Select committee: Energy Security and Net Zero Committee

Recommendation 13

2nd Report - Gridlock or growth? Avoiding energy planning chaos Published 7 Jul 2025 Addressed to Department for Energy Security and Net Zero
Recommendation (the committee's words)
The Government should review and, if necessary, amend the proposed guidance endorsing the CSNP in paragraphs 3.3.78 to 3.3.80 of EN-1, to make the language more consistent, unambiguous, and more in keeping with current understandings of the intended purpose of the CSNP. This may involve: • reviewing the reference to the CSNP displaying “indicative routes” in paragraph 3.3.80; • removing the reference in paragraph 3.3.79 to a “strategic solution”, an undefined term distinct from “strategic parameters”; and/or • replacing “strategic parameters” with “strategic corridors” until the CSNP is complete and a more precise definition can be adopted. (Recommendation, Paragraph 41)

From: Energy Security and Net Zero Committee, 2nd Report - Gridlock or growth? Avoiding energy planning chaos (HC 868), 7 July 2025

Government response

The government responded to the whole report on 19 November 2025 (deadline 7 September 2025).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government's response says it will provide sufficient time for committee scrutiny of future NPS updates, but it "cannot commit" to a minimum review period, and it sets out amendments and positions on the Committee's wider recommendations.

  • On scrutiny timing, the government "notes" the Committee's concerns and says it will "ensure early liaison with Committee" in future NPS reviews, but cannot commit to a minimum review period.
  • On Critical National Priority infrastructure, it has amended EN-1, replacing "material reduction" with "significant reduction" and adding that exceptional circumstances may "warrant a small reduction in generation capacity and function".
  • On the Centralised Strategic Network Plan, it agrees to remove the term "strategic solution" but will maintain "indicative routes" and "strategic parameters".
  • On distribution infrastructure, it has consulted on removing 132kV wooden poles from the NSIP regime and "will respond in due course"; any threshold change would need secondary legislation.

Read the government's response ↗ Report an error