Conclusion (the committee's words)
We recognise there is a mix of evidence on the role hydrogen can play in the decarbonisation of domestic heating and there is still a substantial amount of work being done that will determine its eventual use. However, in the meantime, the evidence in favour of mandating hydrogen-ready boilers in all suitable properties at the earliest opportunity is convincing, no matter what decision is eventually made on the blend of hydrogen in the system, or whether the system becomes a 100% hydrogen gas network. Assurances from the largest four boiler manufacturers indicate that hydrogen-ready boilers will be the same price as standard boilers, removing a key obstacle in rolling them out across UK households. It means millions more properties would be ready and able to switch to hydrogen sooner rather than later and with lower conversion costs, if required, should the UK Government opt for a low carbon hydrogen-based gas network.

From: Scottish Affairs Committee, Sixth Report - Hydrogen and carbon capture in Scotland (HC 83), paragraph 116, 10 March 2023

Government response

The government responded to the whole report on 8 June 2023 (deadline 1 June 2023).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government agrees that the UK and Scottish Governments have clear hydrogen strategies and that close joint working matters on exports, while setting out its own delivery plans and declining to comment on recommendations addressed to the Scottish Government on devolved matters.

  • On targets, the government calls up to 10GW of low carbon hydrogen by 2030, "subject to affordability and value for money", "a stretching but deliverable ambition". It says the Scottish 5GW ambition "does not have a formal relationship" to the UK-wide figure.
  • It commits to a hydrogen production delivery roadmap, "to be published by the end of the year", and plans a second electrolytic allocation round "later in 2023".
  • On carbon capture, it describes CCUS as "a priority" and says it intends to "provide an update on next steps for Track-2 in the summer". It reports over £40m of development funding allocated to the Scottish cluster.
  • On hydrogen storage, it commits to designing a storage business model "by 2025". On hydrogen-ready boilers, it is analysing consultation responses on a 2026 requirement and "will issue the Government response in due course".