Paragraph: 91
The planning consent process has created a queue of renewable generation projects in Wales to...
Conclusion
The planning consent process has created a queue of renewable generation projects in Wales to which grid capacity has been reserved before planning permission has been granted.
Paragraph Reference:
91
Government Response
A response document is linked to this report, dated 24 January 2023. Response attribution to this conclusion has not been verified. Read the response document ↗