Sizewell C
Open
What the inquiry is looking at
“Sizewell C is a planned large-scale nuclear power station on the Suffolk coast. Funded by the government in partnership with the energy provider EDF, as well as private finance, the project is projected to cost £40.5bn to £47.7bn. When constructed, it will have a generating capacity of 3.2GW, meaning it will be able to generate around 7% of the UK’s current electricity demand. The Public Accounts Committee (PAC) previously reported on the government's deal with EDF to construct a nuclear power station at Hinkley Point, the site with Sizewell C will be based on. The PAC were concerned that that government's negotiations were not championing the interests of consumers, who might be locked into an expensive deal for decades, and warned that the poorest would likely be the hardest hit. In its response , the Government accepted all of the PAC’s recommendations and stated the actions it planned to take in response. The National Audit Office (NAO) will publish its report on Sizewell C in spring 2026. Following the NAO’s investigation, which is likely to examine the government’s current spend, as well as the potential risks to achieving value for taxpayer’s money, the PAC will hear from senior officials at the Department for Energy Security and Net Zero and Sizewell C on the reports key findings. If you have evidence on these issues, please submit here by 23.59 on Monday 18 May 2026. Please note that the Committee’s inquiry cannot assist with individual cases. If you need help with an individual problem you are having, you may wish to read the information on Parliament’s website about who you can contact with different issues .”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
Sizewell C represents a terrible deal for the UK taxpayer. Successive governments’ failure to deliver new nuclear has left the UK in a position where the best terms it could secure to deliver Sizewell C mean that consumers and taxpayers shoulder significant financial risks, while private investors enjoy protected profits. The UK must never be put in this position again.
Sizewell C is a high-risk mega project with an estimated construction costs in the range of £40.5 billion to £47.7 billion. It is expected to be fully operational in 2039 and operate for at least 60 years. The Department for Energy Security and Net Zero (the Department) argues that applying lessons learned from the UK’s other current major nuclear project, Hinkley Point C, and replicating the design of its pressurised water reactors, will reduce risks at Sizewell C. However, no comparable nuclear power station anywhere in the world has been delivered on time and on budget. Projects using the same reactor design have experienced delays of up to 14 years and substantial cost overruns.
The Department has chosen a novel delivery model for Sizewell C in which it relinquishes majority control, despite the public providing most of the financing and bearing most of the risk. The government will therefore rely heavily on its influence through the boards of Sizewell C to steer the project in the interests of taxpayers and electricity consumers. However, it is simply not credible to assume that public and private interests will always align or be reconcilable. For example, a divergence of interests is particularly likely if costs threaten to exceed the limit investors have agreed to fund. Government needs to plan for this in advance.
We are concerned that if costs rise above the baseline—and they are highly likely to—consumers will pay through higher bills, while private investors face little risk to their capital and yet still expect high returns. If construction costs rise to £47.7 billion, which is at the top of the Department’s estimated range, consumers could pay £9.8 billion more during construction and a further £12 billion over Sizewell C’s 60-year operating life, while private investors only need to put in an extra £30 million. Taxpayers also cover many of the other risks. For instance, the taxpayer will pay any final shortfall in funding for the decommissioning of Sizewell C. This all makes it difficult to justify annual investor returns of over 10% and raises concerns about whether investor incentives are strong enough to promote efficient delivery. The Department should make every effort to avoid rising costs for consumers and taxpayers.
Given the costs and risks to the taxpayer, Sizewell C should operate to the highest standards of transparency in major infrastructure delivery, with clear and publicly accessible data so that taxpayers, consumers and future infrastructure projects benefit. Reporting once a year would be totally inadequate given the project’s level of risk. The shareholders will benefit from a six-monthly update verified by an independent technical advisor – Parliament and the public require the same level of transparency and assurance.
A situation in which consumers and taxpayers are exposed to substantial construction and financing risks, while private investors enjoy high and protected profits, cannot happen again. The Department explained why it believes these terms were the best it could negotiate in the current market.
Therefore the Government’s most important task for the future is to build confidence that investment in UK nuclear power infrastructure can offer secure and predictable returns, so that future deals can be negotiated on better terms and the financial risks of any future schemes distributed more fairly. It is crucial that the UK seizes this opportunity to demonstrate it can break the track-record of poor delivery of nuclear projects and deliver Sizewell C on time and on budget. This will help future investors to see future projects as lower risk. It is also vital to develop the skills and experience of our nuclear workforce, strengthen our nuclear supply chains and work across government to secure the best possible legacy from the infrastructure created to support Sizewell C’s construction.
Conclusions and recommendations
1. Sizewell C is a high-risk mega project. No comparable nuclear power station anywhere in the world has been built on time and to budget. Sizewell C is expected to cost between £40.5 billion and £47.7 billion and is expected to finish construction between 2039 and 2043. It is being built using a design that has previously been used in France, Finland, China, and is also being built in the UK at Hinkley Point C. The design has a poor international delivery record, with a clear pattern of delays and cost escalations. The Department is relying on Sizewell C’s more mature design—85% the same as the completed Hinkley Point C design—and the transfer of learning from Hinkley Point C for the project to succeed where others have not. But it remains a highly complex infrastructure mega project with substantial uncertainty over its cost and schedule. This level of risk makes transparency particularly important. We are pleased that Sizewell C and the Department intend to use a consistent understanding of the forecast costs, verified by an independent technical advisor. However, while the shareholders will benefit from six-monthly reports, current plans are for the Department and Sizewell C Ltd to provide Parliament with only an annual report on these forecasts. This is totally inadequate for a project with significant exposure for taxpayers and consumers and could mean that emerging risks remain hidden for longer and are more costly to address when they do become apparent.
recommendation a. Sizewell C should be clearer on the level of risk it faces. Within three months of this report, Sizewell C Ltd should write to the Committee with the scenario analysis that it used to underpin its estimates of the Lower and Higher Regulatory Threshold cost estimates and schedules, its current assessment of the risk that each scenario comes true, and any new scenarios it is aware of.
b. Sizewell C Ltd and the Department should provide Parliament with a progress report every six months. The report should include the latest: actual and forecast costs; changes to cost and schedule forecasts; progress against key milestones; changes to the risk the public sector and consumers face; expected impacts on consumer bills; and forecast investor returns. They should also include any relevant narrative made by the Independent Technical Advisors during the period covered.
c. Sizewell C Ltd and the Department should publish the underlying data for its Sizewell C progress reports in machine readable formats. Figures should be presented consistently in nominal and real terms. Where information is withheld from these reports due to commercial or security sensitivities, Sizewell C Ltd should explain the basis for withholding it.
d. Sizewell C Ltd and the Department should write to the Committee as soon as possible outside the six-monthly reporting cycle if developments mean that the most recently reported cost or schedule forecasts are no longer reliable, or if there is a significant design change that materially affects the cost or delivery timetable of the project and its impacts on consumers.
What the government said
Government response awaited: deadline 28 December 2026.
How the inquiry has run so far
Each dot is a dated item listed on this page, from the inquiry's opening on 20 March 2026 to 28 December 2026. The dashed mark is the deadline Parliament records for the government's response.
- Oral evidence 8 Jun 2026
- Report 28 Oct 2026
- Correspondence 3 letters
What it recommended 7 recommendations · 25 conclusions
1Sizewell C is a high-risk mega project.
2The Department has relinquished control over Sizewell C to a delivery body that is majority...
3The Department’s failure to maintain a market for nuclear left it with only one option,...
4Ultimately, the Department was only able to secure the Sizewell C deal by accepting a...
5It is important that the UK captures the lion’s share of economic value from Sizewell...
6It will be important that Sizewell C has a culture where staff feel able to...
7Decommissioning a nuclear power station is expensive and comes with the risk that costs spiral...
8We asked about the current arrangements proposed for reporting progress to Parliament.22 Sizewell C described...
9Until the government made a final investment decision on Sizewell C in July 2025, the...
10The Department emphasised that its joint venture model is intended to bring the benefits of...
11In government, permanent secretaries (as accounting officers) have direct responsibilities to Parliament while serving ministers,...
12The number of competing large-scale nuclear sites has reduced over time, as the six alternative...
13The NAO report indicates that, over time, other non-EPR nuclear projects did not proceed, reducing...
14We also asked the Department whether alternative technologies could have provided additional flexibility or choice.
15The Department told us to us that the financing model was designed to attract private...
16The Department has also provided contractual commitments that further limit risks to private investors of...
17These structures mean that despite the public sector carrying the majority of the risks, the...
18The NAO concluded that it is “not clear” whether this structure sufficiently incentivises investors to...
19We have previously stated that “Not all risks can or should be transferred to the...
20The results of market processes inevitably reflected existing conditions, including investor views of the project...
21We have previously drawn together lessons for successful use of private finance in infrastructure.
22Important conditions were not in place for investment in Sizewell C.
23Expenditure of this quantum should be expected to leave a significant legacy for the UK,...
24Nuclear is a priority area for the UK’s High Value Manufacturing Catapult.74 Nuclear equipment and...
25We heard from the Department that it believes its investment in Sizewell C will deliver...
26We were pleased to hear that Sizewell C Ltd is working with Sheffield Forgemasters to...
27The previous Public Accounts Committee observed in 2024 that departments can miss opportunities for how...
28This Committee has previously identified weaknesses in organisational culture across parts of the nuclear sector,...
29The NAO reported that Sizewell C has put in place a workforce code of conduct...
30Decommissioning nuclear power stations has historically proven more costly and taken longer than expected, leading...
31Sizewell C Ltd will set aside money over the course of its operational lifetime to...
32There are three risks which could lead to a shortfall in the funding for decommissioning.
Evidence
Oral evidence sessions 1
- 8 Jun 20265 witnesses, listed belowparliament.uk ↗
Who gave evidence 5 witnesses
- Caroline BotwoodDirector, Nuclear Projects Delivery, Department for Energy Security and Net Zero
- Clive MaxwellSecond Permanent Secretary, Department for Energy Security and Net Zero
- Jonathan BrearleyPermanent Secretary, Department for Energy Security and Net Zero
- Joseph RipponDeputy Treasury Director, Sizewell C
- Nigel CannManaging Director, Sizewell C
Correspondence 3 letters
- 3 Sep 2026Letter from the Permanent Secretary at the Department for Energy Security and Net Zero relating to Sizewell C Parliamentary reporting, dated 24 July 2026To committee
- 13 Jul 2026Letter from the CEO at Sizewell C relating to a follow-up on the Sizewell C project, 3 July 2026To committee
- 29 Jun 2026Letter from the Permanent Secretary at the Department for Energy Security and Net Zero relating to Sizewell C oral hearing – follow-up note, 22 June 2026To committee