Smart meter roll-out
Closed
What the inquiry looked at
“Smart meters are due to be rolled out to homes and businesses across the UK between 2014 and 2019, with the costs of roll-out being passed on to consumers in their bills. DECC estimates that smart metering will bring a net benefit of £6.7 billion. However, concerns have been raised about aspects of roll-out, including cost, timescale, data protection, privacy and the extent to which consumers will really benefit. This inquiry explores DECC’s preparations for roll-out and some of the concerns that have been raised. Evidence session 1, 23 April 2013: transcript (PDF 212 KB) | video Evidence session 2, 14 May 2013: transcript (PDF 169 KB) | video Evidence session 3, 14 May 2013: transcript (PDF 163 KB) | video Evidence session 4, 4 June 2013: transcript (PDF 171 KB) | video”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
Smart metering has the potential to bring wide benefits to consumers, energy suppliers and our energy infrastructure, and we welcome this investment in the UK's energy system.
Mass roll-out is due to take place between 2015 and 2020, and will see energy companies install approximately 53 million smart meters in homes and small businesses. DECC estimates that roll-out will cost around £12.1 billion and deliver benefits of £18.8 billion.
Projected benefits include accurate billing, easier switching, energy and bill savings for consumers, and operational savings for energy suppliers. Smart meters could also facilitate the creation of a smart grid that will help to balance peaks and troughs in electricity supply and demand, but the extent to which they will do this is unclear. Not enough has been done to quantify the benefits of a smart grid, and greater transparency is needed for the true costs and benefits of roll-out to be assessed.
The cost of roll-out will ultimately be paid for by consumers in their bills. There is a clear risk that the £6.7 billion net benefit projected by DECC may not be achieved if costs spiral or if consumers do not realise the expected energy and bill savings. DECC, Ofgem and some energy suppliers have suggested that competition in the market will ensure that costs are kept down and that benefits are passed on to consumers through lower energy prices, but we are not convinced that the energy market is sufficiently competitive to ensure this is the case. Until there is strong evidence that it is, DECC and Ofgem must retain responsibility for ensuring that costs do not spiral and that benefits are passed on. Energy companies should co-ordinate installation activity to ensure costs are contained and the benefits of roll-out are maximised.
Consumer acceptance of and engagement with smart metering is crucial to the success of roll-out. The extent to which consumers will benefit directly through energy and bill savings will depend largely on how they engage with smart meters. The provision of accurate, real-time consumption and billing data via the in-home display (IHD) is central to helping consumers to understand, reduce and alter their energy consumption habits. If households and small businesses are to be given the best chance of achieving savings, they should be offered free IHDs, which must provide accurate, real-time data.
It is important that people have a positive experience when they receive a smart meter and that the information they receive when it is installed will help them to get the most out of it.
We welcome the action that DECC and Ofgem have taken to ensure that consumers will receive advice about smart meters and energy efficiency when the meters are installed.
However, the benefits of receiving this information may be lost or significantly reduced if gaps in communications coverage mean that some smart meters have to be operated in “dumb” mode for some time after installation. It would be preferable to wait until communications issues are resolved before installing smart meters so that consumers can access the benefits of smart meters as soon as they are installed. Likewise, suppliers should not be pressed to roll-out earlier versions of smart meters now if they prefer to wait for a version that fully meets the technical specifications in order to give their customers a better experience.
What the government said
4th Report - Smart meter roll-out - Volume II (Volume II: additional written evidence)
No government response is linked to this report.
4th Report - Smart meter roll-out - Volume I (Volume I: Report, together with formal minutes, oral and written evidence)
The government responded on 14 October 2013.
The Government welcomes the Committee's report and responds recommendation by recommendation, agreeing with some, noting others, and declining one amendment to the Installation Code of Practice licence conditions.
- On the roll-out timetable, the Government "agrees with the Committee's recommendation" and says all parties are committed to starting mass roll-out in autumn 2015 and completing it by the end of 2020, with progress "closely monitored".
- On in-home displays for small and micro-businesses, the Government concluded it "would not be of overall economic benefit to mandate the offer of IHDs free of charge"; such customers will be able to purchase them.
- On the Installation Code of Practice, it does "not think it is appropriate" to amend the licence conditions, but DECC "will bring the Committee's view to the attention of the Code of Practice Board".
- On consumer engagement, the Central Delivery Body must now produce its first Consumer Engagement Plan, Performance Management Framework and Annual Budget by the end of 2013, rather than March 2014.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 20 December 2012 to 5 November 2013.
- Report 2 reports
- Government response 14 Oct 2013
- Correspondence 4 letters
What it recommended 5 recommendations · 13 conclusions
1Ofgem must be prepared to strengthen the requirements on suppliers to provide accurate bills if...
2We recommend that suppliers work together to achieve efficiency savings during roll- out.
3Smart metering has the potential to bring wide benefits to our energy infrastructure and to...
4There is a clear risk that the £6.7 billion net benefit projected by DECC may...
5If consumers do not believe that they are benefiting significantly from roll-out, they could rightly...
6We welcome DECC’s recent announcement that the dates for mass roll-out are being pushed back...
7We note the concerns about the centralised DCC model proposed by DECC.
8We are concerned about WAN and HAN coverage in the short to medium term, and...
9We see a fundamental inconsistency between DECC’s position that there is little difference in functionality...
10SMETS 2 meters are more likely to provide customers with a satisfactory smart metering experience...
11The provision of real-time consumption and billing data is central to consumers’ ability to manage...
12We see a fundamental incongruity in DECC and Ofgem’s position that on the one hand...
13We welcome the action that DECC is taking to respond to public concerns about health,...
14We note Ofgem’s reasons for not wanting to give detailed guidance at this stage regarding...
15We agree with Ofgem that it may be reasonable, once roll-out is complete, to charge...
16The provision of good-quality information and support regarding smart meter usage and energy efficiency will...
17Public engagement should begin before the start of mass roll-out.
18Energy companies still have a long way to go in putting right past failures and...
Correspondence 4 letters
- 5 Nov 2013Letter from Baroness Verma to the Chair of the Committee, 29 October 2013To committee
- 5 Nov 2013Letter from Baroness Verma to the Chair of the Committee, 29 October 2013To committee
- 14 Oct 2013Letter from the Chair of the Committee to Baroness Verma, 11 October 2013To committee
- 14 Oct 2013Letter from the Chair of the Committee to Baroness Verma, 11 October 2013To committee