The Government's management of major projects inquiry
Closed
Opened 10 Oct 2018
Closed 10 Oct 2018
1 recommendation
6 conclusions
Public Administration and Constitutional Affairs Committee Inquiry on parliament.uk ↗
Inquiry scope (the committee's words)
The Government’s Major Projects Portfolio currently has 133 projects with a value of £423 billion. This includes high profile infrastructure projects such as Crossrail, HS2 and Hinkley Point but also major Government ICT projects, projects to transform public services, and major defence procurement programmes. In addition, individual departments manage numerous capital projects outside the Major Projects Portfolio. The management of such projects has been criticised, with lack of accountability, poor early planning and limited Government capability amongst the concerns flagged by the National Audit Office. The Public Administration Committee is holding an inquiry into how well such projects are managed by Government. It will consider whether criticisms are justified, what steps have been taken to address them, and where more needs to be done.
Where it stands
The inquiry is closed, opened 10 October 2018.
The committee has published 1 report, most recently 3rd Report - The Government’s Management of Major Projects: An Interim Report on 5 November 2019.
The government's response
No government response is linked to this report.
Recommendations and conclusions
- Recommendation 1Recommendation
- Conclusion 2Conclusion
- Conclusion 3Conclusion
Reports
- 3rd Report - The Government’s Management of Major Projects: An Interim Report5 November 2019 · 7 items
Evidence
- 5 oral evidence sessionsLatest 9 July 2019
Recent activity
- 3rd Report - The Government’s Management of Major Projects: An Interim Report5 November 2019, Report published
- Oral evidence session9 July 2019, Oral evidence
- Oral evidence session25 June 2019, Oral evidence
Recommendations and conclusions 7 shown
The decision to hold an early General Election has curtailed our inquiry into this important topic whilst we were still gathering evidence and before we have been able to consider our conclusions and recommendations. By necessity, this report can only highlight a few of the main issues that have emerged in the evidence we have received to date and some of our initial impressions. We recommend that our successor Committee returns to this important matter at the earliest opportunity.
Conclusion 2
Concluded (the committee's words)When the IPA was established through the merger of the IUK and the MPA, the Public Accounts Committee (PAC) expressed concern that the MPA’s assurance role could be compromised in a merger with IUK, a delivery body the work of which the MPA had been charged with evaluating. We found no evidence to suggest that this has been the case. Should our successor Committee return to this area, an aspect it could usefully consider in more detail is the way in which the IPA interacts with the individual Government departments.
Conclusion 3
Concluded (the committee's words)Improvements in the Civil Service’s project delivery capability have been a priority of government over the last decade and we welcome this investment in a greater skills base for the delivery of major projects. Due to the curtailment of this inquiry, it is difficult for the Committee to know whether this increased training has translated into better delivery of projects and suggest that any inquiry in this area by a successor Committee should look at this.
Conclusion 4
Concluded (the committee's words)Major projects often last many years and it is inevitable that there will be a turnover of the staff involved. Indeed, in some instances, the expertise needed to progress a project will change as it develops, and it is important that this is reflected in the turnover of staff. However, this differs from the rapid rotation of staff between posts. It can be mitigated through ensuring a steady pipeline of replacements and good knowledge management but its impact will still be detrimental. The Government is evidently conscious of the issue of churn on its major projects and steps taken to reduce the turnover of project SROs are to be welcomed. However, churn is an issue throughout the Civil Service and not only at SRO level. There is also a need to consider what conflicts of interest can arise as a result of this churn. The Government is introducing measures to combat it. It is too early to tell whether these have been successful, and it is something our successor Committee could return to.
Conclusion 5
Concluded (the committee's words)Robust pre-approval scrutiny of project business cases is essential. The Government has acknowledged that and there is a comprehensive system of pre-commencement scrutiny now in place. It seems, however, that political imperatives can subvert this 16 The Government’s Management of Major Projects: An Interim Report scrutiny. It is entirely appropriate for Ministers to initiate projects. But if political pressure is sufficient to override this early scrutiny process, this will significantly impact on the successful deliver of major projects.
Conclusion 6
Concluded (the committee's words)We have been critical of the transactional approach the Government tends to adopt in its commercial relationships, at the expense of the quality of personal relationships and trust between contracting parties. An exclusive focus on minimising costs and aggressively attempting to offload risk has neither yielded value for money for taxpayers nor resulted in genuine risk mitigation. There are clearly benefits to a more collaborative approach. However, the circumstances under which this can take place and those where the benefits of a more conventional, transactional approach might be more appropriate are not yet clear to us. This is an issue that, should our successor Committee return to the subject of major projects, it could usefully inquire further.
Conclusion 7
Concluded (the committee's words)The difficulty of accurately forecasting the benefits of a project is clear. It can also be difficult to assess whether they have actually achieved what they were designed to achieve. Nonetheless, whilst there is considerable attention paid to improving project management, major projects are not an end in themselves but exist to achieve public policy goals. Robust ex ante scrutiny of the link between projects and the needs that they are supposed to address, and proper post hoc evaluation of whether they have done so, cannot be overlooked in the focus on improving project delivery.
Reports
3rd Report - The Government’s Management of Major Projects: An Interim Report
- HC No.
- HC 303
- Published
- 5 Nov 2019
- Items
- 7
- Government response
- No government response is linked to this report.
Oral evidence sessions
On smaller screens, scroll horizontally to read every column. Keyboard users can focus the table region and use the arrow keys.
| Date | Session and witnesses | Source |
|---|---|---|
| 9 Jul 2019 |
Oral evidence session
No witnesses recorded
|
View ↗ |
| 25 Jun 2019 |
Oral evidence session
No witnesses recorded
|
View ↗ |
| 11 Jun 2019 |
Oral evidence session
No witnesses recorded
|
View ↗ |
| 26 Nov 2018 |
Oral evidence session
No witnesses recorded
|
View ↗ |
| 6 Nov 2018 |
Oral evidence session
No witnesses recorded
|
View ↗ |