Progress on smart meter roll-out
Closed
What the inquiry looked at
“Plans to install energy saving smart meters in every UK home and business by 2020 are in danger of veering off-track and could prove to be a costly failure because the project has not been driven forward effectively, the Committee has warned.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
Smart meters, which allow energy suppliers to get remote electricity and gas readings from households and businesses using mobile phone-type signals and wireless technologies, should benefit customers through savings from energy usage and efficiency. In 2013 we first looked at the Government’s programme to roll-out smart meters to 100% of UK homes and businesses by 2020. This inquiry reviewed the progress of the roll-out and we have been disappointed by the ongoing policy delivery challenges which the Government has failed to resolve:
• Technical communication problems with multiple occupancy and tall buildings which should have been resolved by now • Compatibility problems between different suppliers and different meters • A slow start to full engagement with the public on meter installation and long-term use • A delay by the Government-appointed communications infrastructure company which has further set back confidence in the programme • A reluctance to improve transparency by publishing the Major Project Authority’s assessments on the smart meter programme These policy problems are symptomatic of a national programme that the Government has left largely to suppliers and failed to drive forward effectively. Consequently, we do not believe that near-universal smart meter roll-out will be achieved by 2020. Without significant and immediate changes to the present policy, the programme runs the risk of falling far short of expectations. At worst it could prove to be a costly failure. The Government must urgently seek industry-wide solutions to the technical challenges that remain. It should also give serious consideration to whether it is possible to reduce costs to consumers by streamlining the roll-out of smart meters, perhaps through more active participation of network companies. For the Government to succeed with this nationwide project, it must now grip the reins and take a more active role to support the industry-led roll-out. Getting it right will eventually cut energy usage and bills for 30 million homes and businesses in the UK. Getting it wrong risks embarrassment for the Government through public disengagement with a flagship energy policy and a costly missed opportunity.
What the government said
The government responded on 26 March 2015.
The Government welcomes the Committee's report and says the roll-out is "making good progress", agreeing with some recommendations (such as keeping the In-Home Display offer) and disagreeing with others.
- It agrees that the obligation on suppliers to offer In-Home Displays to all domestic customers "should be retained", but disagrees that Government should identify a smart app, saying industry should innovate.
- It disagrees with the recommendations to relax SMETS1 requirements, publish a plan on an installer skills shortage, and assess a greater role for network operators, stating that the energy supplier-led roll-out is "the right approach".
- On the DCC delay, it "notes" the recommendation and says the DCC expects to deliver operational services from April 2016, with up to six months of contingency that will be "strictly governed".
- It commits to publish a consultation at the end of March 2015 on HAN solutions, and to consult on enrolling SMETS1 meters into the DCC.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 15 September 2014 to 26 March 2015.
- Oral evidence 2 sessions
- Report 7 Mar 2015
- Government response 26 Mar 2015
- Correspondence 2 letters
What it recommended 6 recommendations · 4 conclusions
1We first identified the technical challenge of multiple occupancy and tall buildings for smart meters...
2As interoperability is at the heart of the Government’s framework on smart meters, the Government...
3Technology has moved on since it was made obligatory for suppliers to offer In- Home...
4We are very concerned about the impact the DCC delay will have on customers during...
5Despite the Minister’s confidence, we are concerned that the current shortage of installation engineers makes...
6The existing roll-out arrangements may now be too advanced for a transfer of responsibility for...
7It is clear that helping 28 million households, including vulnerable customers, to understand the benefits...
8We believe that the potential benefits of Time of Use tariffs working in conjunction with...
9While progress has been made since we first looked at the Government’s smart meter programme...
10Without significant and immediate change to the present policy, the programme runs the risk of...
Evidence
Oral evidence sessions 2
- 16 Dec 2014No witnesses recordedparliament.uk ↗
- 2 Dec 2014No witnesses recordedparliament.uk ↗