Select committee: International Development Committee

Third Report - The Newton Fund review: report of the Sub-Committee on the work of ICAI

HC 260 Published 15 June 2020

At a glanceGovernment response published 8 September 2020 (deadline 15 August 2020)

The government's response

Summary written by Accountability Index from the government's response. It is not the government's own words.

BEIS states that it "welcomes the scrutiny and insights" of the sub-committee and records "Accept (in progress)" on most of the seven recommendations, "Partially accept" on the formal review of matched funding, and states that some measures depend on the Integrated Review and Spending Review.

  • On value for money and strategy, BEIS records "Accept (in progress)". It recognises the Fund lacked an agreed Theory of Change and written strategy at inception, and says it is "on track" to begin onboarding the Research ODA platform in October.
  • A fund-level strategy will be developed only "after the outcome of the Integrated Review and the Spending Review"; the response says work was delayed by COVID-19.
  • On the matched funding review, the position is "Partially accept". BEIS maintains the Fund does not breach untying commitments, and states that "a formal review at this stage is not considered proportionate or necessary".
  • On publishing information on a single platform, BEIS records "Accept (in progress)" but says RODA "will not replicate a single platform" as published by DfID, and notes that "a one-size-fits-all approach may not be the most appropriate".

Read the government's response ↗ Report an error