Select committee: Housing, Communities and Local Government Committee

Cladding progress of remediation: government response to the Select Committee report

Published 8 September 2020

At a glance

The government's response

This document responds to 2nd Report - Cladding: progress of remediation.

This is the government's response, published 8 September 2020.

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government's response sets out funding, enforcement and legislative measures, mainly through the draft Building Safety Bill, and responds to each of the Committee's recommendations without adopting its calls for a wider fund or fixed deadlines.

  • On funding, the government says public money should not be the only means of remediation, and that building owners "should meet the costs without passing them on to leaseholders wherever possible". The £1bn fund is available in 2020/21 and will incentivise pace.
  • On timing, it sets an expectation that building owners will have works on site for removal of unsafe ACM cladding "by the end of 2020", with completion "by the end of 2021". It does not adopt the Committee's broader targets.
  • On compulsory purchase, it says no local authority has yet seriously considered CPO, but "we have not ruled out any options, including CPOs, if the pace of remediation remains too slow".
  • On historic remedial costs not covered by the £1.6 billion, Michael Wade will "accelerate work on identifying options", with an update "before the final Building Safety Bill is introduced to Parliament".

Read the government's response ↗ Report an error

Sources