Defra’s oversight of three PFI waste projects
Closed
What the inquiry looked at
“Defra is responsible for meeting 1999 European Union directive targets for reducing the amount of waste sent to landfill in England. To meet these targets, it has established a Waste Infrastructure Delivery Programme, designed to provide local authorities with the necessary financial and technical support to invest in waste disposal infrastructure. Under this Programme, Defra is providing £1.7bn of grants through a PFI credit mechanism to 28 local authority projects. As a result, it has met the 2010 EU target and is on track to meet the 2020 target. This inquiry was triggered by a high volume of correspondence about three PFI waste incinerator projects in Herefordshire & Worcestershire, Norfolk and Surrey. Under the Programme, Defra has committed £205m of waste infrastructure credits to Surrey County Council and £113m of credits jointly to Herefordshire Council and Worcestershire County Council. In October 2013, Defra withdrew £91m of credits it had previously allocated to Norfolk County Council. This inquiry will examine the effectiveness of Defra’s support to the four local authorities and the challenges to value for money. Relevant information National Audit Office Report: Oversight of three PFI waste projects Government response: Treasury minutes, November 2014, CM 8958 (PDF 597 KB)”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The Department for Environment, Food and Rural Affairs (the Department) is responsible for ensuring that the national portfolio of projects is sufficient to reduce the amount of waste sent to landfill to meet the EU target. The Department provides grants to some local authorities using the Private Finance Initiative (PFI) to build new waste management infrastructure. However the Department does not accept responsibility for projects delivered by local authorities to meet the national targets for which the Department is responsible. PFI contracts typically last for 25-30 years and this does not offer the necessary flexibility to respond to rapidly changing technology and changing policy requirements for waste disposal. Furthermore, the Department has been unacceptably slow to intervene in projects that are struggling to deliver the required waste management infrastructure leading to delays and incurring extra costs. The Department’s handling of the Norfolk PFI waste project has been particularly poor with the Department failing to exercise good judgement by agreeing to give funding to the project and then failing to give sufficient consideration to the local impact of its decision to withdraw funding to that project. This contributed to the contract being cancelled which has left Norfolk taxpayers facing a bill of some £33.7 million.
What the government said
The government responded on 13 January 2015.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 20 May 2014 to its close on 26 March 2015.
- Oral evidence 25 Jun 2014
- Report 17 Sep 2014
- Government response 13 Jan 2015
What it recommended 0 recommendations · 18 conclusions
1In 1999, the European Union introduced a Directive requiring all member states to reduce the...
2The Department’s support of PFI to build waste management infrastructure may result in long term...
3The funding agreements for the early PFI waste deals were poorly drafted and too lax...
4The Department waited far too long before renegotiating its funding agreements with Surrey and with...
5The Department supported the Norfolk scheme despite having strong reservations about the local authority’s timetable...
6Local authorities need better advice on negotiating PFI contracts, particularly on technical aspects such as...
7The Department has made decisions on this programme focused entirely on the need to meet...
8The Department and its predecessor began making payments to Surrey County Council in 1999 and,...
9The Department told us that “[we] have changed the way that we do these contracts,...
10PFI contracts are complex and specialised instruments that require skilled handling to achieve value for...
11The Department for the Environment, Transport and the Regions signed a funding agreement with Surrey...
12The renegotiations with Surrey did not alter the total amount of funding that the Department...
13The Department’s negotiations with Herefordshire and Worcestershire concluded with it reducing the total funding it...
14The Department signed a funding agreement with Norfolk County Council in February 2012 to contribute...
15The Department told us that such compensation clauses are standard in the PFI contracts in...
16The Department told us that, when signing the funding agreement in 2012, it had had...
17A major factor behind the Department’s decision to cancel the PFI funding agreement in October...
18The Department told us that when it made the decision to withdraw PFI credits from...