Conclusion (the committee's words)
Whilst the UK continues to be committed to phasing out the use of coal for electricity generation by 2024, the Government has recently announced its intention to allow the opening of a new coal mine at Whitehaven in Cumbria. The coking coal to be mined there has limited application in the UK steel industry, and 85% of the coal is planned for export to Europe. The UK Government needs to consider the impact of this decision on its ability to exert international influence with regard to the phasing out of unabated coal.

From: Environmental Audit Committee, 4th Report - Accelerating the transition from fossil fuels and securing energy supplies (HC 109), paragraph 38, 5 January 2023

Government response

The government responded to the whole report on 23 March 2023 (deadline 5 March 2023).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The Government welcomes the Committee's report and responds mainly by pointing to existing schemes, targets and planned consultations, while declining several recommendations, including a tax allowance for renewable generators and ringfencing Energy Profits Levy revenue for energy efficiency.

  • On renewable generators' tax relief, it states it "does not accept this recomsmendation" [sic], citing support through Contracts for Difference. On the Energy Profits Levy, it has "considerable fiscal sustainability concerns" about hypothecating revenue for energy efficiency.
  • On green mortgages, it agrees lenders have "an important role to play" but will publish a response only once policy is "resolved", giving no date. It intends to consult on Energy Performance Certificate and wider buildings framework reforms in 2023.
  • On the North Sea, it considers the Transition Deal targets "sufficiently ambitious" and says it does "not propose reopening this deal for negotiation", though it will monitor progress closely, including whether "further steps may be necessary".
  • On energy efficiency funding, it points to £6.6 billion this Parliament and £6 billion of new funding "from 2025 to 2028". It intends to launch ECO+ in spring 2023, "proposed to be worth £1 billion over three years".