Green homes grant voucher programme
Closed
What the inquiry looked at
“In July 2020, the government allocated £3 billion to reduce carbon emissions from current heating systems in 600,000 homes and public buildings. This included £1.5 billion to help property owners cover the cost of installing energy efficient measures, such as insulation or renewable heat systems. The Department for Business, Energy and Industrial Strategy (the Department) contracted with a digital services company to develop an IT platform so people could apply for Green Homes Grant vouchers. In Spring 2021 it was reported that only a small proportion of the vouchers had been allocated. The Committee will question senior officials at BEIS on the Green Home Grant’s design and objectives ; the procurement of the contract for the Green Home Grant IT platform; and how the Green Home Grant has been managed and what has been achieved to date. If you have evidence on these questions, please submit it here by 6pm on Thursday 16 September 2021.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The Green Homes Grant Voucher Scheme (the Scheme) underperformed badly, upgrading around 47,500 homes compared to the 600,000 originally envisaged, delivering a small fraction of the expected jobs and accounting for just £314 million out of the original £1.5 billion budget. Administration costs are likely to amount to more than £1,000 per home upgraded, totalling just over £50 million in all.
We are not convinced that the Department has fully acknowledged the scale of its failures with this scheme. The failure to deliver this scheme continues government’s troubled record of energy efficiency initiatives and risks damaging the Department’s future efforts to harness both consumer and industry action to deliver Government’s net zero commitments. The Scheme was implemented as an urgent response to the COVID-19 crisis, aiming to support jobs at a time of significant risk for the economy while also reducing carbon emissions from homes. Despite these commendable intentions, the 12-week timescale to implement the Scheme was unrealistic and imposed constraints on its design and implementation. The Department proceeded with the Scheme despite its own Projects and Investment Committee rejecting its full business case. The Department should have considered halting or delaying the Scheme given evidence that preparations were not sufficiently progressed.
What resulted was a scheme with poor design and troubled implementation - the Department did not consult meaningfully enough with industry and consumers, leading to an overly complex scheme design with poor customer experiences and a lower uptake than envisaged. By August 2021, 52% of homeowners’ voucher applications were rejected or withdrawn, and 46% of installer applications failed. The Scheme also struggled due to the failure of its scheme administration contractor, ICF Consulting Services Ltd (ICF), to successfully implement the required digital voucher application system. The Department acknowledged that it should have had a better technical understanding of the preferred bidder’s proposed solution, and that, had it done so, it may have had sufficient warning that ICF would be unable to implement the required system successfully. The Scheme’s primary aim was to support jobs, however, the Scheme’s design and duration limited its impact on employment, and its abrupt closure may have in fact led to redundancies. Government needs to stick to a stable, long-term plan, to renew the confidence of industry and consumers in taking the actions needed to realise Government’s net zero ambitions.
It is a matter of concern that green homes schemes have repeatedly been short term and have underdelivered on over optimistic promises on green targets and job creation. The department needs to consider carefully how to approach such schemes in future.
What the government said
The government responded on 1 March 2022. The deadline was 1 February 2022.
The government states that it agrees with each of the Committee's six recommendations on the Green Homes Grant Voucher Scheme, giving target implementation dates for some and describing others as already implemented.
- On regaining consumer and industry confidence, the government agrees and says the BEIS Outcome Delivery Plan "will include trajectories for heat pump deployment and the improvement in EPC ratings for homes", showing what has been achieved and what remains to be done.
- On the scheme's implementation timescale, the government agrees, but explains that a ministerial direction "was not considered to be required in this case", and says an external review will consider the department's Tier 1 Governance structures in 2022.
- On scheme design, the government agrees and recognises that the shortened timescale affected engagement with consumers and installers. It says that for each proposed policy development it "aims to undertake robust public consultation".
- On the Boiler Upgrade Scheme, the government agrees (target implementation date: Winter 2023) and says it will establish a Green Jobs Delivery Group, a commitment in the Net Zero Strategy.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 6 September 2021 to its close on 1 March 2022. The dashed mark is the deadline Parliament records for the government's response.
- Oral evidence 20 Sep 2021
- Report 1 Dec 2021
- Government response 1 Mar 2022
What it recommended 10 recommendations · 19 conclusions
2Despite clear warning signs, the Department proceeded with an unrealistic implementation timescale for the Green...
3The Scheme’s design was overly complex and did not sufficiently address the needs of consumers...
4The creation of jobs was a priority for the Scheme, but the Department failed to...
5The Department appointed a contractor without properly understanding whether it could deliver.
6The Department has persistently failed to learn lessons from previous energy efficiency schemes.
1On the basis of a report by the Comptroller and Auditor General, we took evidence...
7These issues were further exacerbated by underperformance of the Scheme Administrator (ICF Consulting Services Ltd,...
8Despite spending a fraction of what was intended on vouchers, the Department expects it will...
9The Scheme encouraged the installation of primary measures which would produce the greatest carbon savings,...
10Industry associations stated that the short lead up time, and the Scheme’s six-month window was...
11Requiring PAS and MCS certification, alongside Trustmark registration, was intended to protect homeowners from poor...
12Whilst the Department extended the scheme’s duration by 12 months in November 2020, it later...
13The Department acknowledged that the impact on many installers was less than ideal, however, it...
14These factors point to the Scheme’s underperformance on jobs; the Department initially anticipated the scheme...
15Considering these difficulties, it comes as no surprise that industry criticised the design of the...
16In our recent evidence session on Achieving Net Zero Strategy, the Department set out its...
17In 2016 our predecessors on the Committee identified similar problems when they examined the Green...
18The Department argued that it had learned lessons from previous schemes.50 The design of the...
19We are likewise concerned that the Department will fail to learn from this scheme.
20The Department’s previous energy efficiency schemes for private housing have operated in different ways, and...
21The Chancellor announced the Green Homes Grant Voucher Scheme (the Scheme) on the 8 July...
22The Department told us that it had a high-risk appetite in getting the scheme up...
23This rushed timescale meant that the Department undertook limited stakeholder engagement and restricted its options...
24In a previous Committee report Home Energy Efficiency Measures, our predecessors highlighted that Government “should...
25Under Managing Public Money principles, Accounting Officers should consider the regularity, propriety, and feasibility of...
26Due to the 12-week timescale for implementing the Scheme, the Department had limited time to...
27As a result, the Department awarded the contract to ICF, accepting it’s accelerated timetable for...
28Despite the Department appointing a contractor which could not deliver the system, the Department felt...
29The Department stated that at the time of the procurement, it appeared that ICF had...
Evidence
Oral evidence sessions 1
- 20 Sep 2021Green homes grant voucher programme3 witnesses, listed belowparliament.uk ↗
Who gave evidence 3 witnesses
- Ben GoldingDirector, Clean Power 2030
- Sarah MunbyPermanent Secretary, Department for Business, Energy and Industrial Strategy
- Selvin BrownDirector for Net Zero Buildings: Domestic, Department for Energy Security and Net Zero