Nuclear Decommissioning Authority inquiry
Closed
What the inquiry looked at
“The Nuclear Decommissioning Authority (NDA) was set up in 2004 and has overall responsibility for clean-up and decommissioning work arising from the UK’s civil nuclear programme. Since April 2016 it has had direct control of Sellafield Ltd, the company responsible primarily for decommissioning the Sellafield nuclear site in Cumbria. A new report by the National Audit Office into the NDA found that work at Sellafield accounted for 61% of the NDA’s total £3.3 billion expenditure in 2017–18. 8 of NDA’s 10 most hazardous sites are at Sellafield, whilst NAO expected current major projects at Sellafield will cost £6 billion total. The NAO found that the NDA had made significant progress in reducing delays and meeting significant milestones, but expects major NDA projects to cost more than originally estimated in 2015. Evaluating performance at Sellafield remained difficult due to the complexity and scale of the site, but more could be done to explain progress, and to provide assurance of major projects. The Committee will take evidence from the Department of Business, Energy and Industrial Strategy, the Nuclear Decommissioning Authority, and Sellafield to explore NDA and Sellafield’s progress and performance.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The Nuclear Decommissioning Authority (NDA) and Sellafield Limited have recently met significant milestones with reducing risk at the high hazard facilities at Sellafield, the NDA’s largest and most hazardous site. The NDA and Sellafield Limited have also made progress with reducing delays and expected cost overruns with 14 major projects at Sellafield, which have a combined lifetime cost estimate of £6 billion.
While we recognise that there has been progress since this Committee last reported, there is still a long way to go and the NDA cannot afford to be complacent. Most major projects at Sellafield are still significantly delayed, with expected combined cost overruns of £913 million. The NDA has not systematically reviewed why these projects keep running into difficulties, or analysed properly the constraints it says prevent them from making faster progress. Until this work is completed, we remain sceptical about its long-term strategy to decommission Sellafield. Also, despite this Committee’s recommendation nearly five years ago, the Department for Business, Energy & Industrial Strategy has still not decided what to do with the plutonium stockpile currently stored at Sellafield.
Given the scale and unique challenges at Sellafield, the NDA must have a firm grip of the work that takes place on the site. We saw that this was not the case with the NDA’s recently failed contract to decommission its Magnox sites, and we are no more convinced of its current ability to monitor and challenge progress at Sellafield. At the same time, the Department for Business, Energy & Industrial Strategy must be more streamlined and effective in its oversight of the NDA’s performance if it is to hold it properly to account.
What the government said
No government response is linked to this report.
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 28 June 2018 to 27 September 2019.
- Oral evidence 16 Jul 2018
- Report 31 Oct 2018
- Correspondence 8 letters
What it recommended 0 recommendations · 25 conclusions
1The NDA has recently made progress with reducing risk at Sellafield, but most major projects...
2The NDA and Sellafield Limited have not analysed the constraints they say prevent faster risk...
3The NDA has not identified the lessons from project cancellations and past mistakes.
4Given the complexity, cost and long-term nature of the work at the site, the NDA’s...
5Central government’s oversight of the NDA is not holding the NDA to account effectively.
6We are not convinced that the NDA is achieving the wider economic benefits that would...
7The NDA’s programme to deal with the plutonium stockpile in the near term is late...
8The Department, through UKGI, oversees the NDA’s performance at Sellafield.
9The NDA and Sellafield Limited told us that their strategy for decommissioning Sellafield is based...
10The NDA and Sellafield Limited told us that turning Sellafield Limited into a direct subsidiary...
11The NDA has cancelled three major projects since 2012 because it says it has found...
12The NDA also cancelled a third project that involved building new storage tanks to store...
13The NDA and Sellafield Limited have not quantified what, if any, benefits have been derived...
14The Department is responsible for setting government policy for dealing with the UK’s stock of...
15The NDA asserted that it faces three main challenges in managing the plutonium stockpile at...
16The Department for Business, Energy & Industrial Strategy sponsors the NDA and is accountable for...
17UKGI is the main point of day-to-day contact between the government and the NDA.37 UKGI...
18Despite being responsible for monitoring the NDA’s performance and key risks against targets, UKGI does...
19UKGI told us that it tries to minimise overlap with the Department’s work in overseeing...
20The Department acknowledged that the governance system that supports and oversees the NDA’s work is...
21In 2017, we examined the NDA’s management of the Magnox contract to manage the decommissioning...
22The NDA told us that in the last few months it has set up a...
23The Energy Act 2004 requires the NDA to promote socioeconomic development and to work with...
24Last year, the NDA spent £10 million on socioeconomic development activities.
25The NDA and Sellafield Limited have an opportunity to lead and accelerate the development of...
Evidence
Oral evidence sessions 1
- 16 Jul 2018No witnesses recordedparliament.uk ↗
Correspondence 8 letters
- 27 Sep 2019Letter from Alex Chisholm, Permanent Under-Secretary of State, to the Chair regarding Plutonium Disposition, 22 July 2019To committee
- 13 Sep 2019Letter from David Beattie to Chair, in response to the Committee's report on Nuclear decommissioning authority - dated 22 July 2019To committee
- 11 Sep 2019Nuclear Decommissioning Authority - Ownership of Magnox Ltd
- 11 Jun 2019Letter from Alex Chisholm to Chair, regarding nuclear decommissioning system - dated 31 May 2019To committee
- 22 May 2019Letter from David Peattie, Chief Executive Officer at NDA, to Chair, in response to the Committee's report on Sellafield - dated 9 May 2019To committee
- 6 Mar 2019Letter from Councillor Alan Smith to Meg Hillier MP, regarding Committee's report on Nuclear decommissioning authority and Sellafield – 20.02.2019To committee
- 19 Sep 2018Correspondence from Department of Business, Energy and Industrial Strategy on Nuclear Decommissioning Authority – 06.08.2018
- 19 Jul 2018Correspondence with the Comptroller and Auditor General, 13 July 2018