Lessons from major rail infrastructure programmes
Closed
What the inquiry looked at
“This inquiry will review five major rail projects sponsored by the Department for Transport since 1998 (HS1, HS2, West Coast Mainline Modernisation, Thameslink and Crossrail). The Committee will look at the many challenges the Department has encountered in these projects which are large in scale and complex, with construction either expected to or having taken 9 to 10 years, at a cost of up to £21.4 billion. While the Department has made progress in its management of rail infrastructure programmes and responded well on programmes such as Thameslink and Crossrail to manage risks and control costs, there are key lessons, examples of good practice and common risk areas that the Department should be aware of and can act on when designing and implementing future rail projects. Further information National Audit Office report: Lessons from major rail infrastructure programmes”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The Department for Transport is responsible for a number of ambitious, expensive transport infrastructure programmes including the planned High Speed 2 programme. We are not convinced that these programmes are part of a clear strategic approach to investment in the rail network. In particular, recent proposals for a railway connecting cities in the north of England—a possible High Speed 3—suggest that the Department takes a piecemeal approach to its rail investment, rather than considering what would benefit the system as a whole and prioritising its investment accordingly. The Department told us it will deliver the full High Speed 2 programme within its overall funding envelope of £50 billion. However, this funding includes a generous contingency and we are concerned that, without appropriate controls, it could be used to mask cost increases.
When it comes to the wider regeneration benefits, insufficient planning meant that regeneration benefits in Ebbsfleet did not flow from High Speed 1 as expected. Although the Department told us that it has learned and is applying these lessons on High Speed 2, it needs to set out clearly who is responsible for ensuring that benefits are realised, and how that work will be coordinated.
What the government said
The government responded on 27 March 2015.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 8 October 2014 to 27 March 2015.
- Oral evidence 10 Nov 2014
- Report 16 Jan 2015
- Government response 27 Mar 2015
What it recommended 3 recommendations · 14 conclusions
1The Department still lacks a clear strategic plan for the rail network, and it is...
2We remain concerned about the Department’s ability to deliver on time and budget.
3We are sceptical about whether the Department can deliver value for money for the taxpayer...
4There is a risk that industry does not have the capacity to deliver all current...
5The Department has a long way to go to prove that it is being more...
6We are pleased to see that the Department is now focusing on its role as...
7With several rail infrastructure programmes either underway or proposed, the engineering industry also needs to...
8Several of the Department’s past projects have taken longer than was originally planned, partly in...
9The Department acknowledged that good planning and preparation determine success on major programmes, and told...
10The Department told us that it is important that HS2 Limited takes the time to...
11The Department told us that it is confident that it will deliver phase one of...
12The Department’s budget for High Speed 2 has a generous contingency, which the Department told...
13The Department has now revised the budget for phase one and considers that it is...
14We have seen academic research by the Omega Centre for Mega Projects in Transport and...
15In addition to funding from the general taxpayer, the Department and Transport for London used...
16Economic benefits and regeneration have been central to the objectives of a number of the...
17The Department has accepted 18 of the 19 recommendations of Lord Deighton’s Growth Task Force...
Evidence
Oral evidence sessions 1
- 10 Nov 2014No witnesses recordedparliament.uk ↗