Major Projects Authority
Closed
What the inquiry looked at
“Background The Major Projects Authority was established in March 2011 with a mandate to improve project delivery across government through robust assurance processes. Since then, the Authority has developed a range of interventions to give assurance over government major projects and to support HM Treasury approval and funding decisions. The Authority won the Public Accounts Committee award for Outstanding Value for Money in 2013. The Major Projects Authority is responsible for providing assurance over the Government Major Projects Portfolio, which consists of 199 major projects with total lifetime costs in excess of £400 billion. The Authority has published two annual reports; (for 2012-13) in May 2013 and (for 2013-14) in May 2014. This inquiry will look at the status of projects within the government major projects portfolio, assess how the Authority is addressing the Committee’s recommendations in the 2012 report Assurance for major projects, and those made by Lord Browne, in key areas such as strengthening government project delivery; and examine how far the Authority’s annual reports satisfy the Committee’s call for ‘complete and transparent disclosure’ of project information. Further information National Audit Office report: Major Projects Authority Annual Report 2012-13 and government project assurance National Audit Office report: Major Projects Authority Annual Report 2013-14”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
We welcome the progress made by the Ministry of Defence (the Department) in getting to grips with its budget and military equipment costs. The affordability of the Department’s 10-year plan for buying and supporting equipment is, however, dependent on it:
continuing to control cost increases in existing equipment projects; delivering ambitious project cost savings over the next 10 years in order to balance its budget; and having the right skills in place to ensure that the assumptions made in its plans are robust and deliverable. Failure to improve the skills of Defence Equipment and Support (DE&S), which buys and maintains military equipment, will undermine the Department’s efforts to improve control over its finances. The Department agrees that DE&S is over-reliant on expensive contractors and DE&S is spending a further £250 million on contractors over the next three and a half years to determine how it will address this and secure the skills needed to deliver the Equipment Plan within the assumed budget and to time.
There remain risks to the success of the Department’s Army 2020 programme designed to reduce the size of the regular Army and increase the number of trained Army reserves. The Department has not yet addressed our previous recommendations to develop credible contingency plans in the event that it cannot recruit the number of regular and reserve soldiers it requires. While the Department is reporting progress against its recruitment targets, it does acknowledge that targets beyond 2016 will be challenging and require significant improvements in performance.
We support the work of the Major Projects Authority (MPA) and recognise the progress it has made in strengthening project assurance and improving the transparency of information on the costs, risks and performance of government major projects. However, it faces significant challenges in achieving further improvements because there are still serious weaknesses in government’s project delivery capability and its portfolio of projects is rapidly increasing in size. There is still a lack of prioritisation and portfolio management at both a departmental and a cross-government level. The MPA is currently involved in many aspects of project management but in certain areas, such as ensuring departments act on its advice or in recruiting leaders for major projects, it is constrained by having to rely too heavily on informal means to influence departments.
What the government said
47th Report - Major Projects Report 2014 and the Equipment Plan 2014 to 2024, and reforming defence acquisition
No government response is linked to this report.
10th Report - Major Projects Authority
The government responded on 15 December 2014.
Major Projects Authority: Government response to the Committee's Tenth Report of Sessin 2014-15
Major Projects Authority: Government response to the Committee's Tenth Report of Sessin 2014-15, 13 January 2015.
Major Projects Authority: Government response to the Committee's Tenth Report of Session 2014-15
Major Projects Authority: Government response to the Committee's Tenth Report of Session 2014-15, 15 December 2014.
Read the government's response: Major Projects Authority: Government re… ↗Read the government's response: Major Projects Authority: Government re… ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 8 April 2014 to 20 March 2015.
- Oral evidence 5 Jun 2014
- Report 2 reports
- Government response 2 responses
What it recommended 2 recommendations · 18 conclusions
1The MPA was established in March 2011 as a partnership between the Cabinet Office and...
2The MPA is unlikely to achieve a systemic improvement in project management without stronger, more...
3The MPA provides welcome visibility of the Government Major Projects Portfolio, but despite the scale...
4The MPA could increase its impact by prioritising its assurance work more effectively.
5The Major Projects Leadership Academy (MPLA) is a welcome development but there is scope for...
6The MPA’s assessment of major projects does not cover value for money considerations.
7Despite welcome progress in extending the range of information published, the data is infrequent and...
8At the same time as the Government Major Projects Portfolio has grown, the MPA’s assessment...
9The MPA confirmed that an increasing number of “transformational projects”, where departments are looking to...
10The MPA established the Major Projects Leadership Academy (MPLA) in 2012, in partnership with the...
11The MPA told us that it wanted to get more project leaders through the Academy,...
12More generally, the MPA told us that there was a “lack of distributed capability across...
13MPA reviews focus primarily on whether projects will deliver on time rather than whether they...
14The MPA conceded that, while its reviews notionally address value for money issues, they are...
15The MPA provides a delivery confidence assessment that shows how likely it rates the successful...
16We have seen numerous examples of poor planning on government projects over many years.
17The data published by the MPA shows that it has the most serious doubts over...
18The MPA and departments publish information on major projects in line with the Government’s transparency...
19The NAO reported that the MPA’s second annual report and the departmental project data accompanying...
20The Department for Work & Pensions, in consultation with the MPA, published the delivery confidence...
Evidence
Oral evidence sessions 1
- 5 Jun 2014No witnesses recordedparliament.uk ↗