Defence Equipment Plan 2018–27 inquiry
Closed
What the inquiry looked at
“Every year the Public Accounts Committee examines the Government’s Defence Equipment Plan. The plan is a ten-year view of the expected cost of equipment and support for the Ministry of Defence. For 2018 to 2027, the expected spend is £179.7 billion. The National Audit Office (NAO) look at the plan annual, at the request of the Secretary of State for Defence. Reviewing the 2018 to 2027 strategic, the NAO concluded that: The plan was unaffordable The plan did not include £9.6 billion of forecast equipment and support project costs Forecasts of equipment and support projects were understated by £1.3 billion Project costings could be optimistic The NAO were also concerned that the Department had little financial flexibility to help them move money between budgets and address problems. The Department is already managing an overspend in 2017-18. The Public Accounts Committee has discussed Defence Equipment with the Ministry of Defence already this Parliament. At this session, the Committee will ask whether the Department how the Department plans to deliver its equipment plan in a financially sustainably way over the long term.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
Last year we reported that the Ministry of Defence’s (the Department’s) Equipment Plan was at greater risk of becoming unaffordable than at any time since its inception in 2012. These risks have now increased and the Ministry of Defence simply does not have enough money to buy all the equipment it says it needs. It is worrying that the Department is back in the position it found itself in earlier in the decade. The Equipment Plan for 2017 to 2027 is not realistic and the Department lacks cost control.
A significant affordability gap has again opened up; with forecast costs at least £4.9 billion, and potentially as much as £20.8 billion, more than the £179.7 billion budget.
The Department is reluctant to present openly an assessment of the affordability gap and has failed to report transparently to Parliament and the public about the financial risks it faces. The Department has put its faith in the Modernising Defence Programme to solve its affordability issues and to prepare for the continued challenges of a fast-changing defence landscape, including the UK’s capabilities for cyber, chemical, biological, radiological, nuclear and electromagnetic attacks. We are highly sceptical that the Modernising Defence Programme will be able to return the Department to a balanced position.
What the government said
The government responded.
The government states that it "agrees with the Committee's recommendation" in each of the six areas, setting target implementation dates between summer 2018 and January 2019, with one marked "Recommendation implemented".
- On the Modernising Defence Programme, the Department says it is "on track to share headline conclusions" around the NATO Summit in July 2018, and will report implications for equipment in the annual Equipment Plan Summary "following agreement of any equipment changes".
- It will publish the Equipment Plan Summary 2018 in the autumn, including an assessment of affordability, but says it "will not by that time be able to report on the detailed cost implications" of the MDP.
- On the nuclear programme (target date January 2019), it states that Dreadnought "remains on schedule and within the 2015 £31 billion cost estimate", and that it "remains committed to transparency".
- On F-35s, it will provide regular updates on costs, including sustainment costs, in the annual publication "where possible", and offer supplementary confidential evidence "if required".
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 2 March 2018 to 11 May 2018.
- Oral evidence 14 Mar 2018
- Report 11 May 2018
- Correspondence 2 letters
What it recommended 1 recommendation · 19 conclusions
1The Department faces a significant affordability gap in its Equipment Plan for the next 10...
2The Department’s current approach to planning for equipment does not reflect the continually changing nature...
3The Department’s Equipment Plan is characterised by significant cost optimism bias arising from weaknesses in...
4The biggest risk to the Equipment Plan is the cost of the nuclear programme.
5The Department is not sufficiently open with Parliament to allow us and the taxpayer to...
6The Department continues to be reliant on ever increasing and optimistic savings targets.
7The National and Security Capability Review had 12 strands.
8The Department did not account for £9.6 billion of forecast costs in the Plan.
9The Department told us that the projects they worry about most within the Equipment Plan...
10The rates the Department used to forecast costs in the Plan denominated in foreign currency...
11The Department’s Equipment Plan Statement for 2017 to 2027 was published at the end of...
12The Department set out that it is important to have timely, transparent reporting to Parliament,...
13We asked The Department has regularly increased the amount of savings required to fund the...
14The Department informed us that it has recently commissioned Oliver Wyman to assess independently the...
15The Department has started to develop a more rigorous approach to identifying and managing the...
16In previous years, the Department maintained headroom in its Plan to fund extra projects beyond...
17We asked the Department about multiple risks in the defence landscape.
18The Department told us that the rapid changes in the defence landscape mean it potentially...
19We asked the Department what its biggest worries were.
20We asked how the Defence Modernisation Programme links to the prosperity of the UK.
Evidence
Oral evidence sessions 1
- 14 Mar 2018No witnesses recordedparliament.uk ↗