Select committee inquiry

Defra’s oversight of three PFI waste projects

Closed

Public Accounts Committee · Opened 20 May 2014 · Closed 26 March 2015

18 conclusions
Inquiry on parliament.uk ↗

What the inquiry looked at

“Defra is responsible for meeting 1999 European Union directive targets for reducing the amount of waste sent to landfill in England. To meet these targets, it has established a Waste Infrastructure Delivery Programme, designed to provide local authorities with the necessary financial and technical support to invest in waste disposal infrastructure. Under this Programme, Defra is providing £1.7bn of grants through a PFI credit mechanism to 28 local authority projects. As a result, it has met the 2010 EU target and is on track to meet the 2020 target. This inquiry was triggered by a high volume of correspondence about three PFI waste incinerator projects in Herefordshire & Worcestershire, Norfolk and Surrey. Under the Programme, Defra has committed £205m of waste infrastructure credits to Surrey County Council and £113m of credits jointly to Herefordshire Council and Worcestershire County Council. In October 2013, Defra withdrew £91m of credits it had previously allocated to Norfolk County Council. This inquiry will examine the effectiveness of Defra’s support to the four local authorities and the challenges to value for money. Relevant information National Audit Office Report: Oversight of three PFI waste projects Government response: Treasury minutes, November 2014, CM 8958 (PDF 597 KB)”

The committee's words, from the inquiry page on parliament.uk ↗.

What it found

In the committee's words, from the summary of 14th Report - The Department for Environment, Food and Rural Affairs: oversight of three PFI waste projects ↗

The Department for Environment, Food and Rural Affairs (the Department) is responsible for ensuring that the national portfolio of projects is sufficient to reduce the amount of waste sent to landfill to meet the EU target. The Department provides grants to some local authorities using the Private Finance Initiative (PFI) to build new waste management infrastructure. However the Department does not accept responsibility for projects delivered by local authorities to meet the national targets for which the Department is responsible. PFI contracts typically last for 25-30 years and this does not offer the necessary flexibility to respond to rapidly changing technology and changing policy requirements for waste disposal. Furthermore, the Department has been unacceptably slow to intervene in projects that are struggling to deliver the required waste management infrastructure leading to delays and incurring extra costs. The Department’s handling of the Norfolk PFI waste project has been particularly poor with the Department failing to exercise good judgement by agreeing to give funding to the project and then failing to give sufficient consideration to the local impact of its decision to withdraw funding to that project. This contributed to the contract being cancelled which has left Norfolk taxpayers facing a bill of some £33.7 million.

What the government said

The government responded on 13 January 2015.

How the inquiry ran

Each dot is a dated item listed on this page, from the inquiry's opening on 20 May 2014 to its close on 26 March 2015.

  1. Oral evidence 25 Jun 2014
  2. Report 17 Sep 2014
  3. Government response 13 Jan 2015

What it recommended 0 recommendations · 18 conclusions

The committee's own words. Open an item to read it in full.

1In 1999, the European Union introduced a Directive requiring all member states to reduce the...
Concluded (the committee's words)
In 1999, the European Union introduced a Directive requiring all member states to reduce the amount of biodegradable municipal waste sent to landfill. The Department has responsibility for ensuring that England diverts sufficient waste from landfill to enable the UK to meet its target under this Directive of sending less than 10.2 million tonnes of waste to landfill a year by 2020. Local authorities have statutory responsibility for disposing of their municipal waste. The Department established a programme in 2006 to encourage the development of local authority waste infrastructure by providing support, guidance and funding to local authorities undertaking waste projects through PFI contracts. The Department part-funds local PFI projects through this programme. Local authorities are the signatories to the PFI contracts and are responsible for ensuring that their waste contracts represent value for money. The Department contracts staff from an organisation, Local Partnerships, to provide the technical support to local authorities. The Department, which oversees the allocation of funds and scrutinises local authorities’ plans, has allocated £1.7 billion of PFI credits to 28 local authorities under the programme. Our inquiry focused on the Department’s support to three PFI waste projects run by Norfolk County Council, Surrey County Council and a joint project managed by Herefordshire Council and Worcestershire County Council.
2The Department’s support of PFI to build waste management infrastructure may result in long term...
Concluded (the committee's words)
The Department’s support of PFI to build waste management infrastructure may result in long term contracts that are too inflexible for a sector where technology is continually evolving and the amount of waste produced can be hard to predict. The Department’s approach incentivises the use of PFI to construct waste management assets over other options for reducing the amount of waste sent to landfill. While the Department has told local authorities that there are alternatives to PFI contracts for constructing waste management infrastructure, such as selling the waste, it has more work to do to improve local authorities’ contracting capability, especially for PFI projects. PFI contracts typically last 25-30 years and may be inappropriate for the waste sector where technology is continually evolving and the amount of waste that will be produced in the future can be hard to predict. For example, the Department conceded that future waste infrastructure will need to generate both electricity and heat to be environmentally sensible, rather than just generating electricity as some older plants do. Moreover, domestic recycling rates are higher now than was predicted when some of the older projects were approved. Recommendation: The Department should consider including other forms of support to help local authorities to manage their waste in ways that are flexible enough to deal with changes in technology and waste levels to ensure local authorities are not locked into projects that provide more capacity than is required and are very expensive.
3The funding agreements for the early PFI waste deals were poorly drafted and too lax...
Concluded (the committee's words)
The funding agreements for the early PFI waste deals were poorly drafted and too lax as they require payments to be made even though some of the key assets planned have not been built. The Department’s predecessor, the Department for Environment, Transport and the Regions, signed funding agreements with Surrey 5 and with Herefordshire and Worcestershire councils for waste projects in 1998 and
4The Department waited far too long before renegotiating its funding agreements with Surrey and with...
Concluded (the committee's words)
The Department waited far too long before renegotiating its funding agreements with Surrey and with Herefordshire and Worcestershire Councils. Since taking over responsibility for overseeing these PFI grants in 2001, the Department continued to allow payments to be made to Surrey and to Herefordshire and Worcestershire councils even though key infrastructure had not been built. The Department only altered its funding agreements with these councils in 2013 when the Department negotiated a £30 million reduction in its payments to Herefordshire and Worcestershire Councils, and a change in the timing of its payments to Surrey County Council. Recommendation: The Department should act with far greater urgency when it has concerns about a project’s progress.
5The Department supported the Norfolk scheme despite having strong reservations about the local authority’s timetable...
Concluded (the committee's words)
The Department supported the Norfolk scheme despite having strong reservations about the local authority’s timetable for securing planning permission. This contributed to the £33.7 million bill Norfolk taxpayers now face. The Department had serious concerns as far back as 2010 over Norfolk County Council’s timetable for obtaining planning permission for its proposed energy-from- waste facility. Although the Department warned the council that its timetable was too ambitious, the Department still agreed in February 2012 to provide £91 million of PFI credits to part-fund the Norfolk project. We do not accept the Department’s assertion that because the Norfolk PFI contract met its funding criteria, it was a reasonable decision for the Department to agree to part-fund the project. If the Department had not promised funding support in early 2012 it might have prevented the Council from signing the contract. By later withdrawing support the Department contributed to the decision to subsequently terminate the contract, which has left local taxpayers facing an estimated £33.7 million bill for compensation to the contractor. Recommendation: The Department should not agree to fund schemes until all its concerns have been resolved.
6Local authorities need better advice on negotiating PFI contracts, particularly on technical aspects such as...
Concluded (the committee's words)
Local authorities need better advice on negotiating PFI contracts, particularly on technical aspects such as when to secure finance, and compensation arrangements. PFI contracts are complex and require specialist knowledge to 6 achieve value for money. Local authorities, who are likely to enter into such contracts only once in a generation, lack the significant expertise that resides in central government. The Department and the Treasury provide local authorities with guidance and point them towards specialist external advisors, but they do not provide direct advice. This has resulted in some councils making poor decisions and wasting taxpayers’ money as exemplified by the cancellation of Norfolk’s PFI contract where the council decided to put the finance for the facility in place before planning permission had been received, resulting in it having to pay more compensation to the contractor when the contract was terminated. Similarly the terms of the contract signed by both Surrey County Council and Hereford and Worcestershire Councils obliged the councils and the Government to pay contractors for services without a capital asset, which the Councils intend should be built, being provided. Recommendation: The Department should make better use of its position and expertise to support local authorities in negotiating PFI contracts and achieve value for money for local taxpayers.
7The Department has made decisions on this programme focused entirely on the need to meet...
Concluded (the committee's words)
The Department has made decisions on this programme focused entirely on the need to meet the EU target without due regard to the impact of its decisions on local authorities. The Department agreed to provide funding support to the Norfolk project in February 2012 but withdrew its funding in October 2013 because it judged that the Norfolk plant was no longer needed to meet the 2020 EU landfill target. The Department’s decision to withdraw funding was a contributing factor to the Council’s decision to cancel the contract the following year, at an estimated cost to Norfolk taxpayers of £33.7 million. The Department was fully aware of the likely compensation costs that would be incurred when it decided to withdraw funding. Recommendation: The Department needs to balance the need to meet the EU target at minimum cost, with making sure that its decisions serve taxpayers’ interests as a whole and do not result in additional costs for local authorities. The Department should place more weight in its decision-making on the cost to the public in the round when it considers withdrawing its support to individual projects. 7 1 The Department’s waste infrastructure programme
8The Department and its predecessor began making payments to Surrey County Council in 1999 and,...
Concluded (the committee's words)
The Department and its predecessor began making payments to Surrey County Council in 1999 and, by the end of March 2014, had paid £124 million under this funding agreement. The contract that Surrey signed had originally provided for the construction of two energy-from-waste plants, but these have yet to be built.14 Payments to Herefordshire and Worcestershire County Councils began in December 1998 and totalled £89.5 million by 31 March 2014. Again, the planned energy-from-waste plant has not been built.15
9The Department told us that “[we] have changed the way that we do these contracts,...
Concluded (the committee's words)
The Department told us that “[we] have changed the way that we do these contracts, so there are much tighter conditions on the local authority about what happens to the money and what triggers penalties or payments”.16
10PFI contracts are complex and specialised instruments that require skilled handling to achieve value for...
Concluded (the committee's words)
PFI contracts are complex and specialised instruments that require skilled handling to achieve value for money. Individual local authorities are only likely to enter into such contracts once in a generation. However, there is greater experience and expertise in handling them within central government such as in the Department and HM Treasury. The Department has provided support to local authorities since the start of the programme to help them handle complex PFI projects. In addition to providing local authorities with guidance on planning issues, technology, and procurement options, the Department has funded Partnerships UK to act as ‘transactors’ to provide expert support and advice to councils. The Department also told us that, when dealing with specialist areas such as hedging, it pointed authorities to external organisations who could provide support.17 Norfolk County Council in their evidence said that the Department examined and vetted all details of the proposed contracts.18 2 The Department’s oversight of three PFI waste projects
11The Department for the Environment, Transport and the Regions signed a funding agreement with Surrey...
Concluded (the committee's words)
The Department for the Environment, Transport and the Regions signed a funding agreement with Surrey County Council in June 1999 for £204.7 million of PFI grant and with Herefordshire Council and Worcestershire County Councils in December 1998 for £143 million.19 Payment of these grants to the local authorities began shortly after. The terms of the original funding agreements did not allow central government to unilaterally halt or alter the payment terms in the event that key capital assets were not delivered.20 Although the Department has had responsibility for overseeing these grants since it was created in 2001, it did not review these agreements until 2011, and did not successfully renegotiate the terms with Surrey and with Herefordshire and Worcestershire councils 14 C&AG’s Report, Oversight of three PFI waste projects, paragraphs 1.10 to 1.13 15 C&AG’s Report, Oversight of three PFI waste projects, paragraphs 1.14 to 1.17 16 Q 111 17 Qq 62-6 18 Written evidence from Norfolk County Council to the PAC, 23 June 2014, p 1 19 C&AG’s Report, Oversight of three PFI waste projects, paragraphs 1.10 and 1.14 20 Q 22 10 until 2013.21 As a result, grant payments of £213.5 million were made over fifteen years to Surrey and to Herefordshire and Worcestershire councils even though key facilities were not built. The process of renegotiation was time-consuming. In the case of the Herefordshire and Worcestershire negotiations, Defra confirmed that it took them six months to approve the new funding approach that the local authorities were proposing.22
12The renegotiations with Surrey did not alter the total amount of funding that the Department...
Concluded (the committee's words)
The renegotiations with Surrey did not alter the total amount of funding that the Department will provide, but ‘re-profiled’ the schedule of payments. Surrey is expecting a new waste management facility, including a gasifier to produce fuel from waste, to be operational by 2016-17. Under the renegotiated terms, the Department’s payments to Surrey has been reduced for the three years beginning 2013-14 and will continue to be lower until the gasifier starts processing waste.23
13The Department’s negotiations with Herefordshire and Worcestershire concluded with it reducing the total funding it...
Concluded (the committee's words)
The Department’s negotiations with Herefordshire and Worcestershire concluded with it reducing the total funding it will provide by £30 million. The planned energy-from-waste plant experienced serious delays in getting planning permission and, by the time permission had been obtained, the contractor could not arrange the necessary financing. The local authorities ultimately decided to build and finance the plant outside the PFI contract, without the PFI credits provided by the Department for a lesser sum, with risks being transferred back to the public sector.24
14The Department signed a funding agreement with Norfolk County Council in February 2012 to contribute...
Concluded (the committee's words)
The Department signed a funding agreement with Norfolk County Council in February 2012 to contribute £91 million of PFI credits towards a 25-year contract to build an energy-from-waste facility. Norfolk County Council estimate that this would have equated to £169 million in grant payments. However, the planning application to build this facility near King’s Lynn was called in by the Secretary of State for Communities and Local Government, and as a result the Council missed the deadline in its funding agreement with the Department to obtain planning permission by 10 June 2013. The Department subsequently revoked its funding in October 2013 and, after initially deciding to proceed without central government funding, Norfolk County Council terminated the PFI contract in April 2014. The contract Norfolk County Council had signed with its contractor included compensation clauses relating to securing finance and foreign exchange hedging and the decision to cancel the contract means that Norfolk County Council is expected to pay the contractor an estimated £33.7 million.25 The bulk of this compensation relates to contractor costs (£20.3 million) which include fees paid for arranging finance, and fees for unwinding hedging arrangements that were intended to mitigate against foreign exchange risk (£11.8 million).26
15The Department told us that such compensation clauses are standard in the PFI contracts in...
Concluded (the committee's words)
The Department told us that such compensation clauses are standard in the PFI contracts in the programme. Of the eleven bank-funded projects in the programme, the nine that did not have planning consent before financial close all had compensation clauses 21 Qq 124-7 22 Qq 113-17 23 C&AG’s Report, Oversight of three PFI waste projects, paragraph 1.13 24 Q 19 and C&AG’s Report, Oversight of three PFI waste projects, paragraphs 1.16-19 25 C&AG’s Report, Oversight of three PFI waste projects, paragraph 1.20 26 C&AG’s Report, Oversight of three PFI waste projects, paragraph 2.41 11 covering the same sort of costs as the Norfolk contract. Those funded by contractors’ balance sheets also contained similar compensation clauses, but without elements related to arranging bank finance.27 So far, the Norfolk contract is the only one where the compensation clauses have been triggered as no other contracts have been cancelled after signature.28
16The Department told us that, when signing the funding agreement in 2012, it had had...
Concluded (the committee's words)
The Department told us that, when signing the funding agreement in 2012, it had had serious concerns that Norfolk had not scheduled sufficient time to obtain planning permission. The Department was also aware that any delay in obtaining planning permission posed a serious financial risk to the local taxpayer, as Norfolk had secured finance in advance and signed a related compensation clause with the contractor. The Department raised these concerns with Norfolk County Council as far back as 2010, but the local authority was confident that it would achieve planning permission within the proposed timetable.29 When asked why it had agreed to provide funding despite having such serious misgivings about the project timetable, the Department confirmed that it had been under no legal obligation to provide funding, but had chosen to do so on the basis that it had been a “reasonable decision” given that Norfolk met the Department’s criteria for funding and the local authority could have taken the Department to judicial review if it had not provided funding.30
17A major factor behind the Department’s decision to cancel the PFI funding agreement in October...
Concluded (the committee's words)
A major factor behind the Department’s decision to cancel the PFI funding agreement in October 2013 was that the proposed waste facility in Norfolk was no longer needed to meet England’s contribution to the EU target.31 The decision to cancel the funding agreement came only 20 months after it had been signed and was unprecedented within the programme. 32
18The Department told us that when it made the decision to withdraw PFI credits from...
Concluded (the committee's words)
The Department told us that when it made the decision to withdraw PFI credits from the project, it had been fully aware of the compensation clauses in Norfolk County Council’s contract and the compensation costs the council would face if it cancelled the contract. The Department noted that it had considered the impact of withdrawing funding on the affordability of the project to Norfolk when making its decision.33 Norfolk County Council told us that the Department’s withdrawal of funding ‘left the County Council limited opportunity to pursue the substantial savings that could have been gained had it adopted different contract terms to those in standard PFI contracts’.34 27 Written evidence from Defra 28 Q 37 29 Qq 34, 58 30 Qq 43-51 31 Q 101 32 Qq 86-90 33 Qq 39, 85 34 Written evidence from Norfolk County Council to the Public Accounts Committee, 23 June 2014, p.2 12

Evidence

Oral evidence sessions 1