The condition of school buildings
Closed
What the inquiry looked at
“In March 2022 the Public Accounts Committee reported on the risks to schools’ financial sustainability , including wide variations in the condition of individual schools and their funding. The school estate in England comprises some 22,000 schools, with the majority overseen by the responsible body in control of the school, usually the relevant local authority or academy trust. The Department for Education (DfE) provides capital funding of around £5 billion each year and works with responsible bodies to help maintain and improve the condition of school buildings. Based on a National Audit Office investigation into the condition of school buildings in England the Committee will question senior officials at the Department for Education on whether: - they have a good understanding of the condition of school buildings; - they have appropriate arrangements in place to allocate funding for school buildings in line with need; and - whether they can give assurance that funding for school buildings is being used efficiently and effectively. If you have evidence on these issues please submit it here by 23:59 on Thursday 6 July. Please look at the requirements for written evidence submissions and note that the Committee cannot accept material as evidence that is published elsewhere.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The Department for Education (DfE) provides funding and support to those who manage the school estate, so that children can learn in safe and well-maintained buildings, maximising their chances of success. Given this, it is extremely concerning that DfE does not have a good enough understanding of safety risks across school buildings for it to fully quantify and mitigate these risks and keep children and staff in schools safe.
This includes an understanding of how reinforced autoclaved aerated concrete (RAAC), which may lead to a sudden building collapse, has been used alongside asbestos, which we have raised as a concern for several years.
Given how crucial it is to get safety matters right, it is shocking and disappointing that, at the time of our evidence session in September 2023, DfE could not provide basic information on, for example, how many specialist surveys to identify RAAC were outstanding, or how many temporary classrooms had been provided to schools affected by RAAC. Nor could it provide a clear and firm commitment on when RAAC issues would be addressed.
The emerging issues with RAAC add further weight to demonstrating the impact that short-term thinking and decision-making can have on long-term value for money.
The school estate has deteriorated to the point where an alarming 700,000 pupils are learning in a school that needs major rebuilding or refurbishment, impacting their learning experiences and ultimately limiting their educational achievements. All pupils have an equal right to learn in safe and well-maintained buildings, but their chances of doing so are too often affected by factors such as their geographical location and the capability of those responsible for managing their school buildings.
It is encouraging to see that, alongside its annual maintenance and repair funding of £1.8 billion in 2022–23, DfE has packages of work to help address some of the most serious building issues, including a plan for refurbishment and rebuilding in 500 schools over 10 years. However, this work only touches the surface of problems across the school estate. DfE must do more to mitigate critical safety and value for money concerns, and then demonstrate that it has clear plans to address the scale of challenge and uncertainty it faces in the coming years.
What the government said
The government responded on 8 March 2024. The deadline was 19 January 2024.
The government states that it "agrees with the Committee's recommendation" in each of the ten areas, marking some as "Recommendation implemented" and others with target implementation dates.
- On RAAC, the department says its identification programme is complete and a final list of confirmed cases was published on 8 February 2024, with 234 education settings affected and a small number of further checks under way.
- The government says it "has committed to remove RAAC from the school and college estate for good", funded through grants or the School Rebuilding Programme.
- On asbestos, it gives a target implementation date of December 2026, saying the Condition Data Collection 2 programme is "expected to be completed in 2026" with a final set of asbestos data then available.
- Other target dates include September 2024 for the fire safety value for money review, with a response in any new Fire Safety (BB100) guidance "expected to be published later in 2024", and December 2024 for School Rebuilding Programme assurance.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 24 May 2023 to its close on 8 March 2024. The dashed mark is the deadline Parliament records for the government's response.
- Oral evidence 13 Jul 2023
- Report 19 Nov 2023
- Government response 8 Mar 2024
- Correspondence 2 letters
What it recommended 5 recommendations · 37 conclusions
2Clarify DfE's school estate safety risk appetite and publish its RAAC eradication plan.
3Re-examine DfE's funding process for temporary RAAC mitigation, ensuring accessibility and value for money.
4Require DfE to provide a detailed assessment of the RAAC problem, plan, and associated costs.
5Require DfE to demonstrate a full picture of asbestos and adequate management plans in all schools.
6Develop a support package and good practice guidance for schools in poor condition.
7Establish a strategy for timely school repairs and reconsider fire safety value for money analysis.
8Require DfE to provide assurance on School Rebuilding Programme timetable, costs, and scenario planning.
9Review DfE guidance, support, and funding to improve school building condition and estate management.
10Consider supporting local authorities to ensure high-quality places when reducing local school provision.
1DfE significantly changed safety guidance for RAAC-affected schools in August 2023.
11Schools awaiting specialist surveys for suspected RAAC face prolonged uncertainty regarding building safety.
12DfE lacks proactive funding commitments or eradication targets for RAAC in schools.
13DfE unable to report total number of temporary RAAC classrooms supplied to schools
14DfE's central temporary classroom contracts proving ineffective for some responsible bodies
15DfE outlining reimbursement process for schools' RAAC-related costs and surveys
16Caseworker support for RAAC-affected schools facing operational effectiveness issues
17DfE lacks specific figures on RAAC impact, hindering timely public transparency
18Number of RAAC-affected educational settings continues to increase across the estate
19DfE expects RAAC issues to resolve within weeks, with variable timeframes for complex cases
20DfE previously agreed to urgently chase non-responsive schools on asbestos survey
21DfE remains unsighted on asbestos status in 4.4% of schools nationwide
22Asbestos risk higher in schools due to shared occupancy; oversight concerns raised
23DfE policy for asbestos management in schools risks hidden dangers during RAAC works
24Teacher deaths from asbestos-related mesothelioma are rising, linked to historic exposure levels
25Poor school building conditions severely undermine pupil attainment and teacher retention
26700,000 pupils learning in schools requiring major rebuilding, but only 500 will be addressed
27Nearly 6,000 temporary and mobile blocks included in the school estate building count
28Significant number of school building components in unsatisfactory condition (grades C and D)
29DfE prioritises immediate action and funding for urgent school building safety issues
30HM Treasury funds significantly fewer school rebuilds than DfE recommended annually
31Funding constraints prevent rebuilding non-hazardous schools, despite better long-term value for money
32New and refurbished schools continue to lack sprinkler systems despite safety expectations
33School Rebuilding Programme severely behind schedule on contracts awarded and projects completed.
34Inflationary pressures significantly delayed School Rebuilding Programme contract agreements and project delivery.
35External factors like inflation and supply chain issues significantly complicate project cost and timelines.
36Significant geographical disparities persist in school building conditions across England, impacting deprived areas.
37Many high-need schools failed to apply for rebuilding funds due to capacity or awareness issues.
38Direct funding for multi-academy trusts to dioceses could improve strategic estate management.
39Smaller local authorities currently lack specific DfE capital support for school estate management.
40Decisions on school closures and building conditions lack sufficient coordination across authorities.
41DfE regional directors currently play limited role in local school closure decisions.
42DfE considers future pupil numbers when selecting schools for rebuilding programmes.
Evidence
Oral evidence sessions 1
- 13 Jul 2023The condition of school buildings3 witnesses, listed belowparliament.uk ↗
Who gave evidence 3 witnesses
- Jane BalderstoneCapital Delivery, Department for Education
- Jane CunliffeChief Operating Officer, Operations and Infrastructure Group, Department for Education
- Susan Acland-HoodPermanent Secretary, The Department for Education
Correspondence 2 letters
- 26 Feb 2024Correspondence from Susan Acland-Hood, Permanent Secretary, Department for Education, re The condition of school buildings, dated 16 February 2024
- 19 Sep 2023Correspondence from Susan Acland-Hood, Permanent Secretary, Department for Education, re Condition of School Buildings, dated 7 September 2023