Private Finance Initiatives inquiry
Closed
What the inquiry looked at
“Since the 1990s, successive governments have used Public Private Partnership intiatives known as PFI and PF2 to fund assets such as schools and hospitals. These allow private money to finance public projects. For a PFI or PF2 project, a private company called a Special Purpose Vehicle is set up to borrow money from a bank which is uses to fund a public asset. The taxpayer then pays back the Special Purpose Vehicle over a period of around 30 years. According to a National Audit Office (NAO) report on PFI and PF2 , there are currently 716 operating Public Private Partnerships with a capital value of £60 billion. Future charges on these Partnerships could continue to the 2040s costing around £199 billion. The NAO report found that government use of Public Private Partnerships had dropped from a peak of £9 billion in 2007–08 to £0.5 billion in 2016–17. This was in part because the financial crisis made borrowing through Special Purpose Vehicles more expensive than it had previously been. The report also found that Public Private Partnerships were relatively expensive, with initial finance for projects costing up to 5% more than publicly-funded initiatives, and small variations in costs of financing having large cash-terms consequences. The Committee will ask HM Treasury and the Infrastructure and Projects Authority whether Private Finance Initiatives are delivering value for money for the taxpayer, how they will keep costs down over the decades ahead, and what they have learned about how best to finance public projects.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
PFI has been used as a finance vehicle to fund public infrastructure off balance sheet for reporting public debt. The initial gain has been to the Treasury as the expenditure has been kept off the books. However the ongoing costs to the institutions at the front line have been high and the contracts inflexible, and the subject of much public debate.
Yet the Treasury has no plans to assess the value for money of PFI and there is little evidence of a strategy for working with local public sector bodies to co-ordinate sharing of best practice about managing existing PFI deals. The PAC raised concerns in 2011 and it is disappointing that so little progress has been made.
Liverpool City Council is paying £4 million a year for an empty school which underlines the worst extent of the inflexibility of PFI. This flawed deal will see almost £55.5million of taxpayer funds wasted since the school became empty in 2014.
Offshore funds have bought up about half of the equity in PFI and PF2 projects so that the projects’ owners are increasingly remote from the public service being delivered.
In addition, offshore owners of these projects pay little tax, thereby reducing one of the benefits used to justify the contracts in the first place.
Add to this the additional costs (and profits) generated by variations to the contract and the deal is not working for the taxpayer.
The Government’s reform of PFI was ultimately fairly limited, with the new PF2 only allowing greater transparency on a method that didn’t change fundamentally.
We note that there are only a handful of PF2 projects in the pipeline which suggests that the Government has lost faith in its own usage of PFI. If this is the case the Government should provide a clear explanation of its position. The Infrastructure and Projects Authority has identified a need for the UK to spend £300 billion on infrastructure by 2020/21, yet PF2 is only being proposed for two projects which require total public and private investment of up to £7.8 billion.
The Treasury needs to be much clearer about its position on PFI—it maintains that the UK’s level of debt and accounting treatment of PFI and PF2 do not form any part of the decision about whether to use PFI, but it is changing the design of PF2 to prevent capital costs of future projects from counting towards UK national debt statistics.
What the government said
No government response is linked to this report.
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 8 March 2018 to 20 June 2018.
- Oral evidence 28 Mar 2018
- Report 20 Jun 2018
- Correspondence 25 Apr 2018
What it recommended 3 recommendations · 18 conclusions
1It is unacceptable that after more than 25 years the Treasury still has no data...
3The Treasury and IPA are not doing enough to identify or address the impact of...
4The Treasury’s obvious desire to keep PF2 projects excluded from government debt statistics has created...
5PF2 is hardly being used, and IPA hasn’t made clear when its use is appropriate.
2The government has been using the Private Finance Initiative (PFI) and its successor PF2 for...
6The IPA told us that it had recruited a single member of staff, “pretty much...
7The financing structure of a PFI contract typically consists of 90% debt, in the form...
8The previous Committee suspected in 2011 that initial investors were able to make excessive profits...
9We were concerned to hear of high profile cases where the equity element of PFI...
10The Treasury and IPA have focussed on introducing PF2 and making changes to the private...
11The Treasury told us that unless contracts can be terminated on a voluntary basis, which...
12The Treasury told us that it is the combined responsibility of the Treasury, IPA and...
13Another problem currently affecting many public bodies relates to PFI insurance.
14In 2012, the Treasury replaced the PFI model with PF2 as part of efforts to...
15The public sector can borrow more cheaply than the private sector.68 According to Treasury rules,...
16Aside from value for money assessments, there remain budgeting and accounting incentives that encourage the...
17The Treasury told us that PFI and PF2 is only used if it demonstrates value...
18The public sector has used PFI less and less over time, falling from a peak...
19Since its launch in 2012, only 6 projects have used PF2: the Priority School Building...
20The Treasury told us that the outlook for investment in infrastructure is very ambitious.92 In...
21We asked the Treasury when PF2 investment would be suitable, if the public sector is...
Evidence
Oral evidence sessions 1
- 28 Mar 2018No witnesses recordedparliament.uk ↗