HS2 and Euston: Recall
Closed
What the inquiry looked at
“In July 2023, the Committee reported that the Department for Transport (DfT) does not know what it is trying to achieve with the High Speed 2 station at Euston, despite spending over eight years planning and designing it. Construction work at Euston was paused for two years in March 2023. The Committee has called on the DfT to use the pause to finally establish the design and expectations for the station against what it is willing to spend, while noting that the costs and impacts of the pause for the local community and small businesses remain unknown. The Committee will question senior officials at the DfT and HS2 Ltd. on progress on the project since its April 2023 evidence session and leadership changes at HS2 following the Committee’s report. Dame Meg Hillier MP, Chair of the Public Accounts Committee, said: “The HS2 Euston project is floundering. This is a multi-billion pound scheme which has already caused major disruption to the local community put on pause. The pause, ostensibly to save money, is not cost free – mothballing and possible compensation for businesses which have lost work will all need to be added to the HS2 tally. The Government must now be clear what it is trying to achieve with this new station, and how it will benefit the public. “Our report found that a wildly unrealistic budget for HS2 Euston was set in 2020 in the expectation that it would be revised. The Government must demonstrate that that it is not just repeating the same mistakes of unrealistic costings. HS2 Euston has shown us that forging ahead over-optimistically in an unclear direction is clearly not the right approach.” If you have evidence on these issues, please submit it here by 23:59 on Friday 10 November 2023. Please look at the requirements for written evidence submissions and note that the Committee cannot accept material as evidence that is published elsewhere. Please note that the Committee will not be scrutinising policy decisions in relation to HS2 Euston or the HS2 project.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
This Committee has been reporting its concerns on how High Speed 2 (HS2) has been managed for over a decade, but recent events have left us more concerned about the HS2 programme than ever before. The cancellation of the latter stages of the HS2 programme and operating just Phase 1, from London to the West Midlands will achieve poor value for money for the taxpayer, as the Department for Transport (the Department)
acknowledged to us. The Department told us it was still better to complete Phase 1, given the approximately £11 billion of remediation costs (in 2019 prices) that would be incurred if they cancelled the whole programme.
Even before the cancellation of Phases 2a, 2b and East, the costs of HS2 continued to escalate, with HS2 Ltd’s estimated costs for Phase 1 now as high as £57 billion against a budget of £44.6 billion (in 2019 prices). HS2 Ltd estimates that inflation since 2019 will add a further £8 billion to £10 billion to the cost, making a total in current prices of up to £67 billion. Poor cost management indicates a failure of governance and oversight across both HS2 Ltd and the Department. This is of great concern given the scale of the challenge they face in resetting the programme to complete Phase 1 and manage the closedown of the other phases, for example in disposing of land and property no longer needed. We are also highly sceptical that the Department will be able to attract private investment on the scale and speed required to make the London terminus station a success.
Alongside managing changes to the HS2 programme, including the impact on Northern Powerhouse Rail, the Department also has work to do to confirm exactly how the £36 billion redirected from HS2 will be used over the next two decades, and how it will manage this long-term portfolio of projects.
Crucially, the Department does not yet understand how HS2 will operate as a functioning railway following recent changes. It is vital the Department now gets to grips with the programme to complete Phase 1 within the estimated range of 2029 to 2033, with HS2 Ltd aiming for 2030, and maximises what value it can for the taxpayer.
What the government said
The government responded on 2 April 2024.
The government agrees with the Committee's recommendations on benefits, costs, Phase 1 changes, Euston and Network North reporting, but disagrees with the recommendation on reporting a land and property disposal plan alongside the Treasury Minute response.
- On benefits, it agrees and says an updated programme business case will be published in 2024, setting out updated benefits, how delivery will be monitored and updated benefit-cost ratios, with a target implementation date of during 2024.
- On cost control, it agrees and says a plan has been developed with HM Treasury and HS2 Ltd; it will provide an update in forthcoming six-monthly reports to Parliament, with the work on suppliers reported "subject to commercially sensitive details".
- On Euston, it agrees (target dates Summer 2024 and Winter 2024) and says work is "currently underway" on funding packages and financing mechanisms, including "consideration of options" to pay for the Old Oak Common to Euston section.
- On land and property disposal, it disagrees with the recommendation. It says it is "not yet able to share its plan" but will do so by summer 2024, as the programme "will take some time" to set up.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 31 July 2023 to its close on 3 April 2024.
- Oral evidence 16 Nov 2023
- Report 7 Feb 2024
- Government response 2 Apr 2024
- Correspondence 5 letters
What it recommended 3 recommendations · 29 conclusions
2Require Department and HS2 Ltd to implement effective cost controls and oversight for programme
3Require Department and HS2 Ltd to establish revised plans for Phase 1 and organisational needs
4Require Department to develop private investment plans for Euston and decide on tunnelling
5Publish comprehensive plan for HS2 land and property disposal balancing taxpayer and local needs
6Publish reporting plan for Network North projects including timescales and value for money assurance
1HS2 programme repeatedly plagued by escalating costs and lack of transparency
7HS2 Phase 1 alone does not achieve value for money as previously asserted
8Revised HS2 Phase 1 business case requires significant work on costs and benefits
9HS2 programme costs have consistently escalated beyond original budget forecasts.
10Differing cost estimates for HS2 Phase 1 exceed budgets due to inflation and design.
11Department's lowest Phase 1 cost estimate still exceeds allocated budget, requiring additional funding.
12HS2 cost increases driven by inflation, supply chain issues, and poor financial management.
13Cost-plus Main Works Civils contracts are primary driver of HS2 programme cost increases.
14Department outlines new strategy to enhance HS2 Phase 1 cost control and governance.
15HS2 Ltd has streamlined governance and strengthened board for enhanced cost control.
16No final decisions made on HS2 operational train services for Phase 1.
17Cancellation of HS2 Phase 2 impacts Phase 1 design, particularly West Coast Main Line integration.
18Cancellation of HS2 Phase 2 impacts other interdependent projects, lacking business cases.
19HS2 Ltd faces estimated sub-£10 million legal exposure from cancelled Phase 2 contracts.
20HS2 Ltd faces capacity challenges and struggles with recruitment in overheated market.
21Department acknowledges unaffordable Euston station plans, shifts to stripped-back, privately funded development.
22Treasury now supports private sector funding for Euston station and wider development.
23Euston remains HS2 London terminus ambition, but its delivery date remains uncertain.
24Delaying Euston tunnel contracts risks significant additional costs and taxpayer burden.
25Realising Euston's private sector funding requires greater certainty and a coherent market proposition.
26HS2 Ltd spent £634 million acquiring land for cancelled Phase 2 sections.
27Releasing acquired Phase 2 land faces complex and time-consuming 'Crichel Down' rules.
28Balancing fairness to taxpayers and affected individuals crucial for Phase 2 land disposal.
29Process for returning unused HS2 Phase 1 land remains painfully slow
30£36 billion HS2 savings to be reinvested across UK regions
31Network North projects funded by HS2 savings require individual business case approvals
32No comprehensive profiled list of projects funded by redirected HS2 savings exists
Evidence
Oral evidence sessions 1
- 16 Nov 2023HS2 and Euston4 witnesses, listed belowparliament.uk ↗
Who gave evidence 4 witnesses
- Alan OverDirector General, Major Rail Projects Group, Senior Responsible Owner for High Speed 2 Programme, Department for Transport
- Dame Bernadette Kelly DCBPermanent Secretary, Department for Transport
- Dr Nick BissonIntegrated Rail Plan and Northern Powerhouse Rail, Department for Transport
- Sir Jon Thompson KCBExecutive Chair, High Speed Two (HS2) Ltd
Correspondence 5 letters
- 10 Jan 2024Correspondence from Sir Jon Thompson, Executive Chair, High Speed Two (HS2) Ltd, re Public Accounts Committee HS2 and Euston: Recall (16th November) follow up, dated 11 December 2023
- 10 Jan 2024Correspondence from Dame Bernadette Kelly DCB, Permanent Secretary, Department for Transport, re Follow-up to the session of Thursday 16 November 2023 - HS2 and Euston, dated 8 December 2023
- 16 Nov 2023Correspondence from Dame Bernadette Kelly DCB, Permanent Secretary, Department for Transport, re Accounting Officer Assessment of Decision to complete Phase 1 of HS2 – Background and Overview, dated 14 November 2023
- 16 Nov 2023Correspondence from Dame Bernadette Kelly DCB, Permanent Secretary, Department for Transport, re Accounting Officer Assessment of Decision to complete Phase 1 of HS2 – revision to BCR Range, dated 14 November 2023
- 16 Nov 2023Correspondence from Dame Bernadette Kelly DCB, Permanent Secretary, Department for Transport, re Accounting Officer Assessment of Decision to complete Phase 1 of HS2, dated 14 November 2023