Defence Equipment Plan 2018-2028 inquiry
Closed
What the inquiry looked at
“Scope of the inquiry The Ministry of Defence’s (MoD) equipment and support programmes are essential for ensuring the UK’s Armed Forces have the equipment they need to meet their objectives. In 2012, following a period of poor financial management, the MoD introduced a 10-year Equipment Plan to encourage a longer-term perspective and greater cost certainty. Since then, it has published an annual statement outlining its expected equipment and support expenditure over the following ten years. However, a recent report by the National Audit Office has found that the Department’s Equipment Plan remains unaffordable, with forecast costs exceeding budgets by £7 billion over the next 10 years. Moreover, the Committee’s report in May 2018 was also concerned that the MoD lacked cost control, had reverted to previous poor practices, and that the Plan was simply not realistic. Although the Government agreed with all the Committee’s recommendations, it has made limited progress in implementing some of them. The Committee will question representatives from the MoD on how it plans to address its affordability gap across the 10-year equipment and support plan. It will also ask the MoD on plans to further improve its understanding, accuracy and the transparency of its forecast costs and assessment of affordability. Members may also wish to ask about the broader implications of the MoD’s decisions to manage affordability challenges in the short-term.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
In May 2018 we reported that the Ministry of Defence (the Department) did not have enough money to buy and support the equipment it needs. Despite committing to tackle this problem, the Department has made little progress, continuing to delay the difficult decisions needed to make the Equipment Plan (the Plan) affordable, particularly around which programmes to stop, delay or scale back. It now estimates a most likely affordability gap between its budget and its forecast costs of £7 billion across its Plan over the next ten years. It also estimates that the gap could widen to £14.8 billion, but even this looks to be unlikely and overly optimistic. The escalating and continuing affordability issues have led to short-term decision making which has only worsened the longer-term affordability risks. As a direct result, there is uncertainty for both the Department and for industry which needs to be addressed. Coupled with our ongoing concerns over the Department’s ability to forecast costs and efficiencies accurately, we remain sceptical that the Department is close to reconciling what it says it needs with the funding it has available.
What the government said
No government response is linked to this report.
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 3 September 2018 to 27 March 2019.
- Oral evidence 3 Dec 2018
- Report 1 Feb 2019
- Correspondence 2 letters
What it recommended 1 recommendation · 24 conclusions
1The Department’s Equipment Plan remains unaffordable as government continues to delay decisions on its priorities,...
2The Department’s inability to provide certainty on its equipment and support plans, risks reducing the...
3The Department still lacks the capability to accurately cost programmes within its Equipment Plan, making...
4The Department is assuming it will achieve significant efficiency savings, despite not having a coherent...
5The Equipment Plan still does not fully outline the level of risks and uncertainties within...
6HM Treasury’s requirement for departments to live annually within their means hinders the Department’s ability...
7We questioned the Department about its constant cycle of reviews and the failure to make...
8Following the NSCR and the MDP, the Department now expects it will make important programme...
9The Department said that although it was uncomfortable with the current size of the affordability...
10The Department recognises the importance of having clear and flexible relationships with its industrial partners,...
11The Department wants to ensure that the UK can act independently by having a “sovereign...
12We asked the Department whether it discussed industrial strategy and support for industry with other...
13The Department’s Permanent Secretary described his responsibility for ensuring that each year the Department spends...
14The Department agreed with us that it was hampered by having to balance the budget...
15The Department recognised the challenges of balancing short-term budget decisions against longer-term value for money...
16The Department considered that HM Treasury’s autumn 2018 statement showed it recognised the difficult decisions...
17The Department told us that the longer-term thinking the 10-year Plan requires has enhanced its...
18Around 2,000 cost lines feed into the Equipment Plan relating to specific equipment and support...
19For the 2018 Plan, the Department’s Cost Analysis and Assurance Service (CAAS) concluded that the...
20In July 2018, the Department set out a five-year financial skills strategy which it hoped...
21The Department reduces its equipment and support budget to reflect the levels of efficiencies it...
22The Department has included a £13.4 billion efficiency target in the Plan, with forecast costs...
23The 2018 Equipment Plan publication presented risks and uncertainties more transparently than in previous years.
24More specifically, the Equipment Plan describes some of the Department’s major programmes, but does not...
25Given the uncertainties resulting from the external environment, the Department plans for a range of...
Evidence
Oral evidence sessions 1
- 3 Dec 2018No witnesses recordedparliament.uk ↗