this project demonstrate its ineffective sourcing and negotiating approach, which may have implications for other contracts. Recommendation: By October 2019, the BBC should provide us with evidence of how it ensures best practice in procurement and contract management across its diverse range of contracts — for E20 and other contracts. Renewing the EastEnders set 7 The progress of the BBC’s E20 project
4The BBC told us that the forecast cost of E20 had increased partly because of...
Concluded (the committee's words)
The BBC told us that the forecast cost of E20 had increased partly because of inflation in the construction industry, the effect of which had been exacerbated by project delays. For example, the construction of the Front Lot started in October 2018 rather than August 2017 as planned in 2015. The BBC asserted that £9.2 million of the project cost increases were the result of higher than forecast inflation and demand for construction services. However, it was unable to provide evidence to support this figure, beyond simply stating the difference between the original budget for the Front Lot contract and the final outturn in 2018.5 1 C&AG’s Report, E20: renewing the EastEnders set, Session 2017–19, HC 1782, 13 December 2018 2 Qq 1–2, 7–8; C&AG’s Report, paras 1.2–1.8, 1.12; Committee of Public Accounts, BBC critical projects, Eighth Report of Session 2016–17, HC 75, 8 July 2016 3 Qq 2–4; C&AG’s Report, para 1.3 4 Chair’s opening statement; Q5; C&AG’s Report, paras 1.12 and 2.1 5 Q 1, 34–36; C&AG’s Report, figure 6 and paras 3.20–3.21 8 Renewing the EastEnders set
5The BBC accepted that it had underestimated the scale and complexity of the project, including...
Concluded (the committee's words)
The BBC accepted that it had underestimated the scale and complexity of the project, including how it would age the new sets so that they either replicated what viewers are used to (on the Front Lot), or look realistic where there are new locations (on the Back Lot). The BBC told us that it had originally planned to age the new sets while they were being constructed as part of the main Front Lot and Back Lot contracts, but that it now planned for this work to be done separately after construction has completed, as its original intentions added risk and complexity to the project. The BBC has now scheduled more time to age the set — 13 months for the Front Lot and seven months for the Back Lot.6 The BBC told us that £3.5 million of the overall cost increases for the project related to ageing the new sets and additional resources to manage the Front Lot contract.7
6The BBC failed to allocate enough money to manage the risks and contingencies of the...
Concluded (the committee's words)
The BBC failed to allocate enough money to manage the risks and contingencies of the project in 2015. It has since encountered significant problems such as asbestos and obstructions in the ground. These issues have so far cost the BBC around £1.8 million and delayed works by around four months. The BBC told us that contingency represented 18% of the project costs in the 2015 business case, and that as part of its latest plans, it had substantially increased its risk and contingency budget.8 Skills to plan and complete E20 successfully
7For any project to be successful and deliver the intended outcomes, it is vitally important...
Concluded (the committee's words)
For any project to be successful and deliver the intended outcomes, it is vitally important that from the outset the project team has enough staff with the right skills and experience. The BBC acknowledged that it failed to get the right construction project management expertise in place early enough in the project and that the blend of skills in the project team was too focused on the creative, rather than construction-focused, elements of E20. It similarly accepted that this absence of construction project management expertise was a particular problem for the key roles of Programme Director and Manager. This meant there was insufficient construction knowledge to manage design, procurement and construction activities, which led to, for example, Front Lot design coordination problems that meant that the BBC had to commission various internal and external reviews to rectify design problems and inconsistencies. It also meant the project decisions and documents were ineffectively reviewed and challenged. The BBC had, however, made improvements in this area — recruiting a new Programme Director in September 2017 and a Front Lot Project Manager in July 2017, with both having construction experience.9
8The lack of sufficient construction project management skills also meant that the project team failed...
Concluded (the committee's words)
The lack of sufficient construction project management skills also meant that the project team failed to introduce design development and change processes early enough. The BBC accepted that having a change control process for the design of the Front Lot was particularly important and that it should have managed it better.10 It told us that it had taken over a year after the 2015 project business case was approved for a design change process to be agreed between the E20 programme and EastEnders production teams. As a result, there was a build-up of change requests — with associated costs of around £440,000 — after the design was meant to be stable. It also told us that this was exacerbated by the project and production teams failing to work together effectively in the early stages of E20 — with important members of the production team having poor quality working 6 Q 19; C&AG’s Report, paras 1.7, 2.8 and 3.8 7 Q 35 8 Qq 1, 10–12, 16; C&AG’s Report, paras 2.4 and 3.18–3.19 9 Qq 21–22; C&AG’s Report, paras 3.4–3.6 10 Q 40 Renewing the EastEnders set 9 relationships with members of the E20 team. The BBC recognised that the project and production teams were too distant and told us that it had made improvements in this area.11 Commercial approach
9One of the most important elements of E20 is the Front Lot, which will replicate...
Concluded (the committee's words)
One of the most important elements of E20 is the Front Lot, which will replicate the existing external set using brick structures rather than the current facades. The contract for this work is the largest in a wide range of 42 contracts that have supported E20. In 2016, the BBC carried out a single-stage open procurement for the Front Lot but this was unsuccessful owing to limited market interest. Only one of the three bidders met the BBC’s cost and quality requirements. The BBC attributed the lack of market interest to the bespoke nature of the project and the economic environment at the time making contractors more selective.12 The initial procurement failure led the BBC to change its approach and move to a two-stage procurement through its Building Contractor Service Framework, which cost it £2.3 million and delayed the project by six months. The BBC asserted that it was important to the success of the project that it had spent this money to ensure that its subsequent procurement process resulted in a better contract. It similarly claimed that, in all likelihood, had it not undertaken the initial procurement, it would have ended up with a contract with a higher cost and a lack of clarity about roles and responsibilities.13
10Owing to the limited market interest on the first procurement, the BBC adopted a new...
Concluded (the committee's words)
Owing to the limited market interest on the first procurement, the BBC adopted a new two-stage procurement approach for the Front Lot construction contract, using its Building Contractor Services Framework of six contractors, that began in March 2017. The BBC’s second procurement, where there were only three bidders with two bidders meeting the BBC’s requirements, led to Wates being awarded the contract. After an opening offer of £21.7 million from Wates, following clarifications and the confirmation of provisional sums and change requests, the cost of the final contract was £24.2 million, £9.5 million more than the BBC had budgeted. We were concerned that the BBC’s cost consultants (AECOM) were unable to validate £3.1 million of the costs that were included in the final contract and concluded that limited market interest was likely to have inflated prices. The BBC told us that AECOM had struggled to identify relevant data that it could use to benchmark the increased costs of the project but had nevertheless concluded that inflation was driving the difference.14
11The BBC’s contract negotiations with Wates took 11 months — six months longer than planned...
Concluded (the committee's words)
The BBC’s contract negotiations with Wates took 11 months — six months longer than planned — from October 2017 to September 2018. These lengthy negotiations were the result of the BBC receiving a more expensive contract offer from Wates than it expected, and partly because of discussions about what bricks to use for the set. The BBC told us that the process for choosing bricks had taken weeks and that it was important, consulting with production colleagues, to make the right choice. As part of agreeing the type and supply of bricks for the Front Lot, the BBC reviewed some £50,000 of sample brick panels that were produced by Wates. It explained that ‘Albert Square’ and surrounding scenery 11 Qq 23–26; C&AG’s Report, paras 3.13 and 3.16–17 12 Q 27; C&AG’s Report, paras 1.3, 3.22–3.24 13 Qq 27–29; C&AG’s Report, paras 3.23–3.25 14 Qq 28–29, 35; C&AG’s Report, paras 3.9 and 3.25–3.26 10 Renewing the EastEnders set was in the style of the Victorian era and including multiple shades of both bricks and mortar, and replicating the “look and feel” of the set meant that it was not possible to buy bricks from standard commercial sources.15 15 Qq 29–33; C&AG’s Report, paras 3.25–3.26. Renewing the EastEnders set 11

Evidence

Oral evidence sessions 1

Correspondence 2 letters