Select committee: Scottish Affairs Committee

Conclusion 48

Fourth Report - Defence in Scotland: military shipbuilding Published 27 Jan 2023 Addressed to Scotland Office
Conclusion (the committee's words)
Representatives from the shipbuilding industry told us that having sight of upcoming shipbuilding projects over the coming decades was helpful, but that it was less clear how this translated into a drumbeat of work for shipyards. Ian Waddell of the Confederation of Shipbuilding and Engineering Unions told us: My frustration with this is that all the pieces of the jigsaw are on the table in front of us, and it would not take too much to connect them to make a proper picture. We have the 30-year pipeline of work, which we have been campaigning for, for a long time. Having that visibility of all Government- owned or operated vessels is a big step forward. […] The missing link is to take that pipeline of work and turn it into a drumbeat of work for UK yards.82

From: Scottish Affairs Committee, Fourth Report - Defence in Scotland: military shipbuilding (HC 1096), 27 January 2023

Government response

The government responded to the whole report on 6 April 2023 (deadline 27 March 2023).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The MOD disagrees with the Committee's first conclusion and its conclusion on a potential Scottish workstream gap, while welcoming recognition of export success and the National Shipbuilding Office's Edinburgh presence and setting out its position on the pipeline, skills and SMEs.

  • On the Fleet Solid Support contract, the MOD says the decision to award it to Team Resolute "did not prioritise short-term savings" and followed "a fair and open competition". It says it does not disclose details of losing bids, so it cannot say why the Team UK bid was non-compliant.
  • The MOD "does not agree" that the award creates a potential gap in the workstream for the Scottish warship industry. It cites Type 31 construction continuing until 2028 and Type 26 construction "expected to continue into the mid-2030s".
  • On the pipeline, the MOD says it is "subject to change" as it spans 30 years, but the National Shipbuilding Office "has committed to updating the shipbuilding pipeline at each multi-year Spending Review". For Type 32 frigates, the procurement route is "yet to be determined".
  • On annual Type 26 updates to Parliament, the MOD "will consider its request". On skills, the UK Shipbuilding Skills Taskforce "intends to publish a report of recommended actions in autumn 2023", and its Chair "would be pleased to meet with the Committee" afterwards.

Read the government's response ↗ Report an error