Procuring new trains
Closed
What the inquiry looked at
“The Department for Transport has awarded contracts to two private sector consortia, to supply, finance and maintain new trains for the Intercity Express and Thameslink programmes. The Intercity Express Programme trains will replace ageing high-speed trains on the Great Western Main Line and East Coast Main Line, while the Thameslink trains are part of a wider programme to improve the cross-London Thameslink service. Train operators will pay the consortia to use the trains; the Department estimates that future payments will be around £7.65 billion for Intercity Express and £2.8 billion for Thameslink (present value, in 2014 prices), over 27.5 and 20 years respectively. This inquiry will examine whether the Department for Transport is well placed to achieve value for money from these deals, considering whether the Department and train operators will manage the contracts and the wider programmes effectively, and how well the Department maintained competition throughout the procurements. Further information National Audit Office: Procuring new trains Chair's statement: Procuring new trains”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The Department for Transport’s (the Department’s) decision to lead on two major train procurements itself, despite having no previous experience of doing so, was a significant break from its previous approach of leaving it to the rolling stock companies and train operators to buy trains. The Department has stated that it intends to leave some operational decisions to the market and to intervene in others. But it has not set out when these different approaches will apply, which is confusing for the industry. The Department’s decision to buy the trains itself has constrained the options available to future train operating companies as they will be required to use these trains to run their services. It is open to question as to whether the negotiations with preferred bidders provided best value. It is surprising, to say the least, that Agility reduced their price by 38% after Sir Andrew Foster reviewed the issue. By buying the trains directly the Department has taken on the risk of passenger demand forecasts being wrong. If demand proves to be lower than forecast taxpayers would have to cover the costs of any financial shortfall. These two major projects also demonstrate yet again that the Department has limited capacity and capability to manage large scale procurements, and that it remains overly reliant on consultants. Whilst we welcome Hitachi’s decision on Intercity Express to invest in the UK, it is extremely disappointing that Siemens will not also be manufacturing the Thameslink carriages in the UK, when the £2.8 billion contract is funded by the UK taxpayer and farepayer.
What the government said
The government responded on 25 February 2015.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 19 September 2014 to its close on 26 March 2015.
- Oral evidence 13 Oct 2014
- Report 17 Dec 2014
- Government response 25 Feb 2015
What it recommended 0 recommendations · 15 conclusions
1The Department awarded two large contracts to private sector consortia to supply, finance and maintain...
2The Department’s failure to articulate its role in the rail system has caused confusion in...
3The Department’s decision to purchase the trains leaves all the risk with the taxpayer.
4Value for money was undermined by the lack of certainty at the start of the...
5The procurement process for the Intercity Express Programme was poorly managed from the outset.
6We welcome Hitachi’s commitment to invest in County Durham so that trains are assembled in...
7The Department still lacks the skills needed to manage complex procurements.
8The Department made significant changes to the specifications for the new Intercity Express trains, which...
9When the Department drew up its original specifications for the Intercity Express programme, the business...
10We asked the Department what the Intercity trains would have cost if it had pursued...
11The Agility consortium reduced its price by 38 per cent when the Department changed the...
12The Department admitted that it did not have a credible alternative plan in case its...
13There was a lack of continuity on these two projects, with 7 changes of senior...
14The Department has a shortage of suitably qualified and experienced staff and is still reliant...
15Hitachi will be assembling the Intercity Express trains in the UK, but Siemens will not...
Evidence
Oral evidence sessions 1
- 13 Oct 2014No witnesses recordedparliament.uk ↗